125-22 - KR Homes, LLC - Supplement / Change Order 1CITY OF PORT ORCHARD
Authorization for Change Order No. 1
Date: 5/19/2023 Contractor:
Sroufe Water Main
Project: Replacement
Contract / Job # C125-22
KR Homes, LLC
PO Box 856
Winlock, WA 98596
THIS CHANGE ORDER AUTHORIZES (add description).
Addition of 12" DI casings to protect existing water mains at side sewer crossings in two locations.
Extension of contract C125-22 by one working day to accommodate additional work for a total of 66
working days.
Amount
Contract History
Sales Tax Total Date Appvc1 b
Original Contract
$290 790.00
$26 752.68
$317,542.68
28-Mar-23
Council
Change Order 1
$8 249.82
$767.23
$9 017.05
19-Ma -23
PW Director
Total Contract $299,039.82
$27 519.91 $326,559.73
I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
costs are true and accurate.
Contractor Approval ignature Public Works Director
&" ,- V(00AA,2J Tony Lang
Printed Name & Title Printed Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract Approved:
amount established by City Council can be approved by the Public
Works Director.
Change Orders that do not exceed 10%, with a maximum of Attest:
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action.
Mayor
City Clerk
Council Approval Date
UA3 Capital Improvement Program\B_ActiveProjects\WaterUtility\Sroufe Water Main Replacement\1.0 Financial\1.6 Change Orders\CO#1\Chang7 Order #1.doe
Page 1