051-21 - Apply-A-Line, LLC - Contract165A6298
and
CITY OF PORT ORCHARD SMALL WORKS OVER S35K
CONSTRUCTION CONTRACT NO. C051-21
PUBLIC WORKS PROJECT NO. PW2021-012
THIS Agreement is made effective as of the 1 Ith day of May, 2021, by and between
CITY OF PORT ORCHARD, WASHINGTON ("CITY")
216 Prospect Street
Port Orchard, Washington 98366
Contact: Mayor Robert Putaansuu Phone: 360.876.4407 Fax: 360.895.9029
Apply -A -Line, LLC
175Roy RdSWSte C
Pacific. WA 98047-2150
Contact: Mike Susner
Email: sus(alavolvaline.com
for the following Project:
("CONTRACTOR")
Phone: 253.299.1200
2021 City Road Striping Project
The City and Contractor agree as follows:
1. Contract Documents. The Contractor shall complete the Work described in the Contract
Documents for the Project. The following documents are collectively referred to as the
"Contract Documents":
a. This Agreement signed by the City and the Contractor;
b. Division 1 of WSDOT Standard Specifications for Road, Bridge and Municipal
Construction, 2018 edition, together with APWA Supplement (1-99), subject to specific
provisions contained within the Public Works Terms and Conditions;
c. The attached Special Provisions, Plans and Specifications;
d. 2015 International Building Code (IBC) and 2015 Energy Code Compliance;
e. Written change orders or orders for minor changes in the Work issued after execution of
this Agreement;
f. Public Works Terms and Conditions;
g. Insurance and Bonding Requirements;
City of Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Pagel of 23
Rev 5/l/2020
h. The Invitation to Bid, and bid proposal submitted by the Contractor, except when
inconsistent with Contract Documents a-g; and
i. City of Port Orchard Development Guidelines.
The intent of the Contract Documents is to include all items necessary for the proper execution
and completion of the Work by the Contractor. These Contract Documents complement each other
in describing a complete work. Any requirement in one document binds as if stated in all. The
Contractor shall provide any work or materials clearly implied in the Contract even if the Contract
does not mention it specifically.
2. Date of Commencement and Substantial Completion Date. The date of commencement
shall be August 16, 2021. The Contractor shall substantially complete the Work not later than
September 30, 2021, subject to adjustment by change order.
The Contractor shall do all work and furnish all tools, materials, and equipment in accordance
with the above described Construction Contract Documents. The Contractor shall provide and
bear the expense of all equipment, work, and labor of any sort whatsoever that may be required
for the transfer of materials and for constructing and completing of the work provided for in
these Construction Contract Documents, except those items mentioned therein to be furnished
by the City.
4. Subject to additions and deductions by change order, the construction Contract Sum is the base
bid amount of $58,062.15 (including applicable sales tax.) The construction Contract Sum
shall include all items and services necessary for the proper execution and completion of the
work. The City hereby promises and agrees with the Contractor to employ, and does employ
the Contractor to provide the materials and to do and cause to be done the work described in
the Construction Contract Documents and to complete and finish the same according to the
plans and specifications and the terms and conditions herein contained; and hereby contracts
to pay for the same at the time and in the manner and upon the conditions provided for in this
Contract.
5. The Contractor agrees to comply with all state and federal laws relating to the employment of
labor and wage rates to be paid. The Contractor agrees to furnish insurance of the types and
in the amounts set forth in the Construction Contract Documents.
6. The Contractor agrees to repair and replace all property of the City and all property of others
damaged by himself, his employees, and sub -contractors.
The Contractor for himself and for his heirs, executors, administrators, successors, and assigns,
does hereby agree to the full performance of all the covenants herein upon the part of the
Contractor.
It is further provided that no liability shall attach to the City of Port Orchard by reason of
entering into this Construction Contract, except as expressly provided herein.
City of Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Page 2 of 23
Rev 5/1/2020
9. Title VI
The City of Port Orchard, in accordance with Title VI of the Civil Rights Act of 1964, 78 Stat. 252,
42 U.S.C. 2000d to 2000d-4 and Title 49, Code of Federal Regulations, Department of Transportation
subtitle A, Office of the Secretary, Part 21, nondiscrimination in federally assisted programs of the
Department of Transportation issued pursuant to such Act, must affirmatively insure that its contracts
comply with these regulations.
Therefore, during the performance of this Agreement, the Contractor, for itself, its assignees, and
successors in interest agrees as follows:
1. Compliance with Regulations: The Contractor will comply with the Acts and the Regulations
relative to Nondiscrimination in Federally -assisted programs of the U.S. Department of
Transportation, Federal Highway Administration (FHWA), as they may be amended from time to
time, which are herein incorporated by reference and made a part of this Agreement.
Nondiscrimination: The Contractor, with regard to the work performed by it during this
Agreement, will not discriminate on the grounds of race, color, national origin, sex, age,
disability, income -level, or LEP in the selection and retention of subcontractors, including
procurements of materials and leases of equipment. The Contractor will not participate directly or
indirectly in the discrimination prohibited by the Acts and the Regulations as set forth in
Appendix A, attached hereto and incorporated herein by this reference, including employment
practices when this Agreement covers any activity, project, or program set forth in Appendix B of
49 C.F.R. part 21.
Solicitations for Subcontracts, Including Procurements of Materials and Equipment: In all
solicitations, either by competitive bidding, or negotiation made by the Contractor for work to be
performed under a subcontract, including procurements of materials, or leases of equipment, each
potential subcontractor or supplier will be notified by the Contractor of the Contractor's
obligations under this Agreement and the Acts and the Regulations relative to Non-discrimination
on the grounds of race, color, national origin, sex, age, disability, income -level, or LEP.
Information and Reports: The Contractor will provide all information and reports required by
the Acts, the Regulations and directives issued pursuant thereto and will permit access to its
books, records, accounts, other sources of information, and its facilities as may be determined by
the City or the FHWA to be pertinent to ascertain compliance with such Acts, Regulations, and
instructions. Where any information required of the Contractor is in the exclusive possession of
another who fails or refuses to furnish the information, the Contractor will so certify to the City or
the FHWA, as appropriate, and will set forth what efforts it has made to obtain the information.
Sanctions for Noncompliance: In the event of the Contractor's noncompliance with the Non-
discrimination provisions of this Agreement, the City will impose such contract sanctions as it or
the FHWA may determine to be appropriate, including, but not limited to:
1. withholding payments to the Contractor under the Agreement until the contractor
complies; and/or
2. cancelling, terminating, or suspending the Agreement, in whole or in part.
