02/27/2024 - Additional Doc-Transportation FundingTransportation Update
2024-25 Workplan
Presented by Chris Hammer, PE, PMP
City Engineer
February 27, 2021
2/28/2024
1
1
Introduction to Transportation
Cities 101 – Street and City Transportation system
By AWC
https://wacities.org/about-us/our-281-cities-and-towns/cities-101-videos
2/28/2024
2
2
City Roadway Network
2/28/2024
3
3
Planning Tools
Comprehensive Plan, Chapter 8: Transportation
Traffic Model
Pavement Management Plan
ADA Transition Plan
Local Agency Safety Plan
System Plans (Bethel Sedgwick Corridor Study)
Budget/ Capital Improvement Plan
2/28/2024
4
4
Committee Work
2/28/2024
5
2024 Update Comp Plan Transportation Element
Annual TIP update
2025 Pavement Management Plan
2025 Transportation Impact Fee update
2025/26 Review of asphalt and sidewalk preservation priorities
Grant applications
Review Major Transportation Improvement Project Preliminary Designs/ Assist w/ Public Engagement
5
Challenges
2/28/2024
6
Improvements to address deficiencies and mitigate growth
Transportation Impact Fees
TBD/ 1/10 sales tax
Leveraging with Grant opportunities
Maintaining existing roadways in good condition to keep repair costs low
Addressing sidewalk repair and retrofit.
6
Mind Map
2/28/2024
7
7
2024 Work Plan
2/28/2024
8
Improvement Projects:
SR166/ Bay Street Reconstruction (federal and local funds)
Bay Street Pedestrian Pathway DN, ROW (state & local funds)
Bethel & Lincoln Intersection Project DN,ROW (state & local funds)
Bethel Phase 1, Blueberry to Salmonberry (developer & local funds)
Lincoln & Mitchell Intersection Project CN (state and local funds)
Pottery Non-motorized project CN (state and city funding)
SR166/Sedgewick DN, ROW (local funding)
Sidney Non-motorized project DN (state and city funding)
Old Clifton Intersection Project DN (developer funded project)
Old Clifton Intersection ROW (local funding)
Old Clifton Non-motorized DN (local funding)
Tremont Phase 2 & 3 DN (State funding)
City-wide street lighting CN (state funding)
City-wide street lighting LED conversions (state funding)
8
2024 Construction
2/28/2024
9
Pottery Non-motorized Project
9
2024 Construction
2/28/2024
10
Bethel Phase 5A; Lincoln Mitchell RAB Project
10
Work Plan … Continued
2/28/2024
11
Adjacent UGA Kitsap County Projects:
Lund avenue intersection and complete street improvements
State Projects w/in City Limits
SR16 at Ruby Creek Fish Passage
SR16 at Anderson Creek Fish Passage
SR166 at Ross Creek Fish Passage
SR166 at Johnson Creek Fish Passage, Estuary, and Roundabout
SR166/ Mile Hill at Annapolis Creek Fish Passage
SR166/ Bay Street/ Bethel roundabout
SR166/ Mile Hill Roundabout
11
Work Plan … Continued
2/28/2024
12
Preservation Projects:
Annual City-wide Pavement Repairs (TBD)
Sidney Ave and Kitsap St Sidewalk/ Planter Repairs
Also … Pottery NM Project Pavement Repairs
12
Work Plan … Continued
2/28/2024
13
Preservation Activities:
City crews – Pothole filling and Less extensive asphalt patching
City crews – Crack sealing
Planning:
Comp Plan Transportation Chapter Update
Pavement Management Plan update
Grant Applications
Bay Street & Port Orchard Blvd intersection (State Regional Mobility)
Bethel and Lund intersection (Federal KRCC Countywide)
Citywide Sidewalks (State TIB Complete Streets)
13
Questions and Answers
2/28/2024
14
14
Questions and Answers
2/28/2024
15
Grind and Patch
Crack Seal
Chip Seal
15
Questions and Answers
2/28/2024
16
Show photos of new equipment ( in use)
16