HomeMy WebLinkAbout01232015 - The Sinclair, LLC - Contract Bill of Sale (2)BILL OF SALE
THIS BILL OF SALE is made and executed this 23rd day of January , 2015, by and
between The Sinclair, LLC, a Washington Limited Liability Corporation, hereinafter called the
"Grantor" and the City of Port Orchard, a Municipal Corporation, hereinafter called the "Grantee."
WITNESSETH:
That the Grantor, for good and valuable consideration, the receipt of which is hereby
acknowledged, hereby conveys, sets over, assigns, transfer and deliver and warrants to the City of
Port Orchard ownership in the following described personal property situated in Kitsap County,
State of Washington, and installed by the Grantor to date, TO WIT:
Public water mains, sewer mains and frontage improvements and associated appurtenances
constructed both on -site and off -site of the Southwest Sidney Plaza Mixed Use Development
located on the southwest corner of Sidney Road and Sedgwick Road, in Port Orchard,
Washington. These improvements are further described in Exhibit A and itemized in Exhibit B,
both of which are attached hereto and incorporated herein by this reference.
The Grantor hereby warrants that it is the lawful and sole owner of all the personal property above
conveyed, that such items are free from all liens and encumbrances, that the Grantor has the full
power to convey and transfer the same, and that the Grantor will defend the same against the
claims and demands of any and all persons lawfully making claims thereto. The Grantor further
warrants that the execution of this Bill of Sale is an authorized act of said Grantor.
Dated at Gig Harbor, Washington, this 23`d day of January , 2015
[Remainder of page intentionally left blank]
SW Sidney Plaza— Bill of Sale
GRANTOR: (The Sinclair, LLC)
M
By:�
Its: Managing Member
Print Name: Mathew J. Smith
Page 1 of 5
STATE OF WASHINGTON )
)ss
COUNTY OF PIERCE )
On this 23�d day of January , 2015, before me personally appeared
MATHEW J SMITH, to me known to be the managing member for The Sinclair, LLC, a limited
liability corporation, that executed the within and foregoing instrument, and acknowledged the said
instrument to be the free and voluntary act and deed of said corporation, for the uses and
purposes therein mentioned, and on oath stated that he/she was authorized to execute said
instrument.
Given under my hand and official seal this A-;Ydday of (L71.0 , 2015.
,+
TA ,,� Notary Public ' d fc� t e at Washington,
i : y► residing in
" My Comm ission e p res
-: BI. �.••
N
Dated at Port Orchard, Washington, this IL day of , 2015.
CITY OF PORT ORCHARD
Mayor Tim Matthes
STATE OF WASHINGTON )
)ss
COUNTY OF KITSAP )
On this day and year above personally appeared before me, Tim Matthes, who executed
the foregoing instrument, and acknowledged the said instrument to be the free and voluntary act
and deed of the City of Port Orchard for the uses and purposes therein mentioned, and on oath
states he is authorized to execute the said instrument.
\\\',"q ggd�,r,,�my hand and official seal this day of �-e—rYUa 12015.
�.� �,.• Sion EX '%
f o �O�PAD - o ry ub ? an for,he tate of W shir�o
®' �\G ' z = r iding in V'1�� r lr�'%ll N�'� l L,� 1
PU8 :',�o My commission expires
..1-......
SW S dnf+�'�QFBii��bf��\\\\
/rrnn1110\
Page 2 of 5
EXHIBIT A
LIST OF REQUIRED IMPROVEMENTS
The following provides a general description of the improvements conveyed under this Bill of
Sale related to the "Southwest Sidney Plaza Mixed Use Development" project as shown in the
approved construction plans prepared by Barghausen Consulting Engineering Inc, with the
City approval dated June 17, 2013.
1. Specific improvements conveyed under this Bill of Sale includes the following
elements found within this approved construction drawings set as follows:
a. Public water main extension, associated fire hydrants and appurtenances,
within the plat and along Sedgwick Road as shown on Sheets C3.0 though
C3.6 of the approved construction plans.
b. Public sewer main extension, associated manholes and appurtenances, within
the plat and on Sedgwick Road as shown on Sheets C4.0 though C4.5 of the
approved construction plans.