6. Incorporation of Provisions: The Contractor will include the provisions of paragraphs one
through six in every subcontract, including procurements of materials and leases of equipment,
unless exempt by the Acts, the Regulations and directives issued pursuant thereto. The Contractor
City of Port Orchard and Apply A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Page 3 of 23
Rev 5/1/2020
will take action with respect to any subcontract or procurement as the City or the FHWA may
direct as a means of enforcing such provisions including sanctions for noncompliance. Provided,
that if the Contractor becomes involved in, or is threatened with litigation by a subcontractor, or
supplier because of such direction, the Contractor may request the City to enter into any litigation
to protect the interests of the City. In addition, the Contractor may request the United States to
enter into the litigation to protect the interests of the United States.
IN WITNESS WHEREOF, the parties hereto have caused this contract to be duly executed
on the date first written above.
CITY OF PORT ORCHARD CONTRACTOR
Robert Putaansuu, Mayor
By: Ron Reilly
its: Assistant Vice President
ATTEST/ T ENTICATE:
I3randy Rinearson, MMC, City Clerk
APPROVED AS TO FORM:
Charlotte A. Archer, City Attorney
,,r+F paR7 p ''�+•,,,
- - SEAL -
City of Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012 Rev 5/1/2020
Small Works Contract No. C051-21
Page 4 of 23
N/A
CERTIFICATE AS TO CORPORATE PRINCIPAL
I, (Corporate Officer (Not Contract Signer))
certify that I am the (Corporate Title) of the
corporation named as the Contractor in the Agreement attached hereto; that
, (Contract Signer) who signed said Agreement on behalf
of the Contractor, was then (Corporate Title) of said corporation;
that said Agreement was duly signed for and in behalf of said corporation by authority of its
governing body, and is within the scope of its corporate powers.
Corporate Seal
Corp. officer signature (not contract signer)
Printed
Title
State of )
County of )
, (corporate officer (not contract signer)) being
duly sworn, deposes and says that he/she is (Corporate Title)
of (Name of Corporation)
Subscribed and sworn to before me this day of , 20
City of Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Page 5 of 23
Notary Public (Signature)
Notary Public (Print)
My commission expires
Rev 5/1/2020
CITY OF PORT ORCHARD
PUBLIC WORK PROJECT TERMS AND CONDITIONS
The following terms and conditions shall be used in conjunction with the Standard Specifications
for Road, Bridge and Municipal Construction, 2018 edition, together with the APWA Supplement
(Section 1-99), as issued by the Washington State Department of Transportation and American
Public Works Association, Washington State Chapter, hereinafter referred to as the "standard
specifications". The standard specifications, except as they may be modified or superseded by
these provisions, shall govern all phases of work under this Contract, and they are by reference
made an integral part of these specifications and Contract as if herein fully set forth.
When the provisions of the standard specification conflict with the terms and conditions as
contained herein, the terms and conditions shall prevail.
1. BID PRICE: The bid price(s) shall include all necessary permits, fees and items of labor,
material, equipment, tools, overhead and compensation, supplies, taxes, utilities and other
incidentals necessary to complete the work in a fully functional and operational state. All prices
including bid prices are in US funds.
2. DEFINITIONS: The term "City" means Port Orchard, Washington, "successful bidder" means
the apparent lowest and best responsible bidder to whom an award is made, and "Contractor"
means the successful bidder who has satisfied the requirements for the award and who receives a
contract executed by the City. "Bidder" means the person, firm or corporation that has made an
offer in response to the invitation to bid. "Work" means the construction and services required by
the Contract Documents, whether completed or partially completed, and includes all other labor,
materials, equipment and services provided or to be provided by the Contractor to fulfill the
Contractor's obligations.
3. LICENSING AND REGISTRATION: The Contractor must have a Washington State certificate
of registration per chapter 18.27 RCW; a current state unified business identifier number; and if
applicable, industrial insurance coverage for the bidder's employees working in Washington, an
Employment Security Department number, and a state excise tax registration number. In addition,
the bidder must not be disqualified from bidding on any public works contracts under RCW
39.06.010 or 39.12.065(3).
4. PUBLIC WORK REQUIREMENTS: This project constitutes a public work under state law.
Bidders are warned to take into consideration statutory legal requirements, particularly, the
payment of prevailing wages and fringe benefits, payment and performance bonds and sales tax
implications in making their bids. It is the sole responsibility of the bidder to insure that the
appropriate labor classification(s) are identified and that the applicable wage and benefit rates are
taken into consideration when preparing their bid according to these specifications. The Contractor
shall complete and file State of Washington, Department of Labor & Industries, Statement of Intent
to Pay Prevailing Wages and Affidavit of Wages Paid forms and shall familiarize itself with their
requirements. The Contractor shall also be responsible for and pay all costs pertaining to the
processing of these forms.
5. INSURANCE REQUIREMENT: The successful bidder will furnish insurance as stipulated in
the Attachment entitled "Insurance Requirements."
6. RECEIPT OF ADDENDA: All official clarifications or interpretations of the bid documents
will be by written addenda only.
City of Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Page 6 of 23
Rev 5/1/2020
7. PROJECT COMPLIANCE: In compliance with the request for quotation, Bidder hereby
proposes to perform all work for this project in strict accordance with the Contract Documents, at
the Contract Sum, and within the time set forth herein with the understanding that time is of the
essence in the performance of this Contract.
8. TAXES: Proposals shall include all applicable taxes except sales tax, which is a separate bid
item. It shall be the Bidder's responsibility to furnish Federal Excise Tax Exemption Certificate,
when applicable.
9. ERROR IN EXTENSION: Unit price, when used, shall govern in case of extension error.
10. PERMITS AND FEES: The Contractor shall furnish all permits, inspection fees, and fees
required in the performance of this Contract, including those charged under RCW 39.12.070 by
the Department of Labor and Industries for the approval of statements of intent to pay prevailing
wages and the certification of affidavits of wages paid, etc. The Department may also charge fees
to persons or organizations requesting the arbitration of disputes under RCW 39.12.060. The
Contractor is responsible for all fees resulting from these statutes.
11. CONTRACT: The Contract Documents ("Contract"), when properly signed, will be the only
form that will be recognized by the City as an award. The executed Contract supersedes all
previous communications and negotiations, except as referenced herein, and constitutes the entire
agreement between the City and Contractor (parties), except as provided herein. The Contractor
shall not make any changes, alterations, or variations in the terms of the Contract without the
written consent of the City. No terms stated by the Bidder in its proposal shall be binding on the
City unless accepted in writing by the City. The successful bidder may not assign the Contract
resulting from this invitation to bid without the City's prior written consent. No waiver by the City
of a breach of any provision of the terms and conditions outlined in the invitation to bid shall
constitute a waiver of any other breach of such provision or of any other provisions.
