029-22 - Consor North America, Inc.-Murraysmith - Contract Amendment 1DocuSign Envelope ID: 14FCD201-078F-40A9-A4F1-666B72A62A6C
CITY OF PORT ORCHARD
Authorization for Amendment No. 1
Date: January 10, 2023
Project: 2023 General Sewer Plan
Update for the City's
Sanitary Sewer System
Contract / Job # CO29-22
Contractor: CONSOR North America, Inc
600 University Street, Suite 300,
Seattle, WA 98101
THIS AMENDMENT AUTHORIZES THE FOLLOWING CHANGES TO THE AGREEMENT:
1. A company name change from Murraysmith, Inc. to CONSOR North America, Inc.
3. A Contract increase of $23,124 for a "Time and Materials Not to Exceed" total of $140,396.
In all other respects the Underlying agreement between the parties shall remain in full force and effect,
amended as set forth herein, but only as set forth herein.
Amendment No. 1 is for additional and necessary work associated with the City of Port Orchard (City) General
Sewer Plan Update.
Contract History
Amount Sales Tax Total Date Appvcl b
Original Contract
$117,272.00
$0.00
$117,272.00
22-Feb-22
Council
Amendment 1
$23,124.00
$0.00
$23,124.00
10-Jan-23
Council
Total Contract $140,396.00 $0.00 $140,396.00
I have reviewed the Amendment information above and certify that to the best of my knowledge
descriptions and costs are true and accurate.
-
Consultant Approval Signature Public Works Director/City Engineer
Erika Schuyler, PE, PIMP, Regional Manager Tony Lang
Printed Name & Title Printed Name DocuSignedby:
Approved: 96b P4a&A SWA,
Change Orders that do not exceed 10%, with a maximum of 771
I II''11
$50,000, of either legally authorized budget limit or contract
amount established by City Council can be approved by the Public sc aanaas
Works Director. Attest:
Change Orders that do not exceed 10%, with a maximum of
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action.
City Clerk
January 10, 2023
Council Approval Date
Page 1
DocuSign Envelope ID: 14FCD201-078F-40A9-A4F1-666B72A62A6C
AMENDMENT NO. 1 TO CONTRACT NO. CO29-22
CITY OF PORT ORCHARD AGREEMENT WITH
CONSOR North America, Inc
THIS AMENDMENT No. 1 ("Amendment") to Contract No. CO29-22 is entered into between the City of Port
Orchard, a Washington municipal corporation ("City" or "Port Orchard") and CONSOR North America, Inc., an
Oregon corporation ("Consultant"). City and Consultant are each a "Party" and together "Parties" to this
RECITALS:
WHEREAS, due to limitations of in-house staff, the City utilizes a professional engineering firm to
provide Comprehensive Plan Updates for the City's Sanitary Sewer System; and
WHEREAS, following a successful procurement process on February 22, 2022, the City executed a
Professional Services Agreement for the 2023 General Sewer Plan Update for the City's Sanitary Sewer
System, Contract No. CO29-22 with the Consultant ("Underlying Agreement"); and
WHEREAS, on October 3, 2022, the "Consultant" changed its entity name from Murraysmith, Inc
to CONSOR North America, Inc; and
WHEREAS, additional efforts are required for the General Sewer Plan Update for the City's
Sanitary Sewer System, and the Parties have memorialized these additional subtasks (within the scope of
initial project procurement) as set out in Exhibit A attached hereto; and
WHEREAS, the Consultant and the City have conferred and agreed to increase the "time and
materials, not to exceed" amount Section 3 (Payment), of the agreement as described herein and in
Exhibit B attached hereto; and
WHEREAS, the parties wish to memorialize their agreement and so extend the Underlying
Agreement;
NOW, THEREFORE, in consideration of the mutual benefits accruing, it is agreed by and between the
parties thereto as follows:
FIRST AMENDMENT TO AGREEMENT:
1. Amendment.
a. The Consultant entity name is changed from Murraysmith, Inc to CONSOR North America,
Inc.
b. Section 3A. Payment, of the Agreement, is hereby amended to read as follows:
Compensation under this Agreement will be on a "time and materials not to exceed" basis,
based on the fees included for each approved task assignment, provided total compensation
Amendment No.1 to Agreement between City of Port Orchard and CONSOR North America, Inc
Contract No.0O29-22
updated 4/2022 IBDR
Page 2
DocuSign Envelope ID: 14FCD201-078F-40A9-A4F1-666B72A62A6C
for these services shall not exceed $140,396 (inclusive of all amounts paid prior to the
execution of Amendment 1 to this Agreement), without written authorization, and will be
based on the list of billing rates and reimbursable expenses attached hereto as Exhibit B.
