Loading...
075-22 - Ceccanti, Inc. - Supplement / Change Order 2DocuSign Envelope ID: 4D6FEF55-E997-4328-A022-8A4EF4D14C08 CITY OF PORT ORCHARD Authorization for Change Order No. 2 Date: 6/14/2023 McCormick Village Park Splash Pad Treatment Facility Project: Installation Contract / Job # C075-22 Contractor: Ceccanti, Inc. 4116 Brookdale Road East Tacoma, WA 98446 THIS CHANGE ORDER AUTHORIZES (add description). Additional work: Work Change Directive 1-S4,3M.00- Unsuitable subgrade Found at the invert elevation of the resen-oir. Solution was provided by Consur to over -excavate approximately 12" until Firmer subgrade was found Place geotextile fabric in the hole (leave extra for wrapping). Fi Il over -excavation with 2"x4" quarry spalls. Wrap Fabric ovt r spal is I ike a burrito. Use either top course or bast; course to dress on top of the wrap and under the structure to density and grade. Work Change Directive 2-5221.,.0;;- Relocation of tine 24"x24" Louvered Grill to the north face of building and the addition of the l-hour Eire barrier intended to meet Li 414.2.1 construction requirements. See attached Cost Summary Sheet for break down. Work Change Directive 3-S1-800.D0- Existing, solenoid manifolds (2) for the splash pad are in two vaults at the edge of the splash pad. The manifolds currently leaf extensively and are very dirficult to winterize. Change Directive 93 authorizes the manifold and solenoids to be relocated into the mechanical building. The manifold is to be rebuilt using, new components, existinu solenoids to be rLuscd. Total of Work Change Directive 1. 2, and 3- 58,393.05 ulttS 9.3':o WST=S9,173.60 Contract History Amount Sales Tax Total Date Appvd b Original Contract $540,647.00 $49,739.52 $590,386.52 26-Jul-22 Council Change Order 1 $126,803.00 $12,333.33 $139,136.33 28-Feb-23 Council Change Order 2 $8,393.05 $780.55 $9,173.60 27-Jun-23 Council Total Contract $675,843.05 $62,853.40 $738,696.45 I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and costs are true and accurate. Contractor Approval Signature Public Works Director Donna Motfand, Corporate Secretary Printed Name & Title Tony Lang Printed Name Change Orders that do not exceed 10%, with a maximum of $50,000, of either legally authorized budget limit or contract Approved amount established by City Council can be approved by the Public Works Director. Change Orders that do not exceed 10%, with a maximum of Attest $100,00Q, of either legally authorized budget limit or contract amount established by City Council are to be approved by the Mayor. Change Orders over $100,000 or exceed a total of 10% require Council Action. DocuSigned by: [—`b p IN 6lA.bt,sw Ma orpocuSignedbyy::'1 6VA141 (IALAtt City Clerk approval date Council Approval Date DocuSign Envelope ID: 4D6FEF55-E997-4328-A022-8A4EF4D14C08 City of Port Orchard Date: May 24, 2023 Work Change Directive: 1 Project: McCormick Villatie Park Splash Pad Retro Engineer: Consor Contractor: Ceceanti, Inc Subject: Unsuitable Reservoir Subgrade- Over Excavate, Geo fabric, Spalls, CSBC The following information/clarifcation further explains the Scope of TVork: The City, Consor and Contractor have jointly resolved unsuitable subgrade found at the invert elevation of the reservoir. Our recommendation is as follows: 1. Over -excavate approximately 12" until firmer subgradc is found, 2. Place geotextile fabric in the hole (leave extra for wrapping). 3. Fill over -excavation with 2"x4" quarry spalls. 