Notice of ApplicationCITY OF PORT ORCHARD
Public Works Department
Permit Center
216 Prospect Street, Port Orchard, WA 98366
Ph.: (36o) 874-5533 • permitcenter@portorchardwa.gov
NOTICE OF APPLICATION
This is a public notice of a development proposal that may interest you. You have the right to
comment on this application, receive notice, request a copy of the decision once made and
appeal the project decision. Included in this notice is a summary of the proposal, code reference
for associated permits that may be required, and the targeted timeframe for City review and
decision. Please be aware there are deadlines for comments and appeal; if you do not adhere to
these deadlines, your comments may not be considered and/or you may lose your right of
appeal. Please read this notice carefully and call the Staff Contact listed in this notice if you have
questions.
Date of Issuance:
September 1, 2023
File Number:
PW23-050, PW23-051, PW23-054
Project Name:
Lot 18 Port Orchard Industrial Park
Type of Application:
Major Land Disturbing Activity, Storm Drainage Permits & Concurrency
Review (Type II)
Assessor Parcel Number:
5392-000-018-0005
Applicant:
Tony Branham, Branham Development LLC, PO BOX 1506 Gig Harbor, WA
98335
Applicant
Representative:
Tony Branham, Branham Development LLC, PO BOX 1506 Gig Harbor, WA
98335
Date of Application:
July 24 2023
Date Application was
Determined Technically
Complete:
August 212023
Site Description:
Location: Between Vivian Ct & Leader International Dr
Nearest road intersection: Vivian Ct & Lumsden Rd & Leader
International Dr & Lumsden Rd
Size: 1.4 Acres
Zoning District: Light Industrial
Shoreline Designation: N/A
Project Permits included
with Application:
None.
Description of Proposed Project:
The proposal is for the construction of new light -industrial facility for GTR technologies.
Preliminary State Environmental Policy Act (SEPA) Determination:
The City of Port Orchard SEPA Responsible Official has not issued a SEPA Determination at this
time.
Existing Studies and Environmental Documents Evaluating the Proposal: Storm Drainage
Report, Geotechnical Report, SEPA Checklist
Other Applicable Codes Which May Require Additional Project Review / Permits:
Port Orchard Municipal Code Title 12, Title 13, Title 20.
Public Comment Period and Appeals:
Any interested person may comment on this application. The comment period will remain open
for 14 days. The deadline to submit comments is September 15, 2023. Any interested person
may request notification of any hearings or meetings and request a copy of the decision once
made. Requests must be addressed to City of Port Orchard Permit Center, Attn: Public Works
Permit Clerk, 216 Prospect Street, Port Orchard, WA 98366.
Any interested party may appeal a Type II decision to the Hearing Examiner within 14 calendar
days of the Notice of Decision. The Notice of Decision will be provided to all parties of record.
Examination of File:
The application file may be examined at the Permit Center, 720 Prospect Street, Port Orchard,
WA 98366, by appointment between the hours of 8 AM and 4 PM, Monday through Friday,
except holidays. To schedule an appointment please call 360-874-5533 and indicate the Permit
Number and Project Name for the file you would like to examine.
Staff Contact for this Application:
Ian Smith, PE
Assistant City Engineer
ismith@portorchardwa.gov
360-876-4991
Review Authority:
The Public Works Director. A Type II permit is an administrative decision and shall be reviewed
consistent with the requirements of POMC 20.24.
Project Site Plan: Attached.
Page 2 of 2
P.O. IND. PARK LOT 18
N
C
O
J
M
N
O
N
O
M
O
N
f0
0
Z
Q
J
a
w
H
Z5
5
0
T
co
J
MONUMENT REMOVAL PERMIT PROCESS 0
NO SURVEY MONUMENT SHALL BE REMOVED OR DESTROYED (THE PHYSICAL DISTURBANCE OR
COVERING OF A MONUMENT SUCH THAT THE SURVEY POINT IS NO LONGER VISIBLE OR READILY
ACCESSIBLE) BEFORE A PERMIT IS OBTAINED FROM THE DEPARTMENT OF NATURAL RESOURCES
(DNR), WAC 332-120-030(2) STATES "IT IS THE RESPONSIBILITY OF THOSE PERFORMING
CONSTRUCTION WORK OR OTHER ACTIVITY (INCLUDING ROAD AND STREET RESURFACING
PROJECTS) TO ADEQUATELY SEARCH THE RECORDS AND THE PHYSICAL AREA OF THE PROPOSED
CONSTRUCTION WORK OR OTHER ACTIVITY FOR THE PURPOSE OF LOCATING AND REFERENCING
ANY KNOWN OR EXISTING SURVEY MONUMENTS." CONSTRUCTION SHALL NOT COMMENCE UNTIL
WAC OUTLINED IN CHAPTER 332-120 IS COMPLIED WITH.
Site Plan
PARKING CALCULATIONS
USES:
WAREHOUSE - 2 PER 1,000 SF 3,840 SF= 7.6
MANUFACTURING - 1 PER 1,000 SF 15,000 SF= 15
OFFICE - 2 PER 1,000 SF 2,000 SF= 4
20,840 SF = 27
COMPACT ALLOWED (40%) =11
PARKING SPACES:
14 STANDARD 9'x20(STD)' (1 ELECTRIC)
1 ADA 9'x20'
1 ADA VAN 1 Vx20'
11 COMPACT (C) 8'x16'
27 TOTAL PROVIDED
27 REQUIRED
0' 10, 20' 30'
20' SCALE
COMPACT= C