Draft Capital Facilities Element_webChapter 9. Capital Facilities
9-1. Introduction
This periodic update to the Capital Facilities Element of the 2024 Comprehensive Plan provides information
about the City's existing facilities and plans for future facilities needed to service the growing population.
The Capital Facilities Element helps guide the City in providing appropriate facilities and desirable levels of
service to its residents and businesses. The Capital Facilities Element first reviews the general requirements
and available funding, connects planning to other functional plans, and reviews goals and policies that
guide planning. It also provides an overview of the current capital facility portfolio and identifies future
needs and investments for the next six years.
Capital Facilities Vision
41
Provide outstanding community
facilities that serve the needs of a
growing and changing city. This is
achieved by maintaining existing
facilities that are working well and
adding facilities when needed to address
the city'sgrowth and evolving needs.
New facilities should address multiple
objectives, such as creating new open
space and enhancing neighborhood
character, even as they serve basic
functional requirements. The state requires the City to demonstrate
=M comprehensive and coordinated planning for all capital
facilities serving the City's residents, businesses, and community. The Public Facilities and Services Goal of
the Growth Management Act (GMA) requires that the level of service ("LOS") of public facilities and services
necessary to support development shall be adequate to serve the development at the time of occupancy
and use, without decreasing current service levels below locally established minimum standards. Kitsap
County's Countywide Planning Policies also require the City to have a plan that ensures adequate facilities
and services are or will be available to serve the City's population allocation. If limited funding or other
circumstances would prevent the city from providing adequate facilities and services, the GMA requires
the city to re-evaluate the Land Use Element and make sure that plans for capital facilities and land use are
consistent.
The City of Port Orchard owns and manages a variety of
capital facilities, including roads, parks, utility systems,
police facilities, and administrative buildings. In addition
to the facilities owned and managed by the City, there
are publicly owned capital facilities managed by other
entities. These include, but are not limited to, schools,
library, sewage treatment, and public transit. Privately
owned utilities (electrical, natural gas, and
telecommunications) conduct their own planning
processes and maintain their own system plans. The City
influences private system planning through its authority
to regulate land uses and its obligation to develop and
maintain a Comprehensive Plan.
Ensuring that public facilities are available when growth occurs is critical to the quality of life for Port
Orchard's residents, businesses, and visitors. The implementation of the Capital Facilities Element and
related plans will help realize the community's vision for community facilities, as well as the vision and
goals of the Land Use Element. This Element also functions in coordination with the Comprehensive Plan's
Utilities, Parks, and Transportation Elements and functional system plans for water, wastewater, and
stormwater. These are discussed in more detail in Section 9-3
Capital facilities and functional plans guide planning and budgetary decisions. A list of capital facility
improvements planned in the next six years are described in Section 9-3. The functional plans provide a
complete facility inventory, as well as needs, projected costs, and funding sources.
Financial Overview
The City strategically manages community resources and carefully balances investments in new facilities
and infrastructure with costs to maintain and operate existing facilities. Identifying costs and funding for
capital projects planned in the next six years supports the development of the City's annual budget and
provides a path toward implementing facility projects.
The Capital Facilities Element uses many revenue sources to fund the capital improvement projects,
including sales tax, business and occupation tax, utility rates, state revenues, bonds, and grants. Impact
fees and other specific revenues allowed under the Growth Management Act also offer potential funding
sources.
A partial list of capital facilities funding sources and financing tools is included below:
Tax Revenue
• Property Tax
• Retail Sales and Use Tax
• Business License Fees
• Real Estate Excise Taxes
• Other tax revenue may include lodging excise taxes, admission tax, liquor tax, and motor vehicle
fuel taxes.
Impact Fees
• Transportation Impact Fees
• Park Impact Fees
Enterprise Activities
ire
• System Development Fees
• User Fees/Rates
• Water User Fees
• Sewer User Fees
• Stormwater Utility Fees
• General Obligation Bonds
• Revenue Bonds
• Levy Lid Lift
Grants
• Federal Grants
• Surface Transportation Program (STP)
• Highway Bridge Program (HBP)
• Transportation Enhancement Program
• Safe Route to School Program
• Grant Funding to Address Indoor Air Pollution at Schools Program - EPA
• Intersection and Corridor Safety Program
• Transportation, Community, and System Preservation (TCSP) Program
• Recreational Trails Program
• Washington State Transportation Board
• Energy Retrofits for Public Buildings — Department of Commerce
• Public Works Board funding — Department of Commerce
• Climate Pollution Reduction Grants
Other WA State Funding Programs
• The Pedestrian Bicycle Safety Program
• Community Development Block Grants
Planning Connections
Capital improvement recommendations are drawn primarily from City leadership and the functional plans
specific to each City department or facility type. Water, sewer, and stormwater have specific requirements
according to state and federal law and planning for parks and recreation facilities is included in a parks
focused functional plan. Each plan contains a system inventory and a forecast of demand and capacity
based on population and regulatory mandates. The functional plans identify capital investments that
replace or maintain existing facilities for continued service required to meet future demand for at least a
twenty-year period. The plans also define the customer service level for each facility and provide system -
specific operating policies.
Planning for capital facilities also coordinates with other agency efforts. For example, Port Orchard's capital
facilities plan considers Kitsap County's plans to redevelop the governmental campus, invest in
transportation infrastructure, etc.
Functional Plans
The Capital Facilities Element highlights recommendations from the City's functional plans in the table
below.
FUNCTIONAL PLAN
UPDATE FREQUENCY
Water System Plan
10-year cycle, as needed
Provides a basis for six -year capital improvement planning and forecasts 20-year needs
General Sewer System Plan
6-10-year cycle, as needed
Addresses aging infrastructure and system expansion to accommodate development;
updates policies and practices, data, finances, and growth forecasts; Recommends
improvements for the City's wastewater system
Stormwater and Watersheds Comprehensive Plan
6-10-year cycle, as needed
Establishes the city's storm and surface water policy
Parks, Recreation & Open Space (PROS) Plan
6-10-year cycle, as needed
Recommends 20-year capital project projects to guide growth and development of Port
Orchard's parks and open space system.