12. CHANGE ORDERS: If the City or the Contractor requests a change in the Work, or either
party believes that a change is necessary, then the parties shall comply with the following
procedure to document and reflect a change in the Work: (a) The party requesting the change shall
write a description of the change and give the description to the other party (the "Change Notice");
(b) Before proceeding with the change in Work, unless otherwise excused by emergency, the
Contractor shall provide the City with a fixed -price written estimate of the cost and time impact
of the change in Work; and (c) The City and the Contractor shall execute a Change Order
confirming their agreement as to the change in Work, the fixed -price cost, and the extension of the
Substantial Completion Date, if any. If the change in Work cannot be performed on a fixed -price
basis, the Change Order shall identify the agreed method of compensation.
13. CHANGE DIRECTIVES: A "Change Directive" is a written order signed by the City,
directing a change in the Work prior to agreement on adjustment, if any, in the Contract Sum or
Substantial Completion Date, or both. The City may by Change Directive, without invalidating the
Contract, order changes in the Work within the general scope of the Contract consisting of
additions, deletions or other revisions, the Contract Sum and Substantial Completion Date being
adjusted accordingly. A Change Directive shall only be used in the absence of total agreement on
the terms of a Change Order. Upon receipt of a Change Directive, the Contractor shall promptly
proceed with the change in the Work and advise the City of its agreement or disagreement with
the proposed method for determining the proposed adjustment in the Contract Sum and/or
Substantial Completion Date, if any, provided in the Change Directive. A Change Directive signed
by the Contractor indicates agreement with all terms set forth in the Change Directive. Such
agreement shall be effective immediately and shall be recorded as soon as practical with a Change
City of Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Page 7 of 23
Rev 5/1/2020
Order. If the parties are unable to agree on an adjustment to the Contract Sum and/or Substantial
Completion Date, if any, then either party may submit the matter for determination in accordance
with Section 21.
14. MINOR CHANGES IN THE WORK: The City shall have the authority to order minor
changes in the Work not involving adjustment in the Contract Sum or extension of the Substantial
Completion Date and not inconsistent with the Contract documents. The Contractor shall promptly
carry out such written orders for minor changes in the Work.
15. COMPLIANCE WITH LAWS AND REGULATIONS: The Contractor warrants full
compliance with all applicable local, state or federal laws and regulations and agrees to indemnify
and defend the City against any loss, cost, liability or damage, including reasonable attorney's
fees, by reason of successful bidder's violation of this paragraph.
16. INDEMNIFICATION: All services to be rendered or performed under this Contract will be
rendered or performed entirely at the Contractor's own risk. The Contractor shall defend,
indemnify and hold the City, its officers, officials, employees and volunteers harmless from any
and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in
connection with the performance of this Contract, except for injuries and damages caused by the
sole negligence of the City. Should a court of competent jurisdiction determine that this Contract
is subject to RCW 4.24.115, then, in the event of liability for damages arising out of bodily injury
to persons or damages to property caused by or resulting from the concurrent negligence of the
Contractor and the City, its officers, officials, employees and volunteers, the Contractor's liability
hereunder shall be only to the extent of the Contractor's negligence. IT IS FURTHER
SPECIFICALLY AND EXPRESSLY UNDERSTOOD THAT THE INDEMNIFICATION
PROVIDED HEREIN CONSTITUTES THE CONTRACTOR'S WAIVER OF IMMUNITY
UNDER INDUSTRIAL INSURANCE, TITLE 51 RCW, SOLELY FOR THE PURPOSES OF
THIS INDEMNIFICATION. THIS WAIVER HAS BEEN MUTUALLY NEGOTIATED BY
THE PARTIES. THE PROVISIONS OF THIS SECTION SHALL SURVIVE THE
EXPIRATION OR TERMINATION OF THIS CONTRACT.
17. TERMINATION: This Contract may be terminated in whole or in part, without penalty to the
City, under the following conditions: 1) by mutual written agreement; 2) by the City for breach by
the Contractor of any of the obligations or requirements set forth in the Contract Documents which
would, at the option of the City, require the Contractor to assume liability for any and all damages,
including the excess of re -procuring similar products or services; 3) for convenience of the City;
or 4) by the City for non -appropriation of funds.
18. TERMINATION BY THE CITY WITHOUT CAUSE: Notwithstanding any other provisions
contained herein, the City, without cause, may terminate the Contract between the parties by
providing notice to the Contractor. Upon termination under this section: 1) All remaining
obligations of the parties are discharged, but any right based upon breach or performance occurring
prior to termination survives; 2) If the reasonable costs of performance incurred by the Contractor
prior to termination exceed the amount paid by the City to the Contractor on the Contract Sum, the
City shall reimburse the Contractor in the amount of such excess; 3) If the amount paid by the City
to the Contractor on the Contract Sum exceeds the reasonable costs of performance incurred by
the Contractor prior to termination, the Contractor shall reimburse the City in the amount of such
excess; and 4) Any funds obtained or retained by the Contractor as provided in subsections 2) or
3), above, shall constitute full payment and consideration for the services performed by the
Contractor prior to termination.
City of Port Orchard and Apply A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Page 8 of 23
Rev 5/1/2020
19. COMPLIANCE WITH TERMS: The City may at any time insist upon strict compliance with
these terms and conditions, notwithstanding any previous custom, practice, or course of dealing to
the contrary.
20. PAYMENT: Contractor shall maintain time and expense records and provide them to the City
along with monthly invoices in a format acceptable to the City for work performed to the date of
the invoice. All invoices shall be paid by the City within 45 days of receipt of a proper invoice. If
the services rendered to not meet the requirements of the Contract, Contractor will correct or
modify the work to comply with the Contract. City may withhold payment for such work until the
work meets the requirements of the Contract.
21. DISPUTE RESOLUTION: In the event there is a dispute between the parties, the parties
agree to resolve that dispute in the following manner: (a) The parties shall attempt in good faith to
resolve any dispute promptly through negotiation. Either party may give the other party written
notice that a dispute exists (a "Notice of Dispute"). The Notice of Dispute shall include a statement
of such party's position. Within ten (10) days of the delivery of the Notice of Dispute, the parties
shall meet at a mutually acceptable time and place and attempt to resolve the dispute; (b) If the
parties are unable to resolve the dispute, they may elect to submit the dispute to mediation. The
cost of the mediation shall be borne equally by the parties. The mediator shall be selected by the
mutual agreement of the parties; (c) If the mediation does not result in a settlement of the dispute,
the dispute shall be settled by binding arbitration by the Judicial Arbitration and Mediation
Services ("JAMS") in accordance with the then operative construction rules of JAMS. The parties
may select an arbitrator by mutual agreement, or if unable to agree, the arbitrator will be selected
pursuant to the rules of JAMS. The parties shall be bound by the decision of such arbitrator. The
arbitration shall be conducted in Kitsap County, Washington; provided, if JAMS is unable to
conduct the arbitration in Kitsap County, then the arbitration shall be held in such location as the
parties may agree after consulting with JAMS.
