084-24 - Puget Sound Energy - ContractDocusign Envelope ID: 5A88DF55-1112-4D7A-AOB4-743B59BEBCEO
ruuc l COMMERCIAL ELECTRIC FACILITIES CONTRACT
' SOUND
ENERGY
Date
08/19/2024
Contract is subject to revision after
90 days
CUSTOMER (OWNER) NAME CITY OF PORT ORCHARD
CO-OWNER NAME (IF APPLICABLE)
SERVICE ADDRESS 1201 SIDNEY AVE
CITY PORT ORCHARD
STATE
ZIP 98366
WA
BILLING ADDRESS 216 PROSPECT ST
CITY PORT ORCHARD
STATE WA
ZIP 98366
PHONE 360-876-7048
EMAIL jbrown@portorchardwa.gov
PSE WORKORDER NO. 101176603
Summary of Charges:
Construction Costs: $ 27,737.58
Transformation Charges: $ 9,083.77
Less Applicable Margin Allowance: $ 0
Sub -Total (Potential Refundable Costs): $ 36,821.35
Permitting Fees*: $ 235.94
Relocation/Removal of Existing Facilities: $ 3,041.81
Other Non -Refundable Construction Charges: $ 3,629.38
Sub -Total (Non -Refundable Costs): $ 6,907.13
Less Deposit Paid in Advance: $ 0
Initial
Total Amount to be Billed Under This C n ct: $ 43,728.48
Customer Initials
Brief Description of Work:
REMOVE IDLE THREE PHASE TRANSFORMER BANK,
REPLACE POLE, RELOCATE PRIMARY SPANS.
Brief Description of Other Costs:
FLAGGING, MATERIALS & LABOR
*If the above Permitting Fees are associated with service work only, those costs will be billed with the applicable service
charges below after the service is energized.
SECONDARY SERVICE CHARGES (PERMANENT AND TEMPORARY) ARE NOT INCLUDED IN THE SUMMARY OF CHARGES
ABOVE Any applicable Secondary Service Type charges listed below will be billed after your service line installation, based on the actual
work performed. Base Costs, in the table below, are based on the current tariff pricing as of the date of installation and include the
Schedule 87 tax effect. These charges also do not include permitting fees, trenching and other excavation related work that is your
responsibility. The Secondary Service Type charges from the list below that apply to your project will be invoiced on a second bill.
Secondary Service Tyl2e 1480 Voltage or Below
Cost w/Schedule 87 tax effect
Single wire run to handhole or transformer
$912.07
Each additional run of wire(per circuits)
$189.92
Each additional trip beyond 1st trip due to customer needs
$564.25 per trip
Hourly rate for additional engineering at customer's request
$246.24
Underground Temporary Service Charge
$230.00
Overhead Temporary Service Charge
$474.00
Overhead to Overhead Permanent Service Charge
$914.28
Underground to Underground Permanent Service Charge
$749.75
Overhead to Underground Permanent Service Charge
$1,401.23
C tilnmer
In#als:
By signing this contract you are authorizing PSE to continue with all the needed elements to complete your project. Upon
receipt of a signed contract, PSE will bill you for the amount indicated on the "Total Amount to Be Billed Under This Contract"
line. The bill will sent to the billing address listed on this contract. PSE requires payment of these line extension charges
prior to scheduling construction. Payments can be made via pse.com (fees may apply), by mail, or at a PSE Pay Station.
Delaying payment may result in a construction delay for your project. Customer requested changes in the scope of the
project m y resm, ye 116 additional charges, and/or delays to your project.
Signature: L�' rulwwName: ROBERT PUTAANSUU Title: Mayor Date:10/21/2024
B96492E3F5847D...