Transportation Improvement Program
every two years
Six -year plan indicates needs for maintenance and improvement of the City's transportation
network
Future Needs
While there are unique challenges in each functional area, aging infrastructure, compliance with new laws
and regulations, and increased demand for services impact all Port Orchard's capital facilities plans.
Aging Infrastructure. Some of Port Orchard's capital facilities are aging or inadequate for current service
needs and will require repairs and replacement over the next twenty years. The costs of replacing utility
infrastructure, roads, and municipal buildings can be substantial and take years to plan and implement.
To get an accurate picture of capital facility needs, Port Orchard will conduct a comprehensive facility
condition assessment (FCA). The FCA will highlight current deficiencies at the systems and facility level and
projected repairs needed over the long term. It could include recommendations to prioritize preventative
maintenance and develop a feasible schedule to address capital facility needs. The FCA is a critical first step
to improve the way Port Orchard manages, maintains, and funds its capital facilities to be more resilient
and cost-effective.
New Laws and Regulations. Changing state and federal mandates governing capital facilities systems
require the city to monitor and review its systems to ensure compliance. For example, requirements for
implementing projects, programs, and maintenance continue to evolve and are more stringent than in
2007 when the City received its first National Pollutant Discharge Elimination System Municipal
Stormwater Permit (NPDES), a Federal Clean Water Act mandate that affects programs citywide. The City
operates in accordance with the 2019-2024 Permit (Ecology 2019), adopting a new stormwater manual
and meeting new requirements for watershed planning, public education, and the business source control
and inspection program. Additionally, the City anticipates new requirements from the 2024 NPDES Permit.
Increased Demand. Capital facility investments will also be needed to ensure the City continues to deliver
the high -quality municipal services customers expect and keep pace as the community grows and changes.
Increased demand for services will also require investing in capital facilities across all functional areas.
To plan to meet future service demands, the City should conduct a citywide facilities study. Building on
findings from the facility condition assessment, this plan will assess current and future space needs,
recommend investments to address critical near -term deficiencies, and develop an implementation
strategy to provide facilities needed to serve the Port Orchard community into the future. This plan will
consider facilities investments to better serve the community that could potentially include expanding the
downtown civic campus, investing in appropriately sized public works and police facilities, and increasing
investments in maintenance and operations of City parks and throughout the portfolio.
Partner Efforts. The Port Orchard community benefits from its proximity to centers for recreation, open
space, and sports fields outside City limits and/or owned and managed by other agencies or groups, such
as the South Kitsap School District and Kitsap County. Creating and strengthening regional partnerships
enable Port Orchard and its partners to provide greater facilities and opportunities than would be possible
alone. The City should coordinate with and support these non -city service providers, such as school
districts, libraries, and solid waste processors, as they plan for new or improved facilities, such as Kitsap
County's campus redevelopment. The City of Port Orchard is already working with Kitsap County and other
nearby jurisdiction to create and expand a regional water trail including shoreline access with launch
points, rest areas, and parking facilities.
9-2. Goals and Policies
The goals and policies for Port Orchard's capital facilities align with the Comprehensive Plan vision and
goals and policies in each Element.
Goal 1. Ensure that infrastructure, facilities, and services are adequate to meet present and
future needs.
Policy CF-1 Establish minimum levels of service (LOS) and regularly monitor and update standards for
staffing and public facilities to reflect community preferences for quality -of -service delivery
and align with functional plans. Correct LOS deficiencies through capital improvements.
Policy CF-2 Require that urban level facilities and services are provided prior to or concurrent with
development. These services include, but are not limited to, transportation
infrastructure, parks, potable water supply, sewage disposal, stormwater and surface water
management, and solid waste management.
Policy CF-3 Facilitate adequate planning for services and facilities by coordinating with utility providers
on annual updates of population, employment, and development projections. Encourage
providers to improve accessibility to public services by making information available,
convenient, and complete.
Policy CF-4 Address disparities in historically underserved populations by ensuring transportation,
utilities, telecommunications, and other infrastructure are equitably distributed and
maintained, and that siting or expansion of essential public facilities does not unduly affect
any one group of people or geographic area.
Policy CF-S Maintain an inventory of existing capital facilities owned by public entities.
Policy CF-6 Acquire property sufficient to provide capital facilities at established levels of service,
according to the deficiencies and needs provided in the City's functional plans.
Policy CF-7 Ensure that new growth and development pay a fair, proportionate share of the cost for
facilities needed to serve such growth and development. Seek to reduce the per unit cost
of facilities and services by coordinating improvements such as utilities and roads and
encouraging urban intensity development within the City and Urban Growth Areas.
Goal 2. Leverage facilities investments to efficiently use public resources and improve
quality of life.
Policy CF-8 Direct growth within the community where adequate public facilities exist or can be
efficiently provided when feasible.
Policy CF-9 Encourage the joint use of utility corridors for open space and non -motorized pathways and
trails, provided that such joint use is consistent with limitations prescribed by applicable
law -and prudent utility practice. Coordinate and cooperate with other jurisdictions to
encourage cooperative planning of future facilities, reduce redundancy, and implement
multijurisdictional utility facility expansions and improvements.
Policy CF-10 Explore opportunities to acquire surface parking areas within the downtown core to serve
the public and municipal purposes.
Policy CF-11 Consider developing multi -use facilities that can serve more than one public need. Explore
opportunities for public/private partnerships and funding sources that could provide a mix
of public facilities and other uses such as commercial and residential within the same
development, where appropriate.
Policy CF-12 Make facilities investments that seek to reduce health disparities and improve well-being
and quality of life.
