059-20 - Aqua Tech, LLC - Supplement / Change Order 1CITY OF PORT ORCHARD
Authorization for Change Order No. 1
Date: June 12, 2021
Project: McCormick Woods STEP
System Retrofit
Contract / Job # C059-20
Contractor: Aqua Tech LLC
III Sparrow Court
Port Ludlow, WA 98365
This Change Order Authorizes a contract extension only due to delays in Labor & Industries (L&I)
inspections of completed work. Contractor is waiting for L&I to inspect final 3 residences. C059-20
shall be extended to June 30, 2021.
Contract History
Amount Sales Tax Total Date Appvd b
Original Contract
$583 209.42
$52 488.85
$635 698.27
22-Se -20
Mayor
Change Order 1
$0.00
$0.00
$0.00
12-Jun-21
PW DIRECTO
Total Contract $583 209.42 $52,488.85 $635 698.27
I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
costs are true and accurate.
Contractor Approval Signature
Robert Thurston, Principal
Printed Name & Title
r% Z
Pubic rks Dir r/City Engineer
MARK R. DORSEY, P.E.
Printed Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract Approved:
amount established by City Council can be approved by the Public
Works Director.
Change Orders that do not exceed 10%, with a maximum of Attest:
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor.
Change Ordersover $100,000 orexceed a total of 10% require
Council Action.
Mayor
City Clerk
Council Approval Date
Page 1