Docusign Envelope ID: 5A88DF55-1112-4D7A-AOB4-743B59BEBCEO
TERMS AND CONDITIONS
PROJECT INFORMATION
1. The PSE drawing shows the proposed scope of your project including the location of permanent, above ground
electrical facilities required to provide electrical service to your project. Fault current information for transformers
associated with your project is noted on the work sketch drawing. Please review this drawing as soon as possible
to ensure there are no unforeseen conflicts between PSE's design and your project. If you determine there are
conflicts or if you identify a discrepancy while reviewing the drawing for your project, please contact me at the
number below. This is attached as Exhibit A.
2. Additional construction -related information and information on metering and service entrance requirements
areprovided in PSE's Electric Service handbook for commercial projects. If you would like a copy of the
handbook please contact me at the number below. It is your responsibility to provide your project manager, site
superintendent, and/or subcontractors with any relevant information from this correspondence that apply to their
work in support of your project.
3. The Excavation Requirements & Final Grade Certification must be signed by the project owner or designee and
returned to me along with a signed copy of this contract. This is attached as Exhibit B.
4. Transformers have been sized for diversified commercial loads only, and shall not be used for high load factor
(continuous) temporary power uses, such as electric heaters for dry -out. Fault currents for non- residential
transformers in your project are noted on the attached PSE design drawing. Please notify the PSE representative
listed on this contract immediately if you believe there are conflicts between this design and your project. It is
your responsibility to provide your project manager, site superintendent, and subcontractors with any information
from this correspondence and it's attachments that apply to their work.
5. The requirements for trenching by customers on public right-of-ways and/or on Puget Sound Energy easements
must be signed by the project owner or designee and returned along with a signed copy of this contract. This is
attached as Exhibit C.
POTENTIAL REFUNDS
Margin Allowance:
If PSE has not provided a Margin Allowance or if your Margin Allowance exceeds $75,000, PSE agrees to calculate and
refund the Margin Allowance, subject to Schedule 85. Refund requests must be made within six (6) years of the date on
which the facilities installed under this contract are energized. Customers are responsible for making the one-time refund
request.
DIM Refund:
Other refunds associated with the line extension charge may be available if additional permanent service hook-ups are
made to your line extension. These service hook-ups must be made within five (5) years of the date on which your project
is initially energized Customers are responsible for making all refund requests. A refund may be requested one (1) time
within six (6) years of the date on which your line extension is initially energized. It is the customer's responsibility to
make the refund request. Your refund request should be directed to PSE's Customer Accounting Coordinators at
Schedule85refundrequests@pse.com.
RATE SCHEDULE 85
All terms and conditions, costs, and refunds are in accordance with PSE's Rate Schedule 85, and any discrepancies
between this contract and the Rate Schedule will be resolved in favor of the Rate Schedule. Rate Schedule 85 contains
more detailed information covering costs, refunds, rights, and obligations than is reflected in this contract. The entirety of
Rate Schedule 85 can be viewed at PSE's website www.pse.com.
This cost information is valid for 90 days from the Date Issued, and is subject to being updated after that time. I have read
both pages and agree to the terms and conditions outlined in this contract and its attachments.
The amount noted on this contract is an estimated cost; however PSE's Schedule 85 line extension tariff requires
customers to pay the actual cost of construction. PSE will determine the actual cost of the job once construction is
complete. If the actual cost of the job is more than 10% above or below the estimated cost, an additional billing or refund
will result to account for the difference.
Docusign Envelope ID: 5A88DF55-1112-4D7A-AOB4-743B59BEBCEO
VruuE:I
SOUND
ENERGY
REQUIREMENTS FOR TRENCHING BY CUSTOMERS ON PUBLIC RIGHT-OF-WAYS AND/OR ON PUGET
SOUND ENERGY, INC. EASEMENTS
The following outlines most local governmental guidelines and company standards for trenching on a public right-of-way
or Puget Sound Energy, Inc. (PSE) easement. Any trenching performed by the customer, or their contractor, under a PSE
permit or easement must comply with these requirements.
1. All trench construction must be performed by a Washington State licensed and bonded contractor.
2. Trench excavation, backfill, restoration, and facility placement must be coordinated with a PSE designated
representative, and receive on -site approval by that representative, and local jurisdiction.