2. Severability. The provisions of this Amendment are declared to be severable. If any provision of this
Amendment is, for any reason, held to be invalid or unconstitutional by a court of competent
jurisdiction, such invalidity or unconstitutionality shall not affect the validity or constitutionality of
any other provision.
3. Entire Agreement. The written provisions and terms of this Amendment shall supersede all prior
verbal statements of any officer or other representative of the parties, and such statements shall
not be effective or be construed as entering into or forming a part of or altering in any manner
whatsoever, this Amendment. The entire agreement between the Parties with respect to the
subject matter hereunder is contained in the Agreement and exhibits thereto, any prior executed
amendments and this Amendment. Should any language in any of the Exhibits to the Agreement
or prior amendments conflict with any language contained in this Amendment, then this
Amendment shall prevail. Except as modified by this Amendment, all other provisions of the
original Agreement and any amendments thereto not inconsistent with this Amendment shall
remain in full force and effect.
4. Effective date. This Amendment shall be effective as of January 10, 2023.
DATED this 10th day of January 2023.
CI da€ NTQRCHARD, WASHINGTON
jQb� �IMGIA,Itt,SIA.U.
Robert Putaansuu, Mayor
T�j AWPN:E NTI CATE D:
Brandy Wallace, MMC, City Clerk
k0dAS TO/. FORM:
Charlotte A. Archer, City Attorney
CONSULTANT
C �L_
Signature
Erika Schuyler, PE, PMP, Regional Manager
Printed Name and Title
Amendment No.1 to Agreement between City of Port Orchard and CONSOR North America, Inc
Contract No.0O29-22
Updated 4/2022 IBDR
Page 3
DocuSign Envelope ID: 14FCD201-078F-40A9-A4F1-666B72A62A6C
EXHIBIT A
SCOPE OF SERVICES
2023 General Sewer Plan Update
Amendment 1
City of Port Orchard
Introduction
Consor North America, Inc. (Consor) has developed the following scope of services and accompanying
engineering fee estimate for Amendment 1 to Contract CO29-22 for additional services associated with the
City of Port Orchard (City) General Sewer Plan Update. The need for these services is because the City
requested that Consor provide visual condition assessments for the mechanical, structural, and electrical
components for a portion of the City's sewer pump stations.
The scope of services and fee for this amendment have been developed based on discussions with City staff
and our understanding of the additional project elements.
The additional services defined herein for pump station condition assessments beyond the previously
authorized contract amount for the General Sewer Plan work consist of services supplementing the
following tasks from the original scope of work.
➢ Task 1— Project Management
➢ Task 6 — Sewer System Evaluation
Project Understanding and Assumptions
The scope of services for Amendment 1 was developed based on the following assumptions.
➢ The following pump stations will be assessed for mechanical and structural condition:
o Canyon Court
o Cedar Heights
o Eagle Crest
o Flower Meadows
o Golden Pond
o Harrison Hospital
o Pottery
o Sedgwick
Consor • December 2022 • City of Port Orchard
2023 GSP Update Amendment 1 • 1
DocuSign Envelope ID: 14FCD201-078F-40A9-A4F1-666B72A62A6C
o Tremont Place
o Ridge 1&2
o Ridge 3
o McCormick Meadows
o Lowe's
➢ The following pump stations will be assessed for electrical condition:
o Canyon Court
o Harrison Hospital
o Pottery
o Ridge 1&2
o Ridge 3
o McCormick Meadows
o Lowe's
➢ The condition assessment results will be incorporated into Section 6 of the GSP.
Scope of Services
Consultant will perform the following services.
Task 1 - Project Management
Objective
Provide overall leadership and team strategic guidance aligned with City staff objectives. Coordinate,
monitor, and control the project resources to meet the technical, communication, and contractual
obligations required for developing and implementing the project scope.
Activities
1.4 Coordination with Subconsultants
Manage and coordinate the technical and scope issues of the overall project. Progress meetings will be
conducted as appropriate.
Coordinate with Subconsultants on specific tasks, scope, and budget. Conduct progress meetings as
appropriate.
Consor • December 202 • City of Port Orchard
2023 GSP Update Amendment 1 • 2
G:\PDX_BD\Clients\Port Orchard\2023 General Sewer Plan Update\Scoping\Amendment 1 Condition Assessment\COPO GSP Amendment 1 - Scope of Work_ final_V2.docx
DocuSign Envelope ID: 14FCD201-078F-40A9-A4F1-666B72A62A6C
1.7 Quality Assurance/Quality Control (QA/QC)
Conduct QA/QC reviews at all major deliverable milestones prior to submitting review packages to the City.
Assumptions
➢ Work under this amendment will increase the originally assumed project duration by up to two (2)
months.
➢ Project schedule will be updated once for the work associated with this amendment.
