029-21 - Skillings, Inc. - Supplement / Change Order 2CITY OF PORT ORCHARD
Authorization for Amendment No. 2
Date: June 15, 2022
Bethel & Lincoln Intersection
Project: Roundabout Design and ROW Phase
Contract / Job # CO29-21
Consultant: Skillings, Inc.
5016 Lacey Blvd. SE
Lacey, WA 98516
Description of reason for amendment:
This Change Order authorizes a time only change to the Agreement CO29-21. Section 3. Terms is
amended to read: This Agreement shall commence on February 9, 2021 ("Commencement Date") and
shall terminate December 31, 2023 unless extended or terminated in writing as provided herein. The
City reserves the right to offer two (2) one-year extensions prior to contracted expiration to retain the
selected company's services
Contract History
Amount Sales Tax Total Date Appvd by
Original Contract
$537,454.00
$0.00 1
$537,454.00
09-Feb-21
Council
Amendment#1
$196,900.00
$0,00
$196,900.00
25-Nov-20
Council
Amendment #2
$0.00
$0.00 1
$0.00
15-Jun-22
PW Director
$0.00
$0.00
Total Contract $734,354.00 $0.00 $734,354.00
I have reviewed the Change Order information above and certify that to the best of my knowledge
descriptions and costs are true and accurate.
Contractor Approval Signature
Printed Name & Title
Pu orks y r Ci ineer
MARK R. DORSEY, P.E.
Printed Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract Approved:
amount established by City Council can be approved by the Public
Works Director.
Change Orders that do not exceed 10%, with a maximum of Attest:
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action.
Mayor
City Clerk
Council Approval Date
Page 1