3. Right-of-way easement trenching and backfill must be performed during normal business hours, Monday through
Friday. Same day excavation and backfill is required for all trenching. Job start notification to the local jurisdiction
is the responsibility of Potelco, Inc. Customer shall notify Potelco Project Manager three working days prior to
trenching. Penalties for failure to comply with this requirement will be borne by the customer.
4. If the job scope requires excavation beyond a single day, fencing and barricading must be installed around utility
facilities exposed above the trench, if allowed, must be in accordance with local regulatory requirements.
5. PSE, all participating utilities, and One -Call Locate, must be notified a minimum of 72 hours in advance of the
date and time for right-of-way trenching and facility placement. The One -Call Locate number is 1-800-424-5555.
State law requires locating service notification.
6. Excavated material must remain clear of the roadway whenever possible. Excavation material, spoils, and debris
shall be removed off -site each day, in accordance with local regulatory requirements. All erosion control
requirements in accordance with local regulatory requirements are the responsibility of the customer.
7. Material excavated from the shoulder of the right-of-way shall be properly disposed, and replaced with select
backfill material in accordance with local regulatory requirements.
8. Proper compaction is required to comply with local regulatory specifications. If the permit requires compaction
testing, the cost of said testing is the responsibility of the customer.
9. All permit requirements, traffic control plans, traffic control and flagging shall meet local regulatory specifications
and satisfaction.
10. In the event of failure to abide by the above requirements, PSE reserves the right, at its sole discretion, to assume
trenching. In the event of delays due to equipment failure, PSE may assume trenching to meet regulatory and
joint construction requirements. The customer is responsible for all trenching costs, and will reimburse the
company for costs should PSE perform the trenching. initial
Customer Initials:
11. The customer agrees to indemnify, defend and hold harmless PSE from all liability (including reasonable
attorneys' fees) arising out of, or in connection with, the above mentione I 7r6'
ing activities.
Customer Initials:
I AGREE TO ADHERE TO THE ABOVE CONDITIONS
Service Address: 1201 SIDNEY AVE
PORT ORCHARD 98366 Work Order Number: 101176603
SigneYdd by:
Signature: �� r5 Name: ROBERT PUTAANSUU Title: Mayor Date10/21/2024
Docusign Envelope ID: 5A88DF55-1112-4D7A-AOB4-743B59BEBCEO
PV CJt
' SOUND
ENERGY
PSE ELECTRICAL FACILITIES
EXCAVATION REQUIREMENTS AND FINAL GRADE CERTIFICATION
PURPOSE
This document is an agreement between Puget Sound Energy (PSE) and the Owner/Developer (Developer) who is
providing excavation for the installation of PSE's facilities. This document does not provide an easement for operating
rights. If PSE determines that a recordable easement on the Developer's property or other property is necessary, it shall be
the Developer's responsibility to obtain such easements in a form acceptable to PSE prior to construction.
EXCAVATION REQUIREMENTS
The requirements and conditions outlined below apply when you provide the excavation for PSE's electrical facilities as a
condition of receiving electrical service for your project. If you need additional information, please call the PSE contact
person listed below.
Developer is responsible for acquiring utility locates by calling One -Call, 1-800-424-5555 at least 48 hours (two full
working week days) prior to digging. The excavation must meet the requirements of the Washington Administrative
Code and Safety Standards.
2. Developer shall call the PSE contact person noted below for trench and route approval prior to starting excavation.
3. The electrical primary trench shall be excavated to provide a minimum of 36 inches of facility coverage, to a maximum
trench depth of 48 inches. The electric service trench shall be excavated to provide a minimum of 24 inches of facility
coverage, to a maximum trench depth of 36 inches. A 12 inch horizontal separation is required between PSE electrical
facilities and other utilities within a joint trench.
4. All back fill must be free of sharp objects and construction debris. Developer shall provide and install sand bedding and
shading for electrical facility protection as directed by PSE's contact person. Developer is responsible for any damages
caused by improper backfill or compaction.
