059-23 - Stellar J Corporation - Supplement / Change Order 2DocuSign Envelope ID: FF1C5021-4F43-4AC1-B5BE-B80B902BF70A
CITY OF PORT ORCHARD
Authorization for Change Order No. 2
Date: 2/16/2024 Contractor: Stellar J Corporation
Project: Marina Sewer Lift Station 1363 Downriver Drive
Contract / Job # C059-23
Woodland, WA 98674
THIS CHANGE ORDER AUTHORIZES (add description).
Unforeseen underground condition. Relocation of private electrical service. Additional Work/ Change Directives:
WCD#5: Relocated electrical service discovered in abandoned sewer pipe located in areas to be excavated for new structures.
Change Order #2 Total- $76,228.56 w/ tax and 7 working days. See COR's for breakdown.
Contract History
Amount Sales Tax Total Date Appvd by
Original Contract
$13,621,175.00
$1,266,769.28
$14,887,944.28
08-Aug-23
Council
Change Order 1
$34,227.09
$3,183.12
$37,410.21
PW Director
Change Order 2
$64,253.03
$5,975.53
$70,228.56
Council
Total Contract $13,719,655.12 $1,275,927.92 $14,995,583.05
I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
costs are true and accurate.
Contracto pproval Signature Public Works Director
Casey Cox/ Project Manager Denis Ryan
Printed Name & Title Printed Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract Approved
amount established by City Council can be approved by the Public
Works Director.
Change Orders that do not exceed 10%, with a maximum of Attest
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action.
�^DocuSigned by:
C*n
Ma o� Pro.-Tem
ocuSigned by::
/1
�jvalA t1 1NAUAtt,
City Cler
March 12, 2024
Council Approval Date