018-24 - PumpTech, LLC - Supplement / Change Order 2CITY OF PORT ORCHARD Authorization for Change Order No. 2 Date: 7/24/24 Project: Tremont Place Lift Station irs Contract / Job # C018-24 Contractor: PumpTech, LLC 12020 SE 32"d Street, Suite 2 Bellevue, WA 98005 THIS CHANGE ORDER AUTHORIZES THE FOLLOWING CHANGES TO THE CONTRACT: A Time Only extension of the contract termination date to August 31, 2024 due to supply chain delays. Section 2. Commencement and Substantial Completion date is amended to read: The date of commencement shall be January 23, 2024. The Contractor shall substantially complete the Work not later than August 31, 2024, subject to adjustment by change order. In all other respects the Underlying agreement between the parties shall remain in full force and effect, amended as set forth herein, but only as set forth herein. Contract History Amount Sales Tax Total Date Appvd by Original Contract $56,750.00 $5,277.75 $62,027.75 23-Jan-24 Council Change Order 1 $0.00 $0.00 $0.00 29-May-24 PW Director Change Order 2 $0.00 $0.00 $0.00 24-Ju1-24 PW Director Total Contract $0.00 $5,277.75 $62,027.75 I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and costs are true and accurate. Contractor rova i ture Dewy Ewv Denis Ryan (Jul 2 , 202410:55 PDT) Public Works Director Denis Ryan Printed Name & Title Printed Name Public Works Contracts Greater than $35,000: Change Orders that do not exceed 10%, with a maximum of $50,000, of either legally authorized budget limit or contract Approved: amount established by City Council can be approved by the Public Works Director. Total Contract Amount shall reset to reflect new Council -approved contract totals authorized prior to the requested change order. $50,000-$100,000 require Mayoral Approval. $100,000 and over require Council Approval Attest: Public Works Contracts under $35,000, change orders that individually do not exceed $7,500 with an aggregate cap of $10,000. Public Works Contracts unbudeeted and under $7,500: All Change Orders that do not exceed an aggregate cap of $7,500 (Excluding underlying value), provided there are departmental funds available in the budget. All Departments: Mayor approves any and all Change orders that do not exceed 10% of either authorized budget limit or contract amount established by City Council. With a maximum aggregate amount of $100,000. Total Contract Amount shall reset to reflect new Council -approved contract totals authorized prior to the requested change order. Any individual Change order that is over $100,000 requires Council approval. ayor City Clerk Council Approval Date CO18-24 Final Audit Report CO2_P u m ptech_Tre mo ntP L-LS 2024-07-24 Created: 2024-07-24 By: Heidi Draper (hdraper@portorchardwa.gov) Status: Signed Transaction ID: CBJCHBCAABAAd baFatVTRQB2eTZMKW1eMcURL1fL7ib "C018-24_CO2_Pumptech_TremontPL-LS" History Document created by Heidi Draper (hdraper@portorchardwa.gov) 2024-07-24 - 4:09:54 PM GMT Document emailed to Denis Ryan (dryan@portorchardwa.gov) for signature 2024-07-24 - 4:10:18 PM GMT Email viewed by Denis Ryan (dryan@portorchardwa.gov) 2024-07-24 - 5:55:44 PM GMT 'S Document e-signed by Denis Ryan (dryan@portorchardwa.gov) Signature Date: 2024-07-24 - 5:55:56 PM GMT - Time Source: server Agreement completed. 2024-07-24 - 5:55:56 PM GMT 0 Adobe Acrobat Sign