Task 6 — Pump Station Condition Assessments
Objective
Develop pump station condition assessment criteria and tracking forms. Each criterion to have a numeric
score associated with it based on importance to facilitate ranking pump stations based on condition needs.
Activities
Subtask 6.5 Pump Station Condition Assessments
Submit criteria and forms to City for approval prior to assessing pump stations.
Conduct pump station condition assessment site visits with City staff. Evaluate the condition of major
station components by visual inspection documenting the general condition of the structural, electrical,
and mechanical systems that comprise the stations. Assign a condition rating to document the site visit
using the tracking form.
Participate in review meeting with the City after site visits have been completed and tracking forms filled
out.
Task Deliverables
➢ Criteria and methodology for condition assessment scoring, likelihood of failure, and consequence
of failure
➢ Tracking form example
➢ Completed tracking forms post assessments
Assumptions
➢ Pump station condition assessment assumes three (3) Consultant team members (two from Consor
and one from ISI) for 1 hour per station for 13 pump stations as noted above. Electrical assessments
will be performed at 7 pump stations as noted above.
➢ Structural assessment is visual inspection only and does not include material testing of any kind.
➢ Review meeting to last one (1) hour and will be attended by three (3) Consultant team members
(two from Consor and one from ISI).
Consor • December 2022 • City of Port Orchard
2023 GSP Update Amendment 1 • 3
G:\PDX_BD\Clients\Port Orchard\2023 General Sewer Plan Update\Scoping\Amendment 1 Condition Assessment\COPO GSP Amendment 1- Scope of Work_ final_V2.docx
DocuSign Envelope ID: 14FCD201-078F-40A9-A4F1-666B72A62A6C
Budget
The detailed fee estimate is provided as Exhibit B.
Payment will be made at the Billing rates for personnel working directly on the project, which will be made
at the Consultant's Hourly Rates, plus Direct Expenses incurred. Subconsultants, when required by the
Consultant, will be charged at actual costs plus a 10 percent fee to cover administration and overhead.
Direct expenses will be paid at the rates shown in the table below.
Direct Expenses
Expenses incurred in-house that are directly attributable to the project will be invoiced at actual cost. These
expenses include the following.
Computer Aided Design and Drafting $18.00/hour
GIS and Hydraulic Modeling $10.00/hour
Mileage Current IRS Rate
Postage and Delivery Services At Cost
Printing and Reproduction At Cost
Travel, Lodging and Subsistence At Cost
Project Schedule
Work will begin upon receipt of a signed contract amendment and notice to proceed, or other agreeable
written authorization. Work will proceed in a timely manner with an anticipated completion date two
months from notice to proceed. The project duration is based on timely input, information, City staff
availability to access assessed stations, and review comments from City staff.
Consor • December 202 • City of Port Orchard
2023 GSP Update Amendment 1 • 4
G:\PDX_BD\Clients\Port 0rchard\2023 General Sewer Plan Update\Scoping\Amendment 1 Condition Assessment\COPO GSP Amendment 1 -Scope of Work_fina l_V2.docx
DocuSign Envelope ID: 14FCD201-078F-40A9-A4F1-666B72A62A6C
2023 GENERAL SEWER PLAN UPDATE - AMENDMENT 1
CITY OF PORT ORCHARD
PROPOSED FEE ESTIMATE
LABOR
CLASSIFICATION (HOURS)
Principal Engineer
VI
Professional
Engineer IX
Engineering
Designer III
Hours
Labor
Subconsultants
Multiplier
% Markup
Subconsultant Total with
Markup
Expenses
CADD Units $18/hr
GIS Units $10/hr
Total
E&IC
Task 1- Project Management
Task 1.4 - Coordination with Subconsultants
1
3
4
$ 1,043
1.1
$
$
$
$
$ 1,043
Task 1.7 - Quality Assurance/Quality Control (QA/QC)
2
2
$ 617
1.1
$
$
$
$
$ 617
Task 1 Subtotal
3
3
0
6
$ 1,660
$ -
$
$ -
$
$
$ 1,660
Task 6 - Pump Station Condition Assessments
Task 6.5 - Pump Station Condition Assessments
22
22
44
$ 9,379
$ 10,850
1.1
$ 11,935
$ 150
$
$
$ 21,464
Task 6 Subtotal
0
2?
2?
44
$ 9,37t9$
10,850
$ 11,935
$ 150
$
$
$ 21,464
TOTAL -ALL TASKS
3
25
22
50
$ 11,03
10,850
$ 11,935
$ 150
$
$
$ 23,124
City of Port Orchard GSP Amendment 1
December 2022 Consor Page 1
G:\PDX_BD\Clients\Port Orchard\2023 General Sewer Plan Update\Scoping\Amendment 1 Condition Assessment\COPO GSP Amendment 1 Fee Estimate 2022 Rates_final_V2