City of Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Page 9 of 23
Rev 5/1/2020
CITY OF PORT ORCHARD
INSURANCE REQUIREMENTS
The Contractor shall procure and maintain for the duration of the Contract with the City, insurance
against claims for injuries to persons or damage to property which may arise from or in connection
with the performance of the work hereunder by the Contractor, their agents, representatives,
employees and subcontractors.
No Limitation. The Contractor's maintenance of insurance, its scope of coverage and limits as
required herein shall not be construed to limit the liability of the Contractor to the coverage
provided by such insurance, or otherwise limit the City's recourse to any remedy available at law
or in equity.
Minimum Scope of Insurance. The Contractor shall obtain insurance of the types described below:
• Automobile Liability insurance covering all owned, non -owned, hired and leased vehicles.
Coverage shall be written on Insurance Services Office (ISO) form CA 00 01 or a substitute
form providing equivalent liability coverage. If necessary, the policy shall be endorsed to
provide contractual liability coverage.
Commercial General Liability insurance shall be written on ISO occurrence form CG 00
01 and shall cover liability arising from premises, operations, stop gap liability,
independent contractors, products -completed operations, personal injury and advertising
injury and liability assumed under an insured contract. The Commercial General Liability
insurance shall be endorsed to provide the Aggregate Per Project Endorsement ISO form
CG 25 03 11 85 or an equivalent endorsement. There shall be no endorsement or
modification of the Commercial General Liability Insurance for liability arising from
explosion, collapse or underground property damage. The City shall be named by
endorsement as an additional insured under the Contractor's Commercial General Liability
insurance policy with respect to the work performed for the City using ISO Additional
Insured endorsement CG or substitute endorsements providing equivalent coverage.
• Workers' Compensation coverage as required by the Industrial Insurance laws of the State
of Washington.
Builders Risk insurance covering interests of the City, the Contractor, Subcontractors, and
Sub -subcontractors in the work. Builders Risk insurance shall be on an all-risk policy form
and shall insure against the perils of fire and extended coverage and physical loss or
damage including flood, earthquake, theft, vandalism, malicious mischief, collapse,
temporary buildings and debris removal. The Builders Risk insurance covering the work
will have a deductible of $5,000 for each occurrence, which will be the responsibility of
the Contractor. Higher deductibles for flood and earthquake perils may be accepted by the
City upon written request by the Contractor and written acceptance by the City. Any
increased deductibles accepted by the City will remain the responsibility of the Contractor.
The Builders Risk insurance shall be maintained until final acceptance of the work by the
City.
City of Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Page 10 of 23
Rev 5/1/2020
Employer's Liability insurance limit of $1,000,000 each accident, Employer's Liability
Disease each employee $1,000,000 and Employer's Liability Disease — Policy limit
$1,000.000.
Minimum Amounts of Insurance. The Contractor shall maintain the following insurance limits:
• Automobile Liability insurance with a minimum combined single limit for bodily injury
and property damage of $1,000.000 per accident.
• Commercial General Liability insurance shall be written with limits no less than
$1,000,000 each occurrence, $2,000,000 general aggregate and a $2,000,000 products -
completed operations aggregate limit.
• Builders Risk insurance shall be written in the amount of the completed value of the project
with no coinsurance provisions.
Other Insurance Provisions. The Contractor's Automobile Liability, Commercial General
Liability and Builders Risk insurance policies are to contain, or be endorsed to contain that they
shall be primary insurance as respects the City (as applicable to each line of coverage). The
Consultant's insurance coverage shall be primary insurance as respect the City. Any insurance, self-
insurance or insurance pool coverage maintained by the City shall be excess of the Contractor's
insurance and shall not contribute with it. If any coverage is written on a "claims made" basis,
then a minimum of three (3) year extended reporting period shall be included with the claims made
policy, and proof of this extended reporting period provided by the City.
Contractor's Insurance for Other Losses. The Contractor shall assume full responsibility for all
loss or damage from any cause whatsoever to any tools, including but not limited to the
Contractor's employee -owned tools, machinery, equipment or motor vehicles owned or rented by
the Contractor, or the Contractor's agents, suppliers or contractors as well as any temporary
structures, scaffolding and protective fences.
Waiver of Subro ag tion. The Contractor waives all rights against the City, any of its
Subcontractors, Sub -subcontractors, agents and employees, for damages caused by fire or other
perils to the extent covered by Builders Risk insurance or other property insurance obtained
pursuant to this Insurance Requirements Section of the Contract or other property insurance
applicable to the work. The Contractor's insurance shall be endorsed to waive the right of
subrogation against the City, or any self-insurance, or insurance pool coverage maintained by the
City. The City will not waive its right to subrogation against the Contractor. The Contractor's
insurance shall be endorsed acknowledging that the City will not waive its right to subrogation.
Acceptability of Insurers. Insurance is to be placed with insurers with a current A.M. Best rating
of not less than ANII.
Verification of Coverage. The Contractor shall furnish the City with original certificates and a
copy of the amendatory endorsements, including but not necessarily limited to the additional
City of Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Page 11 of 23
Rev 5/1/2020
insured endorsement, evidencing the Automobile Liability and Commercial General Liability
insurance of the Contractor before commencement of the work. Before any exposure to loss may
occur, the Contractor shall file with the City a copy of the Builders Risk insurance policy that
includes all applicable conditions, exclusions, definitions, terms and endorsements related to this
project.
Subcontractors. The Contractor shall have sole responsibility for determining the insurance
coverage and limits required, if any, to be obtained by subcontractors, which determination shall
be made in accordance with reasonable and prudent business practices.
Notice of Cancellation. The Consultant shall provide thirty (30) days written notice by certified
mail, return receipt requested, to the City prior to the cancellation or alteration of coverage. The
Contractor shall provide the City and all Additional Insureds for this work with written notice of
any policy cancellation, within two business days of their receipt of such notice.
Failure to Maintain Insurance. The insurance required by this Section will not be canceled,
materially changed or altered without forty-five (45) days prior written notice submitted to the
City. Failure on the part of the Contractor to maintain insurance as required shall constitute a
material breach of contract, upon which the City may, after giving five business days' notice to
the Contractor to correct the breach, immediately terminate the Contract, or, at its discretion,
procure or renew such insurance and pay any and all premiums in connection therewith, with any
sums so expended to be repaid to the City on demand, or at the sole discretion of the City, offset
against funds due the Contractor from the City.
City of Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Page 12 of 23
Rev 5/1/2020
CITY OF PORT ORCHARD
DECLARATION OF OPTION FOR PERFORMANCE
BOND OR ADDITIONAL RETAINAGE
(APPLICABLE TO CONTRACTS OF $150 000 OR LESS —RCW 39.08.010)
Note: This form must be submitted at the time the Contractor executes the Contract. The
Contractor shall designate the option desired by checking the appropriate space.
The Contractor shall provide 5% retainage, pursuant to RCW 60.28.011(1)(a).