5. Developer agrees to maintain a minimum of 2 feet of horizontal clearance between PSE conduit, pipe or conductors and
any foundation on Developer's property.
6. The vault excavation shall be dug to the dimensions noted on the attached work sketch. Vault holes shall have a solid
level bottom with a 6 inch deep layer of crushed rock bedding.
7. Developer shall provide the excavation for PSE electrical facilities within the designed location. Developer shall identify
and provide final grade, property lines, and utility easements prior to installation of PSE's electrical facilities.
8. Developer will be financially liable for the relocation of PSE's facilities which are inadequately covered, located outside
the area where PSE has adequate operating rights, improperly graded inhibiting standard access and/or any damages
resulting from dig -ins due to changes or variations in grade that are made after the installation of PSE's facilities.
FINAL GRADE CERTIFICATION
By my signing below, I certify that the electrical facilities work area shall be at final grade prior to excavation. I assume full
responsibility for my excavation work and the resulting location of these facilities. I also agree to indemnify, defend, and hold
harmless Puget Sound Energy from all liability arising out of, or in connection with my work, including but not limited to all
claims, losses, damages, and expenses, including reasonable attorney's fees, which result from my failure to excavate
within easement areas or rights -of -way, or from digging without adequate rights on adjoining properties.
Service Address: 1201 SIDNEY AVE
PORT ORCHARD 98366
SigneYdJ by:
Signature: r 4a&ASWA' Name: ROBERT PUTAANSUU
Work Order Number: 101176603
Title: Mayor Date:10/21/2024
2806 08/15
Docusign Envelope ID: 5A88DF55-1112-4D7A-AOB4-743B59BEBCEO
Sq. Footage: 420 SQ. PUMP STATION_
Panel Size: 400 AMPS
Heat Type: N/A
Est. Demand: 126 KW
LRC: 359A
% V. Drop: 2.4%
% Flicker: 5.5%
1104
150kVA 277/480v w
Fault Current: 10,600
R/X:0.6 %Z:1.70
1112 Q
I
�1123
M
27-1133
I X
M 1137
M 139
114
I � � 709
1128
1132
1136
619883
02 155486
15 kVA (C)
25T
13-477
1025
EPO
Q U 16
U 22
II
22
II
c°h' `i cl / / 1111-1113
w
Q
M 1129
II
z I
619898
Poll155487
to
75 kVA 480V (ABC
SLAG1237
d0
\ ^ ^ 33
1P
P03 619876
155485
MELCHER ST
7
SWING 3PH OH PRI FROM
\ P03 TO NEW PO4R
� �b0
619864
P05 155481
706 1306 GPQj
'A - � Z_
103
226 /
1230
SITE PLAN
SCALE: 1" = 100'
8J
6/826
812
M
M 1141
w
M 01
PO4 _ M
BUSH TRIM REQ'D
61987:
155501
619872 04
155486
3X 50KVA, 277/480V
TRANSFORMER REMOVAL
Removed at site: Po l
Grid Number: 619898-155487
kVA Rating: 25
Foreman to redline the following information
Company ID#:
Primary phase connected to:
Tested Secondary Voltage
TRANSFORMER REMOVAL
Removed at site: PD l
Grid Number: 619898-155487
kVA Rating: 25
Foreman to redline the following information
Company ID#:
Primary phase connected to:
Tested Secondary Voltage
TRANSFORMER REMOVAL
Removed at site: Po l
Grid Number: _619898-155487
kVA Rating: 25
Foreman to redline the following information
Company ID#:
