079-22 - KCI Technologies, Inc. - Contract Amendment 1CITY OF PORT ORCHARD
Authorization for Amendment No. 1
Date: February 27, 2023 Contractor: KCI Technologies, Inc
Project: Asset Management Program 936 Ridgebrook Road
Strategic Planning Phase Sparks, MD 21152-9390
Consultant
Contract / Job # rmq-77
THIS AMENDMENT AUTHORIZES THE FOLLOWING CHANGES TO THE AGREEMENT: A time only extension -
extending the termination date to March 31, 2023. C079-22, Section 4. Duration of Agreement is amended
to read as follows: This Agreement shall be in full force and effect for a period commencing on August 9,
2022 and ending March 31, 2023 unless sooner terminated under the provisions of this Agreement.
In all other respects the Underlying agreement between the parties shall remain in full force and effect, amended
as set forth herein, but only as set forth herein.
This Time Only amendment is needed to allow the Consultant additional time to complete the project and staff
time to review and comment on the final product.
Contract History
Amount Sales Tax Total Date Appvd b
Original Contract
$99,932.80
$0.00
$99,932.80
10-Au -22
Council
Amendment 1
$0.00
$0.00
$0.00
27-Feb-23
PW Director
Total Contract $99,932.80 $0.00 $99,932.80
I have reviewed the Amendment information above and certify that to the best of my knowledge
descriptions and costs are true and accurate.
Consultant Approval Signature
Heidi Hammel, Vice President
Printed Name & Title
X.n-
Public Works Director
Tony Lang
Printed Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract
amount established by City Council can be approved by the Public Approved:
Works Director.
Change Orders that do not exceed 10%, with a maximum of
$100,000, of either legally authorized budget limit or contract Attest:
amount established by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action.
Mayor
City Clerk
Council Approval Date