CITY OF PORT ORCHARD
Change Order No. 1
Date: 7/26/23 Contractor: Miles Resources, LLC
Project: 2023 City Wide Asphalt Repair 400 Valley Ave NE
Contract / Job # C040-23
Puyallup, WA 98372
THIS CHANGE ORDER AUTHORIZES (add description).
Additional work to be completed at SW Sedgwick Rd. Miles Resources has provided a proposal for the 2"
grind, 6" grind, pavement, roadway markings and loops for the WSDOT light. See proposal and cost
summary sheet for details.
Amount
Contract History
Sales Tax Total Date A pad by
Original Contract
$867,629.60
$0.00
$867,629.60
09-May-23
Council
Change Order #1
$93,135.22
$0.00
$93,135.22
08-Aug-23
Council
Total Contract $93,135.22
$0.00 $960,764.82
I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
costs are true and accurate.
Cont ctor Approval Signature
Jeff Williams - Project Manager
Printed Name & Title
FDocuSigned by:
A.f,�l brbwvt,
i5 —ubl is Wor s Director
Jacki Brown
Printed Name
Change Orders that do not exceed 10%, w-th a maximum of
$50,000, of either legally authorized budget limit or contract Approved
amount established by City Council can be approved by the Public
Works Director.
Change Orders that do not exceed 10%, with a maximum of Attest:
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor
Change Orders over $100,000 or exceed a total of 10% require
Council Action.
IDocuSigned by:
i96 P IM a&A-SWA,
3696492EY5847D...
Md �UocuSigned by:
i�v aln t� UJA.UAtt,
as IA1
City Clerk
August 8, 2023
Council Approval Date
Page 1