005-23 - Consor North America, Inc. - Contract Amendment 1CITY OF PORT ORCHARD
Authorization for Amendment No. 1
Date: July 27, 2023 Contractor: CONSOR North America, Inc
Project: McCormick Village Park Splash 600 University Street, Suite 300
Pad Construction Support Seattle, WA 98101
Contract / Job # C005-23
THIS AMENDMENT AUTHORIZES THE FOLLOWING CHANGES TO THE AGREEMENT:
A time only extension - extending the Agreement termination date to November 30, 2023. Agreement
0005-23, Section 4 Duration of Agreement is amended to read as follows: This Agreement shall be in full
torce and effe—ct fo- r a perioTcommencing on January 24, 2023, and ending November 30, 2023, unless
sooner terminated under the provisions of this Agreement.
In all other respects the Underlying agreement between the parties shall remain in full force and effect,
amended as set forth herein, but only as set forth herein.
Contract History
Amount Sales Tax Total Date Appvd b
Original Contract
$57,475.00
$0.00
$57,475.00
24-Jan-23
Council
Amendment 1
$0.00
$0.00
$0.00
27-Jul-23
Interim PW Di
Total Contract $57,475.00 $0.00 $57,475.00
1 have reviewed the Chanee Order information above and certifv that to the best of my knowledEe
descriptions and costs are true and accurate.
Contractor Approval Signature
Printed Name & Title
�G2�12�
Interim Publ c Works Director
Jacki Brown
Printed Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract
amount established by City Council can be approved by the Public Approved:
Works Director.
Change Orders that do not exceed 10%, with a maximum of
$100,000, of either legally authorized budget limit or contract Attest:
amount established by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action.
Mayor
City Clerk
Council Approval Date