080-19 - Beckwith Consulting Group - Supplement / Change Order 1CITY OF PORT ORCHARD
Authorization for Change Order #1
Date: 08/4/2021 Contractor: Beckwith Consulting Group
Project: Parks Plan Update P.O. Box 704
Contract / Job # C080-19 LaConner, WA 98257
360 466 3536
Brief Description of Change Order work (Documentation to be attached): This is a
change in the agreed upon contract termination date. The termination date is extended
from August 30, 2021, through September 30, 2021.
Contract History
Expiration
$ Date Appvd by]
Original Contract
$44,084.00
30-Aug-21
DCD-Director
Change Order
$0.00
30-Sep-21
DCD-Director
Total Contract $44,084.00
I have reviewed the Change Order information above and certify that to the best of my
knowledge descriptions and costs are true and accurate
Submitted by: Eck
Title: DCD Director 9 % 21
Change Orders over $15,000 up to $24,999 are to be
Approved by the Mayor.
Approved:
Attest:
Change Orders over $25,000 require
Council action.
Mayor
City Clerk
Council Approval Date
Common/CITY OF PORT ORCHARD change order
Page 1 of 1