081-22 - Art Anderson Associates, Inc. - Contract Amendment 1CITY OF PORT ORCHARD
Authorization for Amendment No. 1
Date: November 17, 2022
Project: 390 Zone Low Pressure Booster
Station-Sedgwick
Contract / Job # C081-22
Contractor: Art Anderson Associates, Inc.
830 Pacific Avenue, Suite 200
Bremerton, WA 98337
THIS AMENDMENT AUTHORIZES THE FOLLOWING CHANGES TO THE AGREEMENT:
A time only extension - extending the Agreement termination date to June 30, 2023.
The Hydraulic model was in the process of being updated by our On Call consultant. The completed
Hydraulic model was necessary to begin this project.
C081-22, Section 4. Duration of Agreement is amended to read as follows: This Agreement shall be in full force
and effect for a period commencing on June 14, 2022 and ending June 30, 2023 unless sooner terminated under
the provisions of this Agreement.
In all other respects the Underlying agreement between the parties shall remain in full force and effect, amended
as set forth herein, but only as set forth herein.
Contract History
Amount Sales Tax Total Date Apavd b
Original Contract
$205,041.00
$0.00
$205,041.00
14-Jun-22
Council
Amendment 1
$0.00
$0.00
$0.00
17-Nov-22
PW Director
Total Contract $205,041.00 $0.00 $205,041.00
I have reviewed the Change Order information above and certify that to the best of my knowledge
descriptions and costs are true and accurate.
Contractor Approval Signature Public Works Director•
Brad Ginn, VP of A&E
Printed Name & Title
Tonv Lan
Printed Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract
amount established by City Council can be approved by the Public Approved:
Works Director.
Change Orders that do not exceed 10%, with a maximum of
$100,000, of either legally authorized budget limit or contract Attest:
amount established by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action.
Mayor
City Clerk
Council Approval Date