2. In addition, the Contractor elects to (select one):
X (1) Furnish a performance bond in the amount of the total contract sum. An
executed performance bond on the required form is included with the executed contract
documents.
(2) Have the City retain, in lieu of the performance and payment bonds, ten
percent (10%) of the total contract amount for a period of thirty days after date of final
acceptance, or until receipt of all necessary releases from the department of revenue and
the department of labor and industries and settlement of any liens filed under chapter 60.28
RCW, whichever is later. RCW 39.08.010.
In choosing option 2, the Contractor agrees that if the Contractor, its heirs, executors,
administrators, successors, or assigns, shall in all things stand to and abide by, and well
and truly keep and perform the covenants, conditions and agreements in the Contract, and
shall faithfully perform all the provisions of such Contract and shall also well and truly
perform and fulfill all the undertakings, covenants, terms, conditions and agreements of
any and all duly authorized modifications of the Contract that may hereafter be made, at
the time and in the manner therein specified, and shall pay all laborers, mechanics,
subcontractors, and materialmen, and all persons who shall supply such person or
persons, or subcontractors, with provisions and supplies for the carrying on of such work,
on his or her part, and shall defend, indemnify, and save harmless the City of Port
Orchard, Washington, its officers and agents from any claim for such payment, then the
funds retained in lieu of a performance bond shall be released at the time provided in said
option 2; otherwise, the funds shall be retained until the Contractor fulfills the said
obligations.
City of Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Page 13 of 23
Contractor Signature, Date 05/21 /2021
Bond No. HSHNSU 0800759
Rev 5/1/2020
PERFORMANCE AND PAYMENT BOND
We. Apply -A -Line, LLC
(Principal)
CITY OF PORT ORCHARD
2021 CITY ROAD STRIPING
CONTRACT NO. C051-21
Bond to City of Port Orchard, Washington
Bond No. HSHNSU 0800759
and Harco National Insurance Company
(Surety)
a Illinois Corporation, and as a surety corporation authorized to become
a surety upon Bonds of Contractors with municipal corporations in Washington State, are jointly and
severally bound to the City of Port Orchard, Washington ("Owner"), in the penal sum of
Fifty Eight Thousand Sixty Two and 15/100 Dollars ($ 58,062.15 )
the payment of which sum, on demand, we bind ourselves and our successors, heirs, administrators,
executors, or personal representatives, as the case may be. This Performance Bond is provided to secure the
performance of Principal in connection with a contract dated May 11 , 20 21 , between Principal and
Owner for a project entitled 2021 City Road Striping Contract No. C051-21 ("Contract"). The initial
penal sum shall equal 100 percent of the Total Bid Price, including sales tax, as specified in the Proposal
submitted by Principal.
NOW, THEREFORE, this Performance and Payment Bond shall be satisfied and released only upon the
condition that Principal:
Faithfully performs all provisions of the Contract and changes authorized by Owner in the manner and
within the time specified as may be extended under the Contract;
Pays all laborers, mechanics, subcontractors, lower tier subcontractors, material persons, and all other
persons or agents who supply labor, equipment, or materials to the Project; and
• Pays the taxes, increases and penalties incurred on the Project under Titles 50, 51 and 82 RCW on:
(A) Projects referred to in RCW 60.28.011(1)(b); and/or (B) Projects for which the bond is
conditioned on the payment of such taxes, increases and penalties.
The surety shall indemnify, defend, and protect the Owner against any claim of direct or indirect loss
resulting from the failure:
Of the Principal (or any of the employees, subcontractors, or lower tier subcontractors of the Principal)
to faithfully perform the contract, or
Of the Principal (or any subcontractor or lower tier subcontractor of the Principal) to pay all laborers,
mechanics, subcontractors, lower tier subcontractors, material person, or any other person who
provides supplies or provisions for carrying out the work.
The liability of Surety shall be limited to the penal sum of this Performance and Payment Bond.
Principle and Surety agree that if the Owner is required to engage the services of an attorney in connection
with enforcement of this bond each shall pay the Owner reasonable attorney's fees, whether or not suit is
commenced, in addition to the penal sum.
City of'Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012 Rev 5/1/2020
Small Works Contract No. C051-21
Page 14 of 23
No change, extension of time, alteration, or addition to the terms of the Contract or to the Work to be
performed under the Contract shall in any way affect Surety's obligation on the Performance Bond. Surety
hereby waives notice of any change, extension of time, alteration, or addition to the terms of the Contract
or the Work, with the exception that Surety shall be notified if the Contract time is extended by more than
twenty percent (20%).
If any modification or change increases the total amount to be paid under the Contract, Surety's obligation
under this Performance and Payment Bond shall automatically increase in a like amount. Any such increase
shall not exceed twenty-five percent (25%) of the original amount of the Performance and Payment Bond
without the prior written consent of Surety.
This Performance and Payment Bond shall be governed and construed by the laws of the State of
Washington, and venue shall be in Kitsap County, Washington.
IN WITNESS WHEREOF, the parties have executed this instrument in two (2) identical counterparts this
19th day of May , 20 21
Tit..
'''►r,
irrc/r'•�
=SEAL
on
LLC
Signature of Authorized Official
Reillv. Assistant Vice President
Printed Name and Title
Name and address of local office of
Agent and/or Surety Company:
Harco National Insurance Company
Sur ty
'Signatifre of Authorized Official.
By Aaron P. Clark, Attorney in Fact
Attorney in Fact (Attach Power of Attorney)
Lockton Companies
3657 Briarpark Drive, Ste. 700
Houston, TX 77042
Surety companies executing bonds must appear on the current Authorized Insurance List in the State of
Washington per Section 1-02.7 of the Standard Specifications.
City of'Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Page 15 of 23
Rev 5/1/2020
ACKNOWLEDGEMENT
Corporation, Partnership, or Individual
STATE OF WASHINGTON
)ss.
COUNTY OF PIERCE )
On this 21 St day of May , 20 21 , before me, the undersigned, a Notary Public in and for the
State of Washington, duly commissioned and sworn, personally appeared_ Ron Reilly , to
me known to be the (check one of the following boxes):
0
corporation,
of
the
❑x Assistant Vice President of Apply -A -Line, LLC , the
partnership,
❑ individual,
that executed the foregoing instrument to be the free and voluntary act and deed of said ❑ corporation, ❑x
partnership, ❑ individual for the uses and purposes therein mentioned, and on oath stated that ❑x he ❑
she was authorized to execute said instrument.
WITNESS my hand and official seal hereto affixed the day and year first above written.
SANDRA L SABLAN
Notary Public
State of Washington
Commission # 90877
My Comm. Expires Mar 29, 2023
Notary Seal with Ink Stamp
City of Port Orchard and Apply A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Date 05/21/2021
Sandra L. Sa an
Print or type name
NOTARY PUBLIC,
in and for the State of Washington
Residing at: Covington
My Commission expires: 03/29/2023
Page 16 of 23
Rev 5/1/2020
SURETY ACKNOWLEDGEMENT
STATE OF Texas
)SS.