Policy CF-13 Design and locate capital facility improvements to reduce crime risks and optimize public
safety through increased visibility at joint use facilities (e.g., streets, public buildings, etc.).
Policy CF-14 Ensure that site selection, construction, operation, and maintenance of capital facilities is
environmentally sensitive, safe and reliable, aesthetically compatible with surrounding land
uses, economical to consumers, and does not have adverse social impacts on marginalized
communities.
Goal 3. Equitably engage with the community around capital facilities planning.
Policy CF-15 Provide meaningful inclusive opportunities for community involvement in the planning of
capital facilities, prioritizing the inclusion of historically underrepresented populations.
Policy CF-16 Coordinate with local tribes in planning capital facilities, especially in areas with cultural
significance.
Policy CF-17 Encourage public awareness and consult public input when considering the need for and
proposed locations of new public facilities.
Goal 4. Develop and maintain adequate and convenient parks, recreation, and open space
areas and facilities for all age groups to serve both the existing and future
population of Port Orchard and surrounding areas.
Policy CF-18 Encourage private property owners and developers to donate public trail access and parcels
for park development in areas identified for future municipal parks and trail connections.
Policy CF-19 Increase the size and number of parks and open spaces by providing input on development
plans for public parks within Port Orchard's Urban Growth Boundary.
Policy CF-20 Reevaluate the City's park impact fee at least every four years to ensure that the fee is
appropriate based on the City's LOS for parks acquisition, improvement, and maintenance.
Policy CF-21 Collaborate with Kitsap County to explore forming a Municipal Parks District to help fund
and develop community and neighborhood scale parks throughout the city and Urban
Growth Area.
Policy CF-22 Encourage implementation of the County's Greenways Plan that outlines a citywide system
of trails that will serve park, recreation, and open space needs. Link a system of trails
between neighborhoods and parks, school sites, and other public property. Utilize public
lands and existing rights -of -way for trail purposes whenever feasible.
Policy CF-23 Place interpretive signs along trails to encourage community, historical, and environmental
awareness, and place distance markers along the trail for walkers and runners.
Policy CF-24 Create new parks in recently annexed areas or update existing parks within newly annexed
portions of the City.
Policy CF-25 In conjunction with partners, develop the Port Orchard Community Events Center as a
recreational and civic amenities hub for Port Orchard and the South Kitsap region.
Goal 5. Ensure that an adequate water supply is available to support the level of population
growth and land development projected within the City.
Policy CF-26 Maintain water system facilities and drinking water quality in accordance with State and
Federal standards to ensure the high quality of drinking water and level of service is
provided to all customers while maximizing the life of facilities to protect the investment of
ratepayers.
Policy CF-27 Provide high quality domestic and fire protection service within the retail service area.
Policy CF-28 Utilize City -owned and operated sources of supply to maximize efficiency and cost
effectiveness of the water system.
Policy CF-29 Construct new facilities as required to serve the existing and future populations of the
established water service area and South Kitsap Urban Growth Area.
Policy CF-30 Interconnect the City's main water system with the independent facilities serving the City's
580 and 660 Pressure Zones (McCormick Woods System). This will allow for combining the
two existing systems under one water system identification number.
Policy CF-31 Encourage, implement, and maintain land use and water use efficiency and conservation
programs to discourage water waste, promote the prudent use of water resources, and
support protection of habitat and the environment.
Policy CF-32 Work with neighboring water utilities, participate in regional water planning efforts to
establish common goals of uniform water system standards, and facilitate coordination of
efforts toward the adequate provision of water service throughout the region.
Policy CF-33 Revise water service boundaries in cases where the designated water service provider
cannot provide timely or reasonable service.
Policy CF-34 Ensure that land uses permitted in aquifer recharge areas do not lead to contamination of
water resources
Policy CF-35 Encourage new developments adjacent to properties with private wells or existing septic
systems to connect to the City's water system or, if not feasible, ensure that adverse
impacts to existing wells or septic systems from new development is avoided or mitigated.
Goal 6. Provide safe, reliable, and timely sewer service to consumers at a fair and
reasonable price.
Policy CF-36 Coordinate construction of sewage improvements with other utilities. The City shall require
all new development to connect to public sewer and water systems, unless physically or
financially infeasible.
Goal 7. Ensure that all utility and transportation infrastructure expansion provides an
adequate level of public service to support new development and is consistent with
current land use plans and development regulations.
Policy CF-37 Utilize best construction methods and practices and innovative techniques in the design
and construction of utilities.
Policy CF-38 Evaluate, monitor, and reduce greenhouse gas emissions in the construction and operation
of capital facilities.
Policy CF-39 Whenever possible, utility construction should be scheduled to minimize disruption of
access to area residences and businesses.
Policy CF-40 Schedule utility construction activities to avoid sensitive times in the lifecycle of fish and
wildlife, such as spawning, nesting, and migration.
Goal 8. Minimize development related impacts to existing hydrologic conditions and
functions and strive to correct current deficiencies resulting from past development
practices such as stormwater-related flooding.
Policy CF-41 Identify areas within and adjacent to the City and its UGA which are highly sensitive to
changes in hydrologic conditions and functions. Within these highly sensitive areas,
establish standards that provide for near zero change in hydraulic and hydrologic function
on a property, such as no net increase in the peak flow or volume of runoff or erosion
products leaving a site post- development.
Policy CF-42 Encourage Low Impact Development (LID) strategies for stormwater management through
incentives and flexibility in application of regulatory requirements.
Policy CF-43 Utilize new inventories of flood hazard -prone properties in the decision -making process to
prioritize stormwater system improvements.
Policy CF-44 Coordinate the basin planning process with the community planning process to address
surface water runoff and flooding issues.
Policy CF-45 Integrate public regional stormwater detention and retention facilities into the natural
environment.