Primary phase connected to:
Tested Secondary Voltage
619875 PO
155511
SITE SPECIFIC NOTES
P01 GRID #619898-155487: (EXISTING)
-EXIST (1988) 45' CL1 POLE TO REMAIN
-REMOVE 3PH 75KVA, 277/480V OH XFMR BANK
P02 GRID #619883-155486: (EXISTING)
-EXIST (2005) 45' CL2 POLE TO REMAIN
P03 GRID #619876-155485: (EXISTING)
-EXIST (2008) 45' CL1 TO REMAIN
PO4R GRID #619872-155486: (6° LINE ANGLE)
-REPL EXIST (1995) 30' CL4 SEC POLE W/ 45' CL3 POLE W/ GRND (AS STAKED)
PD453 6010.1000
**POLE MUST BE INSTALL WITHIN 10' WEST OF THE EXIST POLE**
**BUSH TRIM REQUIRED FROM PO4R-P06 (±108')**
-INST 12kV 3PH SINGLE WINGARM, 397 AAC
TASW313 6033.4012
-INST (1) 11' 8P SINGLE ARM
-INST PINS & INSUL (3)
INDBSA
-INST RIGID CLEVIS (E)
INDNRC
-CONNECT EXIST (2) OH SEC SPANS FROM P06 TO NEW XFMR BANK
-INST (3) 50kVA OH XFMR 277/480v WYE-WYE BANK
BNKRXI 6025.3000
-INST (3) L/B CUTOUT ON WOOD ARM, FUSE @15T
-INST (3) STIRRUPS & HOT CLAMPS
-REMOVE EXIST NEUT DWN GUY & ANCHOR
-INST (2) 3/8" DWN GUYS (PRI & NEUT) GYD3SA,
GYD3SAN 6013.0100
-INST 24" PLATE ANCHOR L=10' (NW)
ANDP24 6012.1000
-RECONNECT EXIST CUSTOMER OH-UG SVC (M01)
-NO COMMS HERE
P05 GRID #619864-155481: (EXISTING)
-EXIST (2016) 50' CL-H1 POLE TO REMAIN
P06 GRID #619873-155501: (EXISTING)
-EXIST (1993) 35' CL5 SEC POLE TO REMAIN
P07 GRID #619875-155511: (EXISTING)
-EXIST (1977) 25' CL5 SPAN GUY POLE TO REMAIN
M01: (EXIST METER #P171644490)
-EXISTING 2 RUNS OF CUSTOMER OWNED UG SVC WIRE TO A 400A CT PANEL
SPAN SPECIFIC NOTES:
P03-P05-PO4R:
-DISCONNECT EXIST 3PH PRIMARY OH WIRES AT P03 AND SWING UNTO NEW PO4R
-SEE TABLE FOR ADDITIONAL SPAN NOTES
WIRE REMOVAL TABLE
Location
Wire Size & Type
Quantity
Length
(per
conductor)
Remarks
From
To
P01
P03
1/0 TPLX OH SEC
2
480'
Total Feet (Wire Size & Type) Removed
POLE TABLE (NEW)
2-20A
Site
Pole Data
#
Grid #
Height
Class
Year
Remarks / Location Ref.
PO4R
619872-155486
45'
3
PSE Equip #
WIRE STRINGING PRIMARY
Location
Pri
Wire Size & Type
Quantity
Length
(Per conductor)
Total
Actual
From
To
PO4R
P03
X
397 MCMTW
3/1
60'
240'
2-15
2-24(2)
3-10
POLE RETIREMENT TABLE
TEMP TRANSFERS
ST. LIGHT TRANSFERS
SITE
POLE DATA
POLE
#
TEL
TV
FIBER
TRAIN
ID NUMBER
GRID #
HEIGHT
CLASS
YEAR
TOPPED
RMVD
PO4
619872-155486
30
5
1995
❑
❑
❑
❑
❑
❑
❑
TRANSFORMER BANK INSTALLATION
Foreman to redline field changes
Installed at site: PO4R
Grid Number: 619872-155486
Bank Configuration:
®WYE/WYE ❑WYE/DELTA ❑OPEN WYE/OPEN DELTA ❑WYE/WYE 120/208v W/10 120/240v
Secondary Voltage:
0120/208v I@ 277/480v 0120/208v W/120/240v 10 0 120/240v 0 240/480v
AO Xfmr MID # 6214200 kVA 50KVA, 277/480V
BO Xfmr MID # 6214200 kVA 50KVA, 277/480V
CO Xfmr MID # 6214200 kVA 50KVA, 277/480V
Foreman to redline the following information
AO Xfmr Company ID#:
BO Xfmr Company ID#:
CO Xfmr Company ID#:
Tested Secondary Voltage
NOTE: The foreman should record one phase -to -neutral and one phase -to -phase
voltage. if the bank is a combination 120/208V with single phase 120/240V,
record the tested voltage of the 240V connection in addition to the voltage of the
120/208 transformer connections.
