025-20 - BHC Consultants, LLC - Contract Amendment 111 CITY OF PORT ORCHARD
Date:
Project:
Contract / Job #
Authorization for Amendment No. 1
November 5, 2020
Water Concurrency
CO25-20
Contractor: BHC Consultants, LLC
1601 Fifth Avenue, Suite 500
Seattle, WA 98101
THIS CHANGE ORDER AUTHORIZES A TIME EXTENSION ONLY. CONTRACT END DATE EXTENDED TO
March 31st, 2021.
Contract History
Amount Sales Tax Total Date Appvd by
Original Contract
$0.00
$0.00
$0.00
16-Jan-20
Council
Change Order 1
$0.00
$0.00
$0.00
05-Nov-20
PW Director
Total Contract $0.00 $0.00 $0.00
I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
costs are true and accurate.
s
Contractor Approval Signature
James Gross, Executive Vice President
Printed Name & Title
Public Works Dir for ity Engineer
MARK R. DORSEY, P.E.
Printed Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract Approved:
amount established by City Council can be approved by the Public
Works Director.
Change Orders that do not exceed 10%, with a maximum of Attest:
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor.
Mayor
City Clerk
Change Orders over $100,000 or exceed a total of 10% require
Council Action. k\WrU1D7PP\BHC Contract Amendment 1 Water Concurrency doc