Policy CF-46 Recognize that regional facilities can provide aesthetics, recreation, and fish and wildlife
habitat in a community park -like or open space setting.
Goal 9. Support provision of adequate, timely, and efficient fire protection and emergency
medical service within the City.
Policy CF-47 Coordinate with South Kitsap Fire and Rescue on planning for the location of new fire
stations to ensure that they are dispersed throughout the City and located near areas of
high population concentration.
Policy CF-48 Encourage consolidation of duplicate services between fire districts to use resources more
effectively.
Goal 10. Coordinate land use and school district capital facilities planning.
Policy CF-49 Recognize that schools provide a unifying social and physical amenity that are key foci for
successful neighborhoods. Encourage elementary schools to be located in or near
neighborhood centers and middle schools, junior high schools and senior high schools to be
located near community centers.
Policy CF-50 Support the South Kitsap School District School Board in maintaining and funding individual
school levels of service as adopted, in accordance with the City's intent to provide adequate
school facilities for the community.
Policy CF-51 Coordinate with the South Kitsap School District to develop strategies to ensure that
students are not forced to attend a school outside their neighborhood.
Policy CF-52 Review annual reports and update school impact fees as needed.
Policy CF-53 Explore opportunities to develop joint use facilities with the South Kitsap School District,
such as recreational and community center facilities. Develop neighborhood parks adjacent
to school sites whenever possible to promote facility sharing. Facilities on the
neighborhood park site should supplement uses that the school does not provide such as
trails, open space, picnic areas, playground equipment, and multi -purpose paved sport
courts.
9-3. Capital Facilities
This section addresses capital facilities in the following four categories:
1. Administration and Community Facilities
2. Public Safety Facilities
3. Public Works Facilities
4. Parks Facilities
Each section contains a capital facilities inventory, summarizes key context and issues, recommends
improvements, and proposes projects for the next six -year planning period, with estimated costs and
potential funding sources.
Administration and Community Facilities
This section first covers the facilities supporting City administration and the overall community. It also
briefly covers the Fire Protection and Schools, community facilities that are owned and maintained by
partner agencies.
Inventory
Facility
City Hall (includes Police Station & Municipal Court)
Location
216 Prospect St
Size (scl ft)
28,370
Prospect Street Facility
720 Prospect St
2,925
Library
87 Sidney Ave
8,586
Employee Parking Lot (Gravel)
213 & 215 Prospect Street
6,500
Existing Conditions
City Hall
City Hall has served as the primary municipal building for Port Orchard's
administrative functions since it was built in 1999. The building is
approximately 28,370 square feet with three stories and a partial fourth
floor. The first floor is occupied by the Police Department and the second
floor by the Mayor's Office, City Clerk, Public Works Administration, and
Finance. The City Council Chambers and Municipal Court are located on
the third floor. Public Works operations staff are located in the Public
Works Shop. Refer to Public Works Facilities and Public Safety Facilities
sections for more information.
City Hall is in good condition for its age and was renovated in 2024 to
address needed repairs, security, and ADA accessibility, and improve the
first floor. Condition and improvement information for the first floor is
Figure 1: City Hall
discussed in the Public Safety Facilities section. Even with these improvements, functional issues remain,
including security concerns, challenging wayfinding, and limited parking. There is also not enough work
and support space; for example, breakrooms have been repurposed as workspace and the Community
Development Department was relocated due to space limitations. Municipal Court is rightsized to
accommodate future growth. Planning for City Hall should consider the space needed to accommodate
future growth and the operational efficiency gained by co -locating all departments.
In response to a need for a new community event center and aligned with Policy CF-25, the City is in the
process of designing the new Port Orchard Community Event Center. This new facility would have rentable
event space for community programming. Designs also include space for the library to relocate. The City's
Council Chambers could also be relocated if supported by leadership, which would free up space for use in
City Hall. See the Library section below for more information on existing conditions and needs.
Prospect Street Facility
Community Development is in two facilities, one located adjacent to City Hall at 720 Prospect Street with
Building, Code Enforcement, and Parking Enforcement functions (as well as the City's IT department), and
one at 600 Kitsap Street with Planning functions. The Kitsap Steet facility is leased.
The Prospect Street facility is undersized for current and future operations and in fair condition, requiring
maintenance to address age -related needs such as upgrades to the HVAC system. The division of staff
between two buildings and separation from City Hall
creates communication and operational inefficiencies. ,
There is limited parking and City vehicles are parked at
City Hall. The public interface also requires patrons to
go between the Prospect Street facility and City Hall to
complete applications. For pedestrians passing
between these two buildings, there are no crosswalks
and limited ADA compliance.
Library
Built in 1960, the City -owned library building houses
the local branch of the Kitsap Public Library. The
building is nearing the end of its useful life requiring
upgrades or relocation of the library functions.
Future Needs
Figure 2: Kitsap Regional Library's Port Orchard branch
As Port Orchard's population has grown, City staffing has increased to maintain service standards and meet
basic functional requirements.
The following investments are needed:
• In accordance with Policy CF-14, perform required maintenance at all administrative and
community facilities, including upgrading the HVAC system at the Prospect Street facility. Conduct
a facilities condition assessment to understand the current conditions and near- and long-term
maintenance needs for all capital facilities.
• Invest in the following near -term projects:
o Improve wayfinding at City Hall by installing a centralized reception kiosk and improved
signage.
o Increase security by adding lighting and safety features around exits and limiting publicly
accessible areas.
o Aligned with Policy CF-10, consider paving gravel lots, acquiring property, or constructing
structured parking to increase available staff and public parking. Provide ADA-accessible
parking near public entrances.
o As space becomes available, add staff work and support space, including workstations,
break rooms, and a lactation room.
