RESOLUTION NO.017-25
A RESOLUTION OF THE CITY OF PORT ORCHARD, WASHINGTON, ACCEPTING THE
660 ZONE RESERVOIR AND BOOSTER STATION AS CONSTRUCTED BY MCCORMICK
COMMUNITIES, LLC IN ACCORDANCE WITH CONTRACT C048-22 AND APPROVING
THE CERTIFIED CONSTRUCTION COSTS FOR THE PROJECT.
WHEREAS, on March 10, 2022, the City entered into a reimbursement agreement for
utility system improvements with McCormick Communities, LLC, under Contract C048-22; and
WHEREAS, Contract C048-22 required McCormick Communities, LLC to finance and
construct five Capital Improvement Projects, including CIP No. 15 — 580 to 660 Zone Booster
Station and CIP No. 16 — 660 Zone Reservoir; and
WHEREAS, the agreement provided that McCormick Communities, LLC would certify the
final costs of each project and that the City would review and approve those certified costs; and
WHEREAS, McCormick Communities, LLC has completed construction of the 660 Zone
Reservoir and 580 to 660 Zone Booster Station and has submitted the certified construction
costs for both projects; and
WHEREAS, McCormick Communities, LLC has also submitted a Bill of Sale transferring
ownership of the facilities to the City; and
WHEREAS, the Public Works Director has reviewed the submitted documentation and
has determined that the 660 Zone Reservoir and Booster Station are substantially complete and
recommends that the City accept the improvements and approve the certified construction
costs; and
WHEREAS, the certified construction cost for CIP No. 16 — 660 Zone Reservoir is $6,172,
094.68, for which the maximum credit authorized under the agreement is $2,850,000; and
WHEREAS, the full $2,850,000 credit for CIP No. 16 has already been previously
authorized and no additional credit is due; and
WHEREAS, the certified construction cost for CIP No. 15 — 580 to 660 Zone Booster
Station is $2,249,623.67, and the Public Works Director recommends approval of the maximum
credit amount of $750,000 as authorized under the agreement; and
WHEREAS, the City wishes to formally accept ownership of the improvements and
establish the certified construction costs and authorized credits for both projects in accordance
with the 2022 Agreement;
Docusign Envelope ID: 7322C9B3-B1FF-483C-89BB-23CA5E14752E
Resolution No. 017-25
Page 2 of 2
THE CITY COUNCIL OF THE CITY OF PORT ORCHARD, WASHINGTON, HEREBY RESOLVES
AS FOLLOWS:
THAT: The 660 Zone Reservoir and Booster Station as constructed by McCormick
Communities, LLC is accepted in accordance with Contract C048-22.
THAT: The total certified cost of 660 Zone Reservoir and Booster Station is
$8,421,718.35.
THAT: The Mayor is authorized to sign the Bill of Sale which is attached to this
Resolution.
THAT: The Resolution shall take full force and effect upon passage and signatures
hereon.
PASSED by the City Council of the City of Port Orchard, SIGNED by the Mayor and attested
by the Clerk in authentication of such passage this 22nd day of April 2025.
Signed by:
�;3e
Robert Putaansuu, Mayor
ATTF: gTa by:
�jVGUn 1N "':ORS r07"'`�%,,��
Brandy Wallace, MMC, City Clerk
'SEAL
`�� � •�luRpR^: �cA\
Docusign Envelope ID: 7322C9B3-B1FF-483C-89BB-23CA5E14752E
BILL OF SALE
THIS BILL OF SALE is made and executed this /z� day of - ' <' 20 ,
by and between _McCormick Development Corp , a Washington Limited Liability
Corporation, hereinafter called the "Grantor" and the City of Port Orchard, a Municipal
Corporation, hereinafter called the "Grantee."
WITNESSETH:
That the Grantor, for good and valuable consideration, the receipt of which is hereby
acknowledged, hereby conveys, sets over, assigns, transfers and delivers and warrants to the
City of Port Orchard ownership in the following described personal property situated in Kitsap
County, State of Washington, and installed by the Grantor to date, TO WIT:
Public Water and associated appurtenances constructed on -site at the McCormick 660 reservoir
rolect located on parcels 072301-1-006-2003. These improvements are further described in
Exhibit A and itemized in Exhibit B, both of which are attached hereto and incorporated herein
by this reference.
The Grantor hereby warrants that it is the lawful and sole owner of all the personal property
above conveyed, that such items are free from all liens and encumbrances, that the Grantor
has the full power to convey and transfer the same, and that the Grantor will defend the same
against the claims and demands of any and all persons lawfully making claims thereto. The
Grantor further warrants that the execution of this Bill of Sale is an authorized act of said
Grantor.
Dated at _ ytzk�ti� Washington, this -' `l day of APR - k , 20 zV
GRANTOR: (M ormic Development Corp)
By:
Its: A orized Signatory
Print Name: James N Tosti
PASurcty fonw Bill of Sole approved by Immm A"t Bill of Salc - Mader Forth
Docusign Envelope ID: 7322C9B3-B1FF-483C-89BB-23CA5E14752E
[Remainder of page intentionally left blank]
PASc ty fonn nBill of Sal6approved by Interim AttylBill of Sale —Master Form
Docusign Envelope ID: 7322C9B3-B1FF-483C-89BB-23CA5E14752E
STATE OF WASHINGTON
COUNTY OF rl;TC- )SS)
On this ��� day of L- , 20`u before me personally appeared
IFS �s t to me known to be the managing member for
a limited liability corporation, that executed the within
and foregoing instrument, and acknowledged the said instrument to be the free and voluntary
act and deed of said corporation, for the uses and purposes therein mentioned, and on oath
stated that he/she was authorized to execute said instrument.
Given under my hand and official seal this few day of APd-1 L-- , 20 2s-.
William izzey
Notary Public
State of Washington
FIMV Appointment Expires 4/18/2026
CQMmA$iqn Nurrlber 22017366
Notary Public in a d for the State of Washington,
residing in ��� ti,J�ct�
My commission expires
Dated at Port Orchard, Washