024-22 - Sascon, LLC - Supplement / Change Order 2CITY OF PORT ORCHARD
Authorization for Change Order No. 2
Date: 10/31/2022
Contractor: Sascon, LLC
Lippert Dr. Pavement Repair
Project: and Sidewalk Retrofit 20211 SE 210th St.
Contract / Job # CO24-22 Maple Valley, WA 98038
THIS CHANGE ORDER AUTHORIZES (add description).
Due to initial misinterpretation of the "working days" stated in the original contract, Change Order No. 1
extended the length of the contract to 10/31 /22. The "working days" were tracked throughout the project
per WSDOT Standard Specifications, Section 1-08. Change Order No. 2 authorizes extension of contract
CO24-22 by 10 "working days". The original 65 working days to complete the project will need to be
extended to complete the following bid items: A-4, A-9, A-10, A-14, A-15, A-17, A-18, A-19, A-20, A-21, A-
22, A-23, B-9, B-29. See MEMO for schedule of working days and more details.
Contract History
Amount Sales Tax Total Date Appvd b
Original Contract
$557,313.00
$0.00
$557,313.00
24-Ma -22
Council
Change Order 1
$0.00
$0.00
$0.00
03-Oct-22
Pw Director
Change Order 2
$0.00
$0.00
$0.00
31-Oct-22
Pw Director
Total Contract $557,313.00 $0.00 $557,313.00
I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
costs are true and accurate.
Z�)QiL"t 1�
Contractor Approval Signature
Derrick Sas - Owner
Printed Name & Title
Public Wci Director
Printed Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract Approved:
amount established by City Council can be approved by the Public
Works Director.
Change Orders that do not exceed 10%, with a maximum of Attest:
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action.
Mayor
City Clerk
Council Approval Date
U U—Capital Improvement Program\B_ActiveProjects\Street\LippertPavementRepair&SldewalkRetrofit\1.0 Financial Administration\1.6 Change Orders\Change Order No. 2\Change Order No. 2.doc