• As part of a citywide facilities plan, estimate future staff and operational space needs and to guide
near -term improvements and property acquisition as well as longer term investments. Encourage
public awareness and input as stated in Policies CF-15 and CF-19. Endeavor to accommodate future
needs, consolidate staff to improve operational efficiency, address accessibility, and other
functional challenges. Aligned with Policy CF-11, consider developing multi -use facilities and
partnering opportunities to meet public need. Consider Police Department needs and coordinate
with plans; see the Public Safety Facilities section.
• As the City designs the Port Orchard Community Event Center, consider relocating the Council
Chambers as an interim or long-term solution to free up space at City Hall and improve security.
Relocate the library to the event center and determine the best use for the current property.
Priority Investments
Maintaining and strategically planning for Administration and Community capital facilities are the priorities
for the next six years.
Funding
Project City
Source
Grant Unfunded 5-Year Total
City Hall Renovations 555,000
6,240,000 6,540,000
Prospect Street Facility
HVAC Upgrade
TBD
Facility Condition
Assessment
TBD
Citywide Facilities Plan
TBD
TOTAL
555,000
6,540,000
Expenditures
Prior Years 0-
2025 2026 2027 2028 2029
City Hall Renovations 555,000 2,992,500
2,992,500
Prospect Street Facility
HVAC Upgrade
Facility Condition
Assessment
Citywide Facilities Plan
TOTAL
555,000
2,992,500
2,992,500
Fire and Schools
Fire Protection
The City of Port Orchard formerly maintained its
own Municipal Fire Department. In 1998, that
department was merged with Kitsap County Fire
District 7, which served the greater South Kitsap
area. In 2005, Kitsap County Fire District 7 was
renamed South Kitsap Fire and Rescue to better
represent the communities it serves.
There are currently two manned fire stations
located within the City of Port Orchard: Station
17, located at 7990 McCormick Woods Drive SW,
and Station 31, at 200 Tremont Street.
Figure 3: Tremont Fire Station
More information on Fire Protection levels of service can be found in South Kitsap Fire and Rescue's
Strategic Positioning Plan 2021-2023.
Schools
The South Kitsap School District provides public
education to Kindergarten through 12th Grade for
the residents of Port Orchard and the South
Kitsap area. It serves 9,815 students within 135
square miles. The facilities include ten
elementary (K-6) schools, three junior high (7-9)
schools, one high school, one alternative high
school, and an academy that encourages family
involvement. One elementary school, Sidney
Glen, is located within Port Orchard city limits, as
is one junior high (Cedar Heights), and South
Kitsap High School and Explorer Academy.
Figure 4: Aerial view of South Kitsap High School
The South Kitsap School District Capital Facilities
Plan can provide more information on the facilities and plans to improve them. It is adopted by reference
as a part of this document.
Public Safety Facilities
Inventory
Facility Location Size
City Hall Police Station 216 Prospect St 5,500 SF
Police Shooting Range & Storage 1278 Lloyd Parkway 113.2 acres
In addition to the facilities above, Fire Station #7 operates as the operations center in case of an emergency.
This facility is owned by the City and leased and operated by South Kitsap Fire and Rescue.
Existing Conditions
City Hall
The Police Department occupies 5,500 square feet of the
first floor of City Hall. While the 2024 renovations to the
Police Department will maximize space use and provide
some operational improvements, they will not address
many of the department's critical needs. To alleviate the
severely limited space in the near term, some staff are
located in a secure off -site leased space. Like the
administrative department, most support space has been
converted to offices or workspace. Storage space is also
inadequate; many areas have been repurposed as storage,
such as the sallyport. Police officers have take-home
vehicles, but there is no secured parking area for staff
vehicles and inadequate parking for department meetings.
.r�.�.animmirn�
.,ninnraaninlin7�ieimmwiMAiPs
Figure 5: Police offices on ground floor of City Hall
In addition to City Hall, the Police rent a 3,000 square foot warehouse for tactical training and storage. This
facility is also used to process vehicles for evidence prior to moving them to long-term storage.
Police Shooting Range & Storage
The police shooting range provides a safe location for
officers to train and practice using firearms. The
range is aging, in poor condition, and in need of
maintenance investments, including lane resurfacing
and roof replacement. There is a Conex box on -site
that offers limited storage, but the site lacks
bathroom facilities. There is also concern the outdoor
range may cause increased noise disturbance as the
surrounding residential areas grow. Long-term
storage is located in a fenced area on the same parcel
adjacent to the Public Works Operations Yard.
Future Needs
Figure 6: Shooting range
The Police department has grown a lot in recent years and expects to grow aligned with the City's
population growth. Many Public Safety facilities are aging with most not sized to accommodate current
staff or future growth.
Continued operations to meet Port Orchard's needs rely on the following steps:
• Review operations and establish level of service standards, where appropriate to assess current
and future needs. The plan should consider workload, geography, and Port Orchard community
needs. Once current and future staffing goals are in place, space needs can be assessed in
accordance with Policy CF-13, to determine the facility space needed to support the Police
department into the future.
• Incorporate plans to construct a Public Safety facility to accommodate future staff and operations
into the citywide facilities plan. Provide secure fleet parking, co -locate large vehicle evidence
storage, and determine the future use of the large evidence storage property. If possible, include
tactical training space and an indoor shooting range. Consider building in a central location free
from natural hazards. Purchase property when feasible or use existing City property for a new
facility as outlined in Policies CF-6 and CF-14. Encourage public awareness and input as stated in
Policies CF-15 and CF-17.
• If unable to include in a new Public Safety facility, modernize the existing range by covering and
resurfacing lanes and upgrading parking; install sanitation, water, and electric utilities; and add
secure storage, classroom space, and a firearm cleaning station.
Priority Investments
Funding and expenditures for the needs assessment, facilities plan, and Police Station renovations are
included with financing for City Hall renovations; refer to the Priority Investments chart in the
Administration and Community Facilities section. There are no other major investments budgeted for
Public Safety in the six -year planning period.
