125-22 - KR Homes, LLC - Supplement / Change Order 3CITY OF PORT ORCHARD Authorization for Change Order No. 3 Date: 6/1/2023 Contractor: KR Homes, LLC Project: Sroufe Water Main PO Box 856 Replacement Contract / lob # C125-22 Winlock, WA 98596 THIS CHANGE ORDER AUTHORIZES THE FOLLOWING CHANGES TO THE CONTRACT: 1. Extension of contract C125-22 by one working day to accommodate additional work for a total of 67 working days. 2. Addition of casing pipes and end seals for water main and hydrant lateral underneath side sewer force main need to be added. The location of existing side sewer laterals was not known prior to design. This change will increase the contract by $8,558.97. Details for this contract increase/change order is attached. In all other respects the Underlying agreement between the parties shall remain in full force and effect, amended as set forth herein, but only as set forth herein. Amount Contract History Sales Tax Total Date Appvd b Original Contract $290,790.00 $26,752.68 $317,542.68 28-Mar-23 Council Change Order 1 $8,249.82 $767.23 $9,017.05 19-Ma -23 PW Director Change Order 2 $7,021.32 $943.77 $7,965.09 22-Ma -23 PW Director Change Order 3 $7,830.71 $728.26 $8,558.97 01-Jun-23 PW Director Total Contract $313,891.85 $29,191.94 $343,083.79 I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and costs are true and accurate. Contractor Appr4Sature Public Works Director Tony Lang Printed Name & Ti le Printed Name Change Orders that do not exceed 10%, with a maximum of $50,000, of either legally authorized budget limit or contract Approved: amount established by City Council can be approved by the Public Works Director. Change Orders that do not exceed 10%, with a maximum of Attest: $100,000, of either legally authorized budget limit or contract amount established by City Council are to be approved by the Mayor. Change Orders over $100,000 or exceed a total of 10% require Council Action. Mayor City Clerk Council Approval Date Sroufe Watermain Extension KR HOMES LLC Request For Compensation May 31, 2023 Kurt Reddig Date of Request offfice@krhomes.org 360-864-5500 Office COR # 3 To: City of Port Orchard Attention: Christian Williams Reason for Compensation: Install 12' DI casing's for hydrant lateral & SS lateral near Tacoma and Sroufe. Request for additional days 1 Day / s Materials and Equipment Totals Column Yds, Tons, LS Rate Deduct for 11' of 1" Poly 11 LF $ (0.51) $ (5.61) HD Fowler Materials casing n seals 1 LS $ 2,596.52 $ 2,596.52 Hours Rate Kubota 55 Excavator 10 $ 75.00 $ 750.00 JD 35G Excavator $ 65.00 $ - Attachment Hammer/Breaker $ 27.00 $ - Skid Steer $ 65.00 $ - Pipe Truck/Pickup 10 $ 24.00 $ 240.00 Chain Saws, oil, gas, tools $ 26.00 $ - Dump Truck $ 100.00 $ - Small Tools/Supplies 10 $ 11.00 $ 110.00 Materials and Equipment Cost $ 3,690.91 Labor Flaggers Hours Wage Rate Tax/WC/Tri Safety $ 51.00 $ 11.00 $ 11.00 $ - $ 51.00 $ 11.00 $ 11.00 $ Labor Cost Trucker $ 70.86 $ 11.00 $ 3.00 $ - Labor 20 $ 56.81 $ 11.00 $ 3.00 $ 1,416.20 Operator 10 $ 75.51 $ 11.00 $ 3.00 $ 895.10 Supervisor 3 $ SS.00 $ 11.00 $ 3.00 $ 297.00 Labor Cost $ 2,608.30 Mobilization Mobilize Equipment Each $ - $ - Mobilization Cost $ - Subcontractors Subcontract Cost $ Costs w/ Markup Cost Mark Up Totals Materials and Equipment $ 31690.91 0% 21% $ 4,466.00 Labor $ 2,608.30 0% 29% $ 3,364.71 Mobilization $ - 0% 0% $ - Subcontractors $ - 0% 21% $ - Total Compensation Requested $ 7,830.71 For KR HOMES, LLC Authorized Signature