2. The "Southwest Sidney Plaza Mixed Use Development — Offsite Water Main
Extension" project as shown in the approved construction plans prepared by
Barghausen Consulting Engineering Inc, City approval dated December 12, 2013.
Specific improvements conveyed under this Bill of Sale includes the following elements
within this approved construction drawings set as follows:
a. Public water main extension, associated fire hydrants and appurtenances,
within the plat and along the Sidney Road & Sedgwick Road frontages as
shown on Sheets 1 -5 of the approved construction plans.
3. The "Southwest Sidney Plaza Mixed Use Development — Offsite Frontage
Improvements" project as shown in the approved construction plans prepared by
Barghausen Consulting Engineering Inc, City approval dated December 12, 2013.
Specific improvements conveyed under this Bill of Sale includes the following elements
within this approved construction drawings set as follows:
a. Public frontage improvements, including curb, gutter, sidewalks, storm drainage
and asphalt pavement along both he Sidney Road & Sedgwick Road frontages
as shown on Sheets R1-R14 of the approved construction plans.
The items, quantity and value of the improvements describe above and conveyed under this
Bill of Sale are presented in Exhibit B.
SW Sidney Plaza — Bill of Sale
Page 3 of 5
PROJECT NAME:
LOCATION/DESCRIPTION:
DATE:
OUR JOB NO.
CONSTRUCTION COST ESTIMATE
Exhibit B
Southwest Sidney Plaza
Water, Sewer, and Roadway Improvements
November 19, 2014
15386
ITEM
DESCRIPTION QTY I UNIT I UNIT PRICE
TOTAL
WATER MAIN AND APPURTENANCES
On -Site Water Main
1
12-Inch D.I. Water Main
1,351
LF
$75.00
$101,325
2.
8-Inch D.I. Water Main
976
LF
$60.00
$58,560
3.
Fire Hydrant
7
Each
$5,000.00
$35.000
Off -Site Sidney Road Water Main and Improvements
4.
12-Inch D.I. Water Main
249 1
LF 1
$95.00
$23,655
Off -Site Sedgwick Road Water Main and Improvements
5.
8-Inch D.I. Water Main
591
LF
$90.00
$53,190
Sanitary Sewer Main and Improvements
6.
8-Inch PVC Sanitary Sewer
1,572
LF
$45.00
$70,740
7.
Sanitary Sewer Manhole
11
Each
$4,000.00
$44,000
OFF -SITE ROAD IMPROVEMENTS
Sidney Road Improvements
8.
New Curb and Gutter
785
LF
$15.00
$11,775
9.
New Concrete Sidewalk
525
SY
$30.00
$15,750
10.
Type I Catch Basin
4
Each
$1,500.00
$6,000
11.
12-Inch Storm Pipe
372
LF
$40.00
$14,880
12.
24-Inch Storm Pipe
38
LF
$75.00
$2,850
13.
Asphalt Pavement
698
SY
$25.00
$17,450
14.
Type II 48-Inch Structure
1
Each
$3,500.00
$3,500
1 of 2
SW Sidney Plaza — Bill of Sale
Page 4 of 5
15386.012 w ContingencyAs
ITEM
DESCRIPTION
CITY
SW Sidney Plaza — Bill of Sale
2 of 2
Page 5 of 5
15386.012 wo Contingency.As
UNIT UNIT PRICE TOTAL
Sedgwick Road Improvements
15.
New Curb and Gutter
1,025
LF
$15.00
$15,375
16.
New Concrete Sidewalk
685
SY
$30.00
$20,550
17.
Type II 60-Inch Structure
1
Each
$7,500.00
$7,500
18.
Type II 48-Inch Structure
1
Each
$3,500.00
$3,500
19.
Type I Catch Basin
9
Each
$1,500.00
$13,500
20.
12-Inch Storm Pipe
331
LF
$75.00
$24,825
21.
Asphalt Pavement
940
SY
$25.00
$23,500
TOTAL:
$567,425