Public Works Facilities
The City of Port Orchard and the Public Works Department owns, operates, and maintains infrastructure
to provide drinking water, sewer, stormwater, and surface water services to its residents and businesses.
Investment in this infrastructure is necessary for continued delivery of utility services that are critical for
human health and safety, economic development, as well as supporting a sustainable, healthy environment.
Capital facility investment helps to ensure that the City can continue to deliver the high -quality municipal
utility services customers expect. This section first covers the general facilities supporting staff and then
briefly covers the individual utilities. See the Utilities Element or individual functional plans for more
detailed utility information.
Inventory
Facility Address Size (acres)
Public Works Shop 1535 Vivian Court 1.82
South Shed Storage 2051 Sidney Ave 3.77
Operations Yard 1278 Lloyd Parkway 14.46
Existing Conditions
Public Works Shop
The Public Works Shop houses Public Works
operations crews and the City's maintenance
vehicles and equipment. The main building is in
fair condition and provides space for crew
support, shops, and storage. Materials storage is
severely limited, often forcing crews to obtain
supplies from local vendors. Transportation
signage is purchased as the existing shop space
does not include an area for sign fabrication.
Limited crew space is unable to support growth
in staff and operations.
Figure 7. Public Works Shop
Staff and fleet parking space is limited and unable to accommodate growth. There are also two adjacent
structures providing covered parking for fleet and equipment. Fleet requiring heated parking can be stored
in the main building's shop space as well as in one bay at the South Shed. The rest of the site is significantly
undersized with limited yard material storage and no room for expansion.
The facility is located on the west side of Highway 16, making it well located near the McCormick Woods
development, but separated from a large portion of the City, staff, and facilities, including City Hall. This
location may provide operational challenges in the event of a natural hazard.
South Shed
The South Shed Facility is located on a 3.77-acre site
located at 2035 Sidney Avenue with 2,000 square feet of
warehouse for material and equipment storage. Most of
the land at this location is utilized as a park. Originally a
fire station, the South Shed was repurposed for Public
Works storage in addition to seasonally providing heated
parking for equipment such as sweeper and vactor
trucks. This aging facility is in poor condition,
inappropriate for staff workspace, and is too small to
meet storage needs.
Operations Yard
Figure 8: South Shed
The Operations Yard is located near the Shop and contains a decant facility and materials laydown storage.
The decant is in good condition but is at capacity as it is used as a regional facility. Spoils frequently do not
have adequate time to dewater, requiring the City to add wicking materials that add weight and cost when
taken to the Kitsap transfer station. The site has limited materials storage but is large enough to
accommodate additional crew space and materials bins.
Future Needs
Public Works is anticipating an estimated staffing increase in the next ten years, growing from 25 to 32-40
or more staff to meet the needs of the rapidly growing community. The City will need to expand Public
Work facilities to accommodate needed staff and equipment. Major needs for this planning period as
identified by Public Works leadership include:
• In accordance with Policy CF-14, perform required maintenance at all public works facilities.
Conduct a facilities condition assessment to understand the current conditions and near- and long-
term maintenance needs for Public Works and other capital facilities.
• In accordance with Policy CF-1, conduct a citywide facilities plan to review current and future level
of service standards, add staff where needed, and increase operational space to accommodate
current and future staff and operations.
• Provide a new public works annex at the industrial center public works yard to house operations
utility staff. The proposed facility should include crew support space (offices, bathroom, showers,
etc.); a heated warehousing for plumbing, electrical, and other materials storage; employee
parking; heated and covered storage bays for equipment and materials; and expanded yard areas
for laydown and materials storage.
• Upgrade the existing Public Works Shop facility to better utilize vertical storage.
• Upgrade the decant facility to increase capacity and add a new composting facility.
• Provide a new Operations East satellite streets facility west of SR16, preferably near the
intersection of Bethel and Lund, and include a crew room and restroom facilities, heated bays for
snowplow equipment, and material storage yard.
• Decommission the south shed facility and determine the best use for the current property.
Priority Investments
Financial information to support the facility condition assessment and citywide facilities plan can be found
in the Administration and Community Facilities section. Investments for the next six years have not been
identified for the general Public Works capital facilities. Please see the Utilities section below for priority
infrastructure investments.
Funding
City
PW Shop Upgrades
Source
UnfundedProject
Grant Total
TBD
Utilities Operations Annex
TBD
Decant Facilities and Yard
Improvements
TBD
PW Operations East Station
TBD
TOTAL
TBD
Expenditures
Prior Years 0-
PW Shop Upgrades
2025 2026 2027 2028 2029
Utilities Operations Annex
Decant Facilities and Yard
Improvements
PW Operations East Station
TOTAL
Utilities and Transportation
Port Orchard's Public Works Department operates and maintains the City's utilities and transportation
systems. Some of Port Orchard's capital facilities are aging or inadequate for current service needs and will
require repairs and replacement over the next twenty years. The costs of replacing utility infrastructure
and roads are substantial and take years for planning and implementation. The City is working to address
substandard infrastructure and comply with changing state and federal mandates governing capital
facilities. In accordance with Goal 1, the City should ensure that all utility infrastructure expansion provides
an adequate level of public service to support new development consistent with the City's policies, criteria,
and standards. In addition, utility expansion should also be consistent with current land use plans and
development regulations of the State of Washington, Kitsap County, and appropriate local planning
agencies.
The following sections list priority projects for Transportation, Stormwater, Sewer, and Water between
2023-2028. More information on these facilities is provided in the Transportation and Utilities Elements as
well as the individual functional plans.
Transportation
Port Orchard is responsible for City roads and other aspects of the City's transportation system. Details on
all City transportation systems can be found in the Transportation Element. Priority investments and
funding assumptions targeted in the next six years are summarized below.