COUNTY OF Harris
On this 19th day of May , 20 21 , before me, the undersigned, a Notary Public in and for th
e State of Texas, duly commissioned and sworn, personally appeared Aaron P. Clark , to the known to be
the Attorney in Fact of Harco National Insurance Company , the corporation that executed
the foregoing instrument, and acknowledged the said instrument to be the free and voluntary act and deed
of said corporation, for the uses and purposes therein mentioned, and on oath
stated that ® he ❑ she was authorized to execute said instrument.
WITNESS my hand and official seal hereto affixed the day and year first above written.
Notary Seal with Ink Stamp
City of Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Dated: 9, 21
Autumn Stockton
Print or type name
NOTARY PUBLIC,
in and for the State of Texas
Residing at:
Houston, TX
My Commission expires: February 22, 2025
Page 17 of 23
���;% ii�.ti A MN 6TOGKTO
NOTARY1C
��• � i its i3i01$9�
j ..... ry' St8te of Texas
Comm. Exp. 02-22.2026
Rev 5/1/2020
CITY OF PORT ORCHARD
MAINTENANCE/WARRANTY BOND
(Note: Before the Performance Bond can be released the City must receive the two years Maintenance/Warranty Bond)
PROJECT #, PERMIT #, PW2021-012
CONTRACT # C051-21
SURETY BOND #: HSHNSU 0800759
DATE POSTED: May 19, 2021
EXPIRATION DATE: May 19, 2023
RE: Project Name: 2021 City Road Stripi
Owner/Developer/Contractor: Apply -A -Line, LLC
Project Address: City of Port Orchard Public Roads
KNOW ALL PERSONS BY THESE PRESENTS: That we, Apply -A -Line, LLC (hereinafter
called the "Principal'), and Harco National Insurance Compana corporation organized under the laws of the State
of Illinois , and authorized to transact surety business in the State of Washington
(hereinafter called the "Surety"), are held and firmly bound unto the City of Port Orchard, Washington, in the
sum of Fifty Eight Thousand Sixty Two and 15/100 dollars ($ 58,062.15 ) 20%
Total Contract Amount, lawful money of the United States of America, for the payment of which sum we and
each of us bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, by
these presents. THE CONDITIONS of the above obligation are such that:
WHEREAS, the above named Principal has constructed and installed certain improvements on public
property in connection with a project as described above within the City of Port Orchard; and
WHEREAS, the Principal is required to post a bond for the twenty-four (24) months following written
and final acceptance of the project in order to provide security for the obligation of the Principal to repair and/or
replace said improvements against defects in workmanship, materials or installation during the twenty-four
(24) months after written and final approval/acceptance of the same by the City;
NOW, THEREFORE, this Maintenance Bond has been secured and is hereby submitted to the City.
It is understood and agreed that this obligation shall continue in effect until released in writing by the City, but
only after the Principal has performed and satisfied the following conditions:
A. The work or improvements installed by the Principal and subject to the terms and conditions of this
Bond are as follows: (insert complete description of work here)
AAL #165A6298 - 2021 CITY ROAD STRIPING CONTRACT #C051-21 / PW PROJECT #PW2021-012
B. The Principal and Surety agree that the work and improvements installed in the above -referenced
project shall remain free from defects in material, workmanship and installation (or, in the case of landscaping,
shall survive,) for a period of twenty-four (24) months after written and final acceptance of the saine and
approval by the City. Maintenance is defined as acts carried out to prevent a decline, lapse or cessation of the
state of the project or improvements as accepted by the City during the twenty-four (24) month period after
final and written acceptance, and includes, but is not limited to, repair or replacement of defective
workmanship, materials or installations.
City of'Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Page 18 of 23
Rev 5/1/2020
C. The Principal shall, at its sole cost and expense, carefully replace and/or repair any damage or defects
in workmanship, materials or installation to the City -owned real property on which improvements have been
installed, and leave the same in as good condition as it was before commencement of the work.
D. The Principal and the Surety agree that in the event any of the improvements or restoration work
installed or completed by the Principal as described herein, fail to remain free from defects in materials,
workmanship or installation (or in the case of landscaping, fail to survive), for a period of twenty, (24)
months from the date of approval/acceptance of the work by the City, the Principal shall repair and/replace the
same within ten (10) days of demand by the City, and if the Principal should fail to do so, then the Surety shall:
1. Within twenty (20) days of demand of the City, make written commitment to the
City that it will either:
a). remedy the default itself with reasonable diligence pursuant to a time schedule
acceptable to the City; or
b). tender to the City within an additional ten (10) days the amount necessary, as
determined by the City, for the City to remedy the default, up to the total bond amount.
Upon completion of the Surety's duties under either of the options above, the Surety shall then
have fulfilled its obligations under this bond. If the Surety elects to fulfill its obligation
pursuant to the requirements of subsection 1)(1)(b), the City shall notify the Surety of the
actual cost of .the remedy, upon completion of the remedy. The City shall return, without
interest, any overpayment made by the Surety, and the Surety shall pay to the City any actual
costs which exceeded the City estimate, limited to the bond amount.
In the event the Principal fails to make repairs or provide maintenance within the time period
requested by the City, then the City, its employees and agents shall have the right at the City's
sole election to enter onto said property described above for the
purpose of repairing or maintaining the improvements. This provision shall not be construed
as creating an obligation on the part of the City or its representatives to repair or maintain such
improvements.
E. Corrections. Any corrections required by the City shall be commenced within ten (10) days of
notification by the City and completed within thirty (30) days of the date of notification. If the work
is not performed in a timely manner, the City shall have the right, without recourse to legal action, to
take such action under this bond as described in Section D above.
F. Extensions and Changes. No change, extension of time, alteration or addition to the work to be
performed by the Principal shall affect the obligation of the Principal or Surety on this bond, unless
the City specifically agrees, in writing, to such alteration, addition, extension or change. The Surety
waives notice of any such change, extension, alteration or addition thereunder.
G. Enforcement. It is specifically agreed by and between the parties that in the event any legal action
must be taken to enforce the provisions of this bond or to collect said bond, the prevailing party shall
be entitled to collect its costs and reasonable attorney fees as a part of the reasonable costs of securing
the obligation hereunder. In the event of settlement or resolution of these issues prior to the filing of
any suit, the actual costs incurred by the City, including reasonable attorney fees, shall be considered
City of Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012 Rev.5/1/2020
Small Works Contract No. C051-21
Page 19 of 23
a part of the obligation hereunder secured. Said costs and reasonable legal fees shall be recoverable
by the prevailing party, not only from the proceeds of this bond, but also over and above said bond as
a part of any recovery (including recovery on the bond) in any judicial proceeding. The Surety hereby
agrees that this bond shall be governed by the laws of the State of Washington. Venue of any litigation
arising out of this bond shall be in Kitsap County Superior Court.