4. Wrap fabric over spalls like a burrito- 5. Use either top course or base course to dress on top of the wrap and under the structure to density and grade. The intent of the change is to ensure reservoir is set on firm and unyielding material. Bid Item A I I- Over excavation is being investigated. All activities will be tracked via force account. Estimated Costs: 2x4 Quarry Spalls $250.00 1 %J Crushed Rock S65.00 Geofabric S65.00 Chevy 6500 (5) Inc. mark up $445,00 Volvo 1201~ (5) Inc. mark up $575.00 Deere 245 G LC (5) 1ne. markup $800.00 Kenworth T-880 (5) Inc. mark up $680,00 Labor x 3 (5) Inc. mark up $1500.00 Total ($4,380.00) Costing: ❑ Not -to -Exceed Price of S 00.00 Actual costs will be submitted after the above scope of work is complete. ❑ Lump Sum Price of S (additive / deductive). ® Force Account. Per General Conditions 1-09.6. Provide daily breakdown for costs associated with above scope of work Contract Tinte changes shall be submitted as follows: Increase/decrease in Contract Time; Method of determining change in Contract Times: Substantial Complete: zero days ❑ Actual Days Required Final Completion days ❑ Acceptance of Contractor Estimate Z Other If the change involves an increase, the Estimated times are not to be exceeded without further authorization. Attachments: Recom n 14 �dy E gineer Date Approved By: r _ /r/.20'p—rOwnerDat Accepted By. DocuSign Envelope ID: 4D6FEF55-E997-4328-A022-8A4EF4D14C08 Citv of Port Orchard Date: June 2, 2023 Work Change Directive: 2 Project: McCormick Village Park Spiash Pad Retro Engineer: Consor Contractor: Ceccanti, Inc Subject: Relocate Louver to North Face, Addition of Fire Wall ?"he following inforntation/elaryication further explains the Scope of Work: Consor has provided a sotution to the CO PO DCD Review Matrix. Relocation of the 24"x24" Louvered Grill to the north face of the building as shown on the revised sheet A 1.0. Addition of the I -Hour Dire Barrier Walls as shown on the revised sheet A 1.0. The design is being modified to move the louver so that it does not face the wetland to the east_ When opened, the louver will allow some sound to escape the building. The loudest piece of equipment anticipated in the building will be the booster pump which when in operation will run at an estimated 65-80 decibels_ Addition of the 1-hour fire barrier wall are intended to meet IBC 414.2.IConstruction requirements. Costing: N.ot-tp-Exceed Price of $ 00.00 Actual costs will be submitted after the above scope of work is complete. ❑ Lump Surn Price of $ additive / deductive). Time and Material estimate 42,213.05 ❑ Force Account. Per General Conditions 1-09.6. Provide daily breakdown for costs associated with above scope of work Contract Time changes shall be submitted as follows: Increase/decrease in Contract Time: Method of determining change in Contract Times; Substantial Complete: Zero clays ❑ Actual Days Required Final Completion days ❑ Acceptance of Contractor Estimate ® Other If the change involves an increase, the Estimated times are not to be exceeded without further authorization. Attachments: RecommgMed By: En ineer Date Approved By: Owner Date Accepted Bv: Contractor Date Incorporated into Change Order DocuSign Envelope ID: 4D6FEF55-E997-4328-A022-8A4EF4Dl4C08 Date: June 7� 2023 Work Change Directive: 3 Project: McCormick Village Park Splash Pad Retro Engineer: Consor Contractor: Ceccanti, Inc Subject; Rebuild Solenoid Manifolds Tire following informalionlelarification further explains the Scope of Work: Existing solenoid manifolds (2) for the splash pad are in two vaults at the edge of the splash pad. The manifolds currently leak extensively and are very difficult to winterize. Change Directive 93 authorizes the manifold and solenoids to be relocated into the mechanical building. The manifold is to be rebuilt using new components, existing solenoids to be reused. Costing: ® Nat -to -Exceed Price of $ 1800.00 Actual costs will be submitted after the above scope of work is complete. ❑ Lump Sum Price of $ (additive 1 deductive)_ ❑ Force Account. Per General Conditions 1-09.6. Provide daily breakdown for costs associated with above scope of work Contract Time changes shall be submitted as follows: increaseldecrease in Contract Time: Method of determining change in Contract Times: Substantial Complete: Zero days ❑ Actual Days Required Final Completion days ❑ Acceptance of Contractor Estimate ® Other If the change involves an increase, the Estimated times are not to be exceeded without further authorization. Attachments: Recommend' y: Engi eer Approved By: Owner Date Accepted By: antractor Date Incorporated into Change Order