041-20 - American West Construction, LLC - Supplement / Change Order 1II CITY OF PORT ORCHARD I
Authorization for Change Order No. 1
Date: 6/3/2020 Contractor: American West Construction, LLC
2020 Library Water Damage
Project: and Roof Repair 2SZ28 Baker St. ##287
Contract / Job # C041-20
Black Diamond, WA 98010
THIS CHANGE ORDER AUTHORIZES A TIME EXTENSION ONLY — EXTEND CONTRACT END DATE TO JUNE
301h, 2020.
I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
Costs are true and accurate.
Cont ctor Approv Signature Public Works Difector/City Engineer
Prirltled Name & Title
MARK R. DORSEY, P.E.
Printed Name
Change Orders that do not exceed 10%, ,with a maximum of
$50,000, of either legally authorized budget limit or contract Approved:
amount established by City Council can be approved by the Public
Works Director.
Change Orders that do not exceed 10%, with a maximum of Attest:
$100,000, of either legally authorized budget limit or contract
amount estabiished by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action.
Mayor
City Clerk
Council Approval Date