H. Bond Expiration. This bond shall remain in full force and effect until the obligations secured hereby
have been fully perfonned and until released in writing by the City at the request of the Surety or
Principal.
DATED this 19th day of May , 20? 1.
SURETY COMPANY DEVELOPER/OWNER `
(Signature must be notarized (Signature must be notarized '� �'� 9 $
By: _ �� By
Its Attorney in Fact, Aaron P. Clark Its Asst. Vice President, Ron Reilly
Business Name: Harco National Insurance Company Business Name: Apply -A-Line, LLC
Business Address: P.O. Box 10800 Business Address: 175 Roy Rd SW Ste. C
City/State/Zip Code: Raleigh, NC 27605 City/State/Zip Code: Pacific, WA 98047
Telephone Number: (919) 833-1600 Telephone Number: (253) 299-1200
CITY OF PORT ORCHARD
Date:
Its Public Works Director/City Engineer
CHECK FOR ATTACHED NOTARY SIGNATURE
Individual (Form P-1)
Corporation (Form P-2)
Surety Company (Form P-2)
FORM P-1 / NOTARY
BLOCK
(Use For Individual/Sole Proprietor Only)
STATE OF WASHINGTON
) ss.
City of'Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012 Rev 5/1/2020
Small Works Contract No. C051-21
Page 20 of 23
COUNTY OF KITSAP
I certify that I know or have satisfactory evidence that is the person who
appeared before me, and said person acknowledged that (he/she) signed this instrument, and acknowledged it
to be (his/her) free and voluntary act for the uses and purposes mentioned in the instrument.
City of Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Dated:
Page 21 of 23
(print or type name)
NOTARY PUBLIC in and for the
State of Washington, residing
My Commission expires:
Rev 5/1/2020
FORM P-2 / NOTARY BLOCK
(Use For Partnership or Corporation Only)
(Developer/Owner)
STATE OF WASHINGTON )
ss.
COUNTY OF PIERCE )
I certify that I know or have satisfactory evidence that Ron Reilly is the person who
appeared before me, and said person acknowledged as the Assistant Vice President of
Apply —A —Line, LLC that (he/she) signed this instrument, on oath stated that (he/she) was
authorized to execute the instrument and acknowledged it to be (his/her) free and voluntary act for the uses and
purposes mentioned in the instrument.
SANDRA L SABLAN
Notary Public
State of Washington
Commission # 90877
My Comm. Expires Mar 29, 2023
(Surety Company)
STATE OF TEXAS )
ss.
COUNTY OF )
Dated: 05 21 2021
Sandra L. Sablan
(print or type name)
NOTARY PUBLIC in and for the
State of Washington, residing
at: Covington
My Commission expires: 03/29/2023
I certify that I know or have satisfactory evidence that Aaron P. Clark is the person who
appeared before me, and said person acknowledged as the Attorney in Fact of
Harco National Insurance Company that (he/she) signed this instrument, on oath stated that (he/she) was
authorized to execute the instrument and acknowledged it to be (his/her) free and voluntary act for the uses and
purposes mentioned in the instrument.
-------------------
;w�p•; AUTUMN STOCKTON
NOTARY PUBLIC
131015989
'�• State of Texas
•' ?P Comm. Exp. 02-22-2025
City of Port Orchard and Apply -A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Page 22 of 23
t/. • ' 1
Autumn Stockton
(print or type name)
NOTARY PUBLIC in and for the
State of Texas, residing
at: Houston, TX
My Commission expires: February22, 2025
Rev 5/1/2020
POWER OF ATTORNEY Bond# HSHNSU0800759
��tj tilySU STATE OF NEW JERSEY STATE OF ILLINOIS
xy vd�F County of Essex County of Cook
SEAL nr
1904
E Kenneth Chapman
Executive Vice President, Harco National Insurance Company
and International Fidelity Insurance Company
HARCO NATIONAL INSURANCE COMPANY
INTERNATIONAL FIDELITY INSURANCE COMPANY
Member companies of IAT Insurance Group, Headquartered: 702 Oberlin Road, Raleigh, North Carolina 27605
KNOW ALL MEN BY THESE PRESENTS: That HARCO NATIONAL INSURANCE COMPANY, a corporation organized and existing under the laws of
the State of Illinois, and INTERNATIONAL FIDELITY INSURANCE COMPANY, a corporation organized and existing under the laws of the State of New
Jersey, and having their principal offices located respectively in the cities of Rolling Meadows, Illinois and Newark, New Jersey, do hereby constitute and
appoint
TIMOTHY F. KELLY, AARON P. CLARK, FLORENCE MCCLELLAN, KRISTIN DARLING, R.F. BOBO
Houston, TX
their true and lawful attorneys) -in -fact to execute, seal and deliver for and on its behalf as surety, any and all bonds and undertakings, contracts of
indemnity and other writings obligatory in the nature thereof, which are or may be allowed, required or permitted by law, statute, rule, regulation, contract
or otherwise, and the execution of such instrument(s) in pursuance of these presents, shall be as binding upon the said HARCO NATIONAL
INSURANCE COMPANY and INTERNATIONAL FIDELITY INSURANCE COMPANY, as fully and amply, to all intents and purposes, as if the same had
been duly executed and acknowledged by their regularly elected officers at their principal offices.
This Power of Attorney is executed, and may be revoked, pursuant to and by authority of the By -Laws of HARCO NATIONAL INSURANCE COMPANY
and INTERNATIONAL FIDELITY INSURANCE COMPANY and is granted under and by authority of the following resolution adopted by the Board of
Directors of INTERNATIONAL FIDELITY INSURANCE COMPANY at a meeting duly held on the 13th day of December, 2018 and by the Board of
Directors of HARCO NATIONAL INSURANCE COMPANY at a meeting held on the 13th day of December, 2018.
"RESOLVED, that (1) the Chief Executive Officer, President, Executive Vice President, Senior Vice President, Vice President, or Secretary of the
Corporation shall have the power to appoint, and to revoke the appointments of, Attorneys -in -Fact or agents with power and authority as defined or limited
in their respective powers of attorney, and to execute on behalf of the Corporation and affix the Corporation's seal thereto, bonds, undertakings,
recognizances, contracts of indemnity and other written obligations in the nature thereof or related thereto; and (2) any such Officers of the Corporation
may appoint and revoke the appointments of joint -control custodians, agents for acceptance of process, and Attorneys -in -fact with authority to execute
waivers and consents on behalf of the Corporation; and (3) the signature of any such Officer of the Corporation and the Corporation's seal may be affixed
by facsimile to any power of attorney or certification given for the execution of any bond, undertaking, recognizance, contract of indemnity or other written
obligation in the nature thereof or related thereto, such signature and seals when so used whether heretofore or hereafter, being hereby adopted by the
Corporation as the original signature of such officer and the original seal of the Corporation, to be valid and binding upon the Corporation with the same
force and effect as though manually affixed."