I
03 619876 1
155485
619864
05 155481
1306
OH MAP: AFTER
SCALE: NONE
619�
155487
SLAG1237
619883 PO
155486
15 kVA (C)
25T
13-477
619873 P06
155501
619875 P07
155511
619872 04
155486
3X 50KVA, 277/480V
Excavated or Place straw mulch
Augered Hole on disturbed area
Install silt fence around Secure bottom of fence
pole excavation Pole with gravel bags
SLOPE �� SLOPE
1 1
FLOWING DITCH or BODY OF WATER
TOP VIEW
UTILITY POLE EROSION CONTROL DETAIL
Not to scale Adjacent to flowing ditches or bodies of water
;o.
I ...
B
•..
1CDLO I
40T
11 I n 3-664
-1 �SS0IV7H
TBM4
�I
15T rohp`� 25T
I I ,ti _wE67,
>I�
I IN X77518TC
OVERHEAD CIRCUIT MAP
SCALE: 6" = 1 Mi
C
POWER GENERAL NOTES - COMMERCIAL PROJECT
1. All materials to be installed in accordance with Puget Sound Energy's (PSE) standards. Any deviation from
this work sketch must be AUTHORIZED by PSE's Project Manager and NOTED on the Foremans' Copy.
2. All switching arrangements and/or outage arrangements are to be made with the Project Manager at least
three (3) working days in advance.
CUSTOMER NOTES
Customer is responsible for all trenching, select backfill, compaction & restoration per Puget Sound Energy
Standards & Local Municipality (See PSE Electric Service Handbook for more details).
1. Contact the Utilities Underground Location Center (1-800-424-5555) at least 48 hours prior to
commencing work to get the underground facilities located.
2. STAKING: The customer will provide all staking (transformer, handhole, trench, grade, lot, pole,
sidewalk, etc.). See sketch and details for locations. Equipment locations must be approved by the
Project Manager.
3. SITE PREPARATION: The work area will be at or near finished grade, clear of trench spoils or
construction materials which would restrict construction and/or equipment access, before work can begin.
4. Roads shall be paved or have a compacted , crushed rock base in place.
5. CLEARANCES: Transformers require a minimum of 6 feet from fire fighting equipment, 10 feet from
combustible walls, overhangs, doors, and windows, and a minimum of 5 feet from the back of curb (or
guard posts will be required per PSE standards). All conduits and vaults are to be at least 5 feet away
from water, storm and sewer lines when paralleling them in the right of way, and at least 1 foot when
crossing them.
6. All work is to be done in accordance with local municipal and county permit requirements as applicable.
7. Inclement weather conditions may cause delays in construction times and dates.
8. EXCAVATION: The customer is to provide all trenching, backfill, vault excavations, compaction and
restoration per this sketch and per PSE standards. A minimum protective cover of 36" is required over
PSE's primary voltage equipment and 24" is required of PSE's secondary voltage equipment. The
customer will provide any and all shoring or they will side slope the trench to 1:1.
9. EROSION & SEDIMENT CONTROL: Erosion & sediment control shall be per PSE standard practice
0150.3200 techniques for temporary erosion & sediment control & any additional local jurisdiction
requirements. (Local jurisdiction may have additional requirements including notes detailing where
erosion or sediment control structures are to be installed, cross section details of the typical erosion
structures, & special requirements for work in sensitive areas.)