Funding Source
Annual Maintenance
4,800,000
4,800,000
Projects
Citywide Street Lighting
210,000
890,000
1,100,000
Bethel Phase 1a: Blueberry
3,591,000
3,591,000
RAB
Bethel Phase 4a: Lund RAB
4,500,000
1,000,000
Bethel Phase 4b; Vallair Ct
3,500,000
1,500,000
Connector
Bethel Phase 1b:
Salmonberry
11,848,000
3,000,000
3,000,000
14,848,000
Bethel Phase 5a:
Bethel/Lincoln RAB
1,500,000
2,600,000
4,100,000
Old Clifton Non -Motorized
450,000
2,700,000
3,150,000
Improvements
Old Clifton/Anderson Hill
2,300,000
2,300,000
Intersection Improvements
Pottery Ave Non -Motorized
400, 000
644, 000
1,044,000
Improvements
Sedgewick Rd W Study
300,000
300,000
Sidney Rd Sidewalk
500,000
1,395,000
1,895,000
Sidney Rd SW Design
500,000
500,000
SR 160/Sedgewick Phase 2a
1,550,000
1,550,000
SR 166/Bay St
Reconstruction
784,000
3,000,000
3,784,000
Tremont Phase 2 & 3
732,000
2,500,000
3,232,000
TOTAL
6,552,000
8,852,000
2,700,000
18,104,000
Expenditures
Annual Maintenance Projects 1,020,500 800,000 800,000 800,000 800,000 800,000
Citywide Street Lighting
210,000
100,000
1,000,000
Bethel Phase la: Blueberry
RAB
250,000
294,000
259,000
2,788,000
Bethel Phase 1b:
Salmonberry
375,000
2,100,000
1 1,997,000
7,370,000
Bethel Phase 4a; Lund Int
500000
1,000,000
Bethel Phase 4b; Vallair Ct
Intersection and Connector
500000
Bethel Phase 5a:
Bethel/Lincoln RAB
800,000
3,200,000
Old Clifton Non -Motorized
Improvements
150,000
450,000
2,700,000
Old Clifton/Anderson Hill
Intersection Improvements
258,000
1,738,000
Pottery Ave Non -Motorized
Improvements
185,000
1,044,100
Sedgewick Rd W Study
300,000
Sidney Rd Sidewalk
235,000
1,660,000
Sidney Rd SW Design
500,000
SR 160/Sedgewick Phase 2a
600,000
950,000
SR 166/Bay St Reconstruction
200,000
1,135,000
2,649,000
Tremont Phase 2 & 3
732,000
2,500,000
,760,000
, 6,000
12,858,000
858,000
2�
,484,000
Stormwater
Port Orchard owns, maintains, and manages its stormwater collection system. Goal 8 states the City should
minimize development related impacts to existing hydrologic conditions and functions and strive to correct
current deficiencies resulting from past development practices such as stormwater-related flooding.
Details on the City's stormwater system can be found in the Utilities Element as well as the 2023
Stormwater and Watersheds Comprehensive Plan. Priority investments and funding assumptions targeted
in the next six years are summarized below.
Funding
Project City
Sidney Regional Storm 1,200,000
Sources
Grant Unfunded 6-Year Total
14,000,000 15,200,000
Sidney Rd. Fish Pass Culvert
1,911,386
1,911,386
Sedgwick Balancing Culvert
450,000
450,000
Annapolis Creek Culvert
1,300,000
1,300,000
Downtown Retrofit
1,350,000
1,350,000
TOTAL
1,200,000
19,011,386
20,211,386
Expenditures
Sidney Regional Storm 1,666,667 466,667
6,766,667 6,300,000
Sidney Rd. Fish Pass
Culvert
80,764
955,693
874,929
Sedgwick Balancing
Culvert
22,500
225,000
202,500
Annapolis Creek Culvert
43,333
43,333
628,333
585,000
Downtown Retrofit
175,000
675,000
500,000
TOTAL
1,813,264
1,865,693
9,147,429
7,385,000
Sewer
The City is tasked to provide safe, reliable, and timely sewer service to consumers at a fair and reasonable
price, as seen in Goal 6. Port Orchard owns, operates, and maintains existing wastewater collection and
conveyance facilities. As of 2016, the City's sewer service area was approximately 2,100 acres and was
expected to grow to 5,700 acres. Details on the City's sewer system can be found in the Utilities Element
as well as the 2016 General Sewer Plan Update. Priority investments and funding assumptions targeted in
the next six years are summarized below.
Project
Funding Source
City
Marina Lift Station
..
$13,000,000
6,200,000 19,200,000
Bay Street LS Cap Upgrades
1,000,000
1,000,000
Lift Station Controls (6) &
Generator (1)
800,000
800,000
TOTAL
21,000,000
Expenditures
Marina Lift Station
7,533,333 5,833,333
5,833,333
Bay Street LS Cap Upgrades
100,000
900,000
Lift Station Controls (6) &
Generator (1)
400,000
400,000
TOTAL
7,933,333
6,333,333
6,733,333
Water
Port Orchard Public Works Department maintains and manages the City's water system. With two systems
serving the City (City System) and McCormick Woods (McCormick Woods System), Port Orchard serves
over 4,000 connections. Goal 5 and its related policies state the City will ensure that an adequate water
supply is available to support the level of population growth and land development projected within the
City. Details on the City's water system can be found in the Utilities Element as well as the 2020 Water
System Plan. Priority investments and funding assumptions targeted in the next five years are summarized
below.
