059-20 - Aqua Tech, LLC - Supplement / Change Order 2II CITY OF PORT ORCHARD
Authorization for Change Order No. 2
Date: June 29, 2021
Project: McCormick Woods STEP
System Retrofit
Contract / Job # C059-20
Contractor: Aqua Tech LLC
111 Sparrow Court
Port Ludlow, WA 98365
This Change Order Authorizes a contract extension only due to delays in Labor & Industries (L&I)
inspections of completed work. Contractor is waiting for L&I to inspect final 2 residences. C059-20
shall be extended to July 31, 2021.
Contract History
Amount Sales Tax Total Date Appvd b
Original Contract
5583,209.42
552.488.85
$635,698.27
22-Se -20
Mayor
Change Order 1
$0.00
$0.00
$0.00
12-Jun-21
PW DIRECTOR
Change Order 2
$0.00
$0.00
$0.00
29-Jun-21
PW DIRECTOR
Total Contract $583,209.42 $52,488.85 $635,698.27
I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
costs are true and accurate.
A eAt-��
Contractc r Approval Signature
Robert Thurston, Owner
Printed Name & Title
w
Public or/City Engineer`
MARK R. DORSEY, P.E.
Printed Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract Approved:
amount established by City Council can be approved by the Public
Works Director.
Change Orders that do not exceed 10%, with a maximum of Attest:
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor.
Change Orders oeer $100,000 or exceed a total of 10% require
Council Action.