IN WITNESS WHEREOF, HARCO NATIONAL INSURANCE COMPANY and INTERNATIONAL
FIDELITY INSURANCE COMPANY have each executed and attested these presents
on this 31 st day of December, 2018 ,. —rr,r
006,g�t*,..
SEAS:
"A'x�rrrrr sy"c"
On this 31st day of December, 2018 , before me came the individual who executed the preceding instrument, to me personally known, and,
being by me duly sworn, said he is the therein described and authorized officer of HARCO NATIONAL INSURANCE COMPANY and
INTERNATIONAL FIDELITY INSURANCE COMPANY; that the seals affixed to said instrument are the Corporate Seals of said Companies; that the
said Corporate Seals and his signature were duly affixed by order of the Boards of Directors of said Companies.
"Wit"+++++., IN TESTIMONY WHEREOF, I have hereunto set my hand affixed my Official Seal, at the City of Newark,
. ..."A: �G��: New Jersey the day and year first above written.
J E �� Shirelle A. Outley a Notary Public of New Jersey
+'++111" 1 My Commission Expires April 4, 2023
CERTIFICATION
I,.the undersigned officer of HARCO NATIONAL INSURANCE COMPANY and INTERNATIONAL FIDELITY INSURANCE COMPANY do hereby certify
that I have compared the foregoing copy of the Power of Attorney and affidavit, and the copy of the Sections of the By -Laws of said Companies as set
forth in said Power of Attorney, with the originals on file in the home office of said companies, and that the same are correct transcripts thereof, and of the
whole of the said originals, and that the said Power of Attorney has not been revoked and is now in full force and effect.
IN TESTIMONY WHEREOF, I have hereunto set my hand on this day, May 19, 2021
A00717
a 4� �__
Irene Martins, Assistant Secretary
APPENDIX A
During the performance of this Agreement, the Contractor, for itself, its assignees, and successors in
interest agrees to comply with the following non-discrimination statutes and authorities; including but not
limited to:
Pertinent Non -Discrimination Authorities:
• Title VI of the Civil Rights Act of 1964 (42 U S.C. § 2000d et seq., 78 stat. 252), (prohibits
discrimination on the basis of race, color, national origin); and 49 C.F.R. Part 21.
• The Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970, (42
U.S.C. § 4601), (prohibits unfair treatment of persons displaced or whose property has been
acquired because of Federal or Federal -aid programs and projects);
• Federal -Aid Highway Act of 1973, (23 U.S.C. § 324 et seq.), (prohibits discrimination on the
basis of sex);
• Section 504 of the Rehabilitation Act of 1973, (29 U.S.C. § 794 et seq.), as amended, (prohibits
discrimination on the basis of disability); and 49 C.F.R. Part 27;
• The Age Discrimination Act of 1975, as amended, (42 U S.C. § 6101 et seq.), (prohibits
discrimination on the basis of age);
• Airport and Airway Improvement Act of 1982, (49 USC§ 471, Section 4 7123), as amended,
(prohibits discrimination based on race, creed, color, national origin, or sex);
• The Civil Rights Restoration Act of 1987, (PL 100-209), (Broadened the scope, coverage and
applicability of Title VI of the Civil Rights Act of 1964, The Age Discrimination Act of 1975 and
Section 504 of the Rehabilitation Act of 1973, by expanding the definition of the terms "programs
or activities" to include all of the programs or activities of the Federal -aid recipients, sub -
recipients and contractors, whether such programs or activities are Federally funded or not);
• Titles II and III of the Americans with Disabilities Act, which prohibit discrimination on the basis
of disability in the operation of public entities, public and private transportation systems, places
of public accommodation, and certain testing entities (42 U.S.C. §§ 12131-12189) as
implemented by Department of Transportation regulations at 49 C.P.R. parts 37 and 38;
• The Federal Aviation Administration's Non-discrimination statute (49 U.S.C. § 47123) (prohibits
discrimination on the basis of race, color, national origin, and sex);
• Executive Order 12898, Federal Actions to Address Environmental Justice in Minority
Populations and Low -Income Populations, which ensures discrimination against minority
populations by discouraging programs, policies, and activities with disproportionately high and
adverse human health or environmental effects on minority and low-income populations;
• Executive Order 13166, Improving Access to Services for Persons with Limited English
Proficiency, and resulting agency guidance, national origin discrimination includes discrimination
because of limited English proficiency (LEP). To ensure compliance with Title VI, you must take
reasonable steps to -ensure that LEP persons have meaningful access to your programs (70 Fed.
Reg. at 74087 to 74100);
• Title IX of the Education Amendments of 1972, as amended, which prohibits you from
discriminating because of sex in education programs or activities (20 U.S.C. 1681 et seq).
City of Port Orchard and Apply A -Line, LLC
Public Works Project No. PW2021-012
Small Works Contract No. C051-21
Page 23 of 23
Rev 5/1/2020
SCHEDULE OF CONTRACT PRICES
2021 CITY ROAD STRIPING
NOTE; If a discrepancy between the numerical unit price and the written (words) unit price is found, the written
(words) unit price shall control.
Item #
1
Description of Work
Mobilization
Estimated
Quantity
1
Unit
Unit Bid Price
Total Item#
Amount
LS
$ 3,150.00
$ 3,150.00
2
3
4
5
6
7
SPCC Plan
1
1
LS
$ 850.00
$ 850.00
$ 6,550.00
$ 1,490.82
Temporary Traffic Control
4" Skip Stripe- White
4" Road Edge- White
8" Road Edge- White
LS
LF
$ 6,550.00
$ 0.06
24,847
177,192
LF
$ 0.08
$14,175.36
$ 2,932.93
22,561
LF
$ 0.13
8" Turn Pocket- White
11,150
LF
$ 0.13
$ 1,449.50
8
9
4" Skip Stripe- Yellow
16,884
LF
$ 0.06
$ 0.15
$ 1,013.04
4" Double Solid- Yellow
116,778
LF
$17,516.70
10
4" Skip/Single Solid- Yellow
39,338
LF
$ 0.10
$1.00
$ 3,933.80
$5,000.00
11 Minor Change
51000
LS
Total Bid: $ 58,062.15
SALES TAX
In accordance with Section 1-07.2(1) and DOR Rule 171, State Sales Tax: Work performed on City, County, or
Federally -owned land, the Contractor shall include Washington State retail sales taxes IN the various unit bid prices or
other amounts. These retail sales taxes shall include those the Contractor pays on purchases of materials, equipment,
and supplies used or consumed in doing the work.