125-22 - KR Homes, LLC - Supplement / Change Order 2CITY OF PORT ORCHARD
Authorization for Change Order NO.2
Date: 5/22/2023 Contractor: KR Homes, LLC
Project: Sroufe Water Main PO Box 856
Replacement
Contract / Job # C125-22
Winlock, WA 98596
THIS CHANGE ORDER AUTHORIZES THE FOLLOWING CHANGES TO THE CONTRACT:
1. Sales Tax Increase: January 1, 2023, the Washington State Sales Tax rate increased in the City of
Port Orchard from 9.2% to 9.3% increasing the original contract by $290.79.
2. Removal of a large maple tree in the right of way at 673 Sroufe St to accommodate the water
main being installed. A contract increase of $7,674.30.
In all other respects the Underlying agreement between the parties shall remain in full force and
effect, amended as set forth herein, but only as set forth herein.
Contract History
Amount Sales Tax Total Date Appvd b
Original Contract $290,790.00 $26,752.681 $317,542.68 28-Mar-23 Council
Change Order 1 $8,249.82 $767.23 $9,017.05 19-Ma -23 PW Director
[Change Order 2 $7,021.32 $943.77 $7,965.09 22-May-23 Pw Director
otal Contract $306,061.14 $28,463.68
I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
costs are true and accurate
—7—
Contractor Approval Signature Public Works Director
OW > Tony Lang
Printed Name & Title Printed Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract Approved:
amount established by City Council can be approved by the Public
Works Director.
Change Orders that do not exceed 10%, with a maximum of Attest:
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action,
Mayor
City Clerk
Council Approval Date