Funding
Source
r
Well#13, 90% DN -> CN (#2)
City
Loan
Unfunded
6-Year Total
Well #11 (#3)
$8,000,000
8,000,000
Melcher PS Rebuild (#10)
500,000
70,000
570,000
Well #7
500,000
500,000
580 to 660 Zone Booster Sta
Developer funded
660 Zone Storage
TOTAL
JL
9,000,000
70,000
9,070,000
Expenditures
Well#13, 90% DN -> CN (#2)
150,000
2,038,000
2,038,000
Well #11(#3)
4,500,000
3,500,000
Melcher PS Rebuild (#10)
370,000
200,000
Well #7
TBD
TBD
580 to 660 Zone Booster Sta
660 Zone Storage
OTAL
1 4,870,000
1 3,850,000
1 2,038,000
1 2,038,000
Parks Facilities
The Parks Element of the 2024 Comprehensive Plan, supplemented by the Parks, Recreation and Open
Space (PROS) Plan, outlines the goals, expectations, and community vision for the City's Parks. This section
draws from those plans with a concentration on capital facilities.
Inventory
Port Orchard owns 89.7 acres of parkland, with a ratio of approximately six acres per every 1,000 residents.
This includes conservancies, resource parks, trails, athletic parks, community centers, special use facilities,
and support facilities.
Parks capital facilities are listed below; refer to the PROS Plan for a full inventory of parks.
Facility
Blackjack Creek Multi -Modal Bridge
Address
1301 Area Bay St
Site Size
(acres)
Boat Ramp -Launch
533 Bay St
0.82
Central Park (Clayton Park/Dwight Park)
915 Dwight
1.4
Dekalb Pier
467 Bay St
4.1
Etta Turner Park/Blackjack Creek Park
1301 Arena Bay Street
0.16
Givens Field/Active Club
1025 Tacoma Ave
0.6
Marina And Observation Deck
707 Sidney Pkwy
McCormick Village Park
3201 SW Old Clifton Rd
28.6
Van Zee Park
300 Tremont St
8.3
Existing Conditions
In general, the City has adequate outdoor park and recreational facilities to serve the population during the
planning period, however, playground, picnic, sports court, and field sites are not evenly distributed within
a 5- or 10-minute walk of all residential areas, creating a need for more neighborhood parks. There are also
deficits in indoor recreation facilities, community gardens, and multipurpose trails.
Additional information on the City's parks and more detailed planning strategies can be found in the City's
PROS Plan and in the Parks Element of this Comprehensive Plan.
Future Needs
The City is committed to providing parks that are safe and well -maintained, enhance residential
neighborhoods, encourage shoreline access, and activate downtown areas.
Considering existing level -of -service for Port Orchard owned parks, the City's projected population growth
will create a need for an additional 61.4 acres of land and 15,661 facility units (square feet of courts, fields,
etc.) by the year 2040, requiring an estimated expenditure of $32,326,076. This does not account for any
maintenance, operation, or repair costs. See the PROs Plan for more information on existing -level -of -
service standards.
The PROS plan highlights the following investments that update and expand existing park facilities.
• In accordance with Policy CF-14, perform required maintenance at all parks and recreation
facilities. Conduct a facilities condition assessment to understand the current conditions and near -
and long-term maintenance needs for all capital facilities.
• As part of a citywide facilities plan, develop a space needs analysis to determine and justify staff
growth and investments needed to achieve the Parks goals. Aligned with Policy CF-11, consider
developing multi -use facilities and partnering opportunities to meet public need.
• Continue plans to design and construct the Port Orchard Community Event Center. The center will
be located at 619 Bay Street on the downtown waterfront and include 7,600-8,600 square feet of
event space and meeting facilities, as well as a 7,000-9,500 square foot library facility with outdoor
decks and an activities area. Consider also relocating the Council Chambers to consolidate
community functions.
• In accordance with Goal 4, perform required maintenance at all parks facilities.
• Protect existing open space and conservancies and acquire and develop parks and trail systems.
• Designate and conserve cultural and historic resources located within park properties; seek joint
funding partnerships with local jurisdictions to create wayfinding and educational signage,
artworks, streetscapes, and gateways.
• Develop master plan for Givens Park and assess condition, repurposing, or removal of the Active
Club.
• Develop a master plan for expanding Etta Turner Park to the west side of Blackjack Creek. Install
lighting on the bridge and enhance Blackjack Creek.
• Develop master plans for Ruby Creek Regional Park and Sherman Ave Stormwater Park.
• Create and strengthen regional partnerships to enable the City and its partners to provide greater
facilities and opportunities than would be possible alone.
Priority Investments
Details on current and planned investments in the next 20 years can be found in the PROS Plan. Financial
information to support the facility condition assessment and citywide facilities plan can be found in the
Administration and Community Facilities section. Priority investments and funding assumptions targeted
in the next six years are summarized below.
Funding
Impact..
Source
Project City Fee Credit
Port Orchard Community
Fees Grant Grant Unfunded . Total
Event Center 927,430
283,900 18,729,963 6,500,000 1,658,707 28,100,000
Waterfront Plaza Shoreline
Restoration/Enhancement
278,920
352,300
500,000
1,376,780
2,508,000
Orchard St Plaza
792,000
500,000
3,008,000
4,300,000
Givens Park Sport Court
Remodel
24,080
176,400
100,000
300,480
McCormick Village Park
Phase 3
1 1,250,000
1,250,000
Telford Way Multimodal
Pathway
979,012
979,012
McCormick Village Dr
Multimodal Pathway
1,468,518
1,468,518
Sherman Ave Stormwater
Park
862,765
1,861,039
2,723,804
TOTAL
2,093,195
3,697,530
1,428,200
19,406,363
7,100,000
7,904,526
41,629,814
Expenditures
Port Orchard Community
Event Center 4,064,132 951,620
23,084,247
Waterfront Plaza Shoreline
Restoration/Enhancement
360,194
271,006
1,876,800
Orchard St Plaza
78,822
691,378
3,529,800
Givens Park Sport Court
Remodel
66,480
234,000
McCormick Village Park
Phase 3
1,250,000
Telford Way Multimodal
Pathway
979,012
McCormick Village Dr
Multimodal Pathway
1,468,518
Sherman Ave Stormwater
Park
862,765
1,861,039
TOTAL
5,365,913
1,980,485
234,000
34,049,416