10. Customer is required to have meter inspected and approved by L&I/City prior to construction.
CIRCUIT LOADING TABLE
CIRCUIT: EPO-16
AS OF 7/29/2024
A PHASE B PHASE C PHASE
EXIST. PEAK LOAD
203
221
210
EST. NEW LOAD
7
7
7
TOTAL 210 228 21
FOREMAN (CHECK BOX WHEN COMPLETED)
❑ PSE Equipment LOCKED/SECURED & Work Area left in CLEAN/SAFE Condition.
ElGrid, Cable, and Switch numbers INSTALLED & VERIFIED.
ElField Changes RED -LINED on As -built.
E]Material VERIFIED and CHANGES noted on Paperwork.
ElTotal PRIMARY Cable noted on As -built.
❑ Company ID#'s RECORDED in correct location on As -built.
E]Indicate correct FUSE SIZE on As -built & VERIFY proper PHASE.
ElDeviations noted on the As -built and their reason.
❑ I certify that the work performed meets PSE's standards and procedures
and that all quality requirements are met.
Foreman's Signature
Print Name Date
PROJECT PHASE
NOTIF#
ORDER#
PWR Superior
Pole & Wire Retire
OH Misc
Xfmr Retire
Temporary
Job Order
514874623
101176603
108157657
593259483
583077451
N/A
N/A
N/A
N/A
GAS Distribution
Service Stubs
HP Svc/MSA
N/A
N/A
N/A
N/A
N/A
N/A
CABLE TV
PHONE
Project Manager Contact Information:
Manager: Shonda Abercrombie
Cell Phone: 360-443-0013
E-Mail: shonda.abercrombie@pse.com
PSE Locates Required YES
Customer Locates Required NO
Vicinity Map
l
�
o
w
a
0
m
_o
m
MELC ER ST
o
O
d
SITF35
J
/
T EMONT ST
E
SF
A E
�Gtio
�
Owner / Developer Contact Info
City of Port Orchard
216 Prospect Street
Port Orchard, WA 98366
ATTN: Jacki Brown 360-876-7048 office
For contacts below dial 1-888-CALL PSE (225-5773)
CALL 811 TWO BUSINESS DAYS BEFORE YOU DIG
THIS SKETCH NOT TO BE RELIED UPON FOR EXACT LOCATION OF EXISTING FACILITIES
Outages Required YES
Flagging Required YES
REAL ESTATE/EASEMENT
N/A
PERMIT
PT. ORCHARD
3
FUNCTION
CONTACT
PHONE NO
DATE
2
PROJECT MGR
S. Abercrombie
360-443-0013
7/26/24
1
ENGR - POWER
Helene Sparks
360-475-7001
7/26/24
REV#
DATE
BY
DESCRIPTION
ENGR - GAS
N/A
N/A
N/A
COUNTY
KITSAP
Emer Sect
N/A
Gas Wk Ctr
N/A
POWER WK CTR
QSSPE
DRAWN BY
Helene Sparks
360-475-7001
7/26/24
CHECKED BY
S. ABERCROMBIE
360.443.0013
8/5/24
1/4 SEC
SE SEC35 T24 R1 E
OP MAP
N/A
PLAT MAP
N/A
APPROVED BY
253-468-2392
8/14/24
FOREMAN #1
U-MAP NO (POWER)
2401E140
OH CKT MAP
2401E137
JUG CKT MAP
1906E011
CIRCUIT NO
EPO-16
FOREMAN #2
MAPPING
JOINT FACILITIES ARRANGEMENTS
UTILITIES
N/A
N/A
N/A
N/A
CONTACT
N/A
N/A
N/A
N/A
PHONE#
N/A
N/A
N/A
N/A
PUGET MELCER PUMP STATION
SOUND REMOVE IDLE 3PH XFMR BANK, REPL POLE & RELOC PRI SPANS
ENERGY 1201 SIDNEY AVE PORT ORCHARD, WA 98366
PSE
INCIDENT
N/A
MAOP
N/A
Gas Order
N/A
Elect Order
101176603
SCALE
I AS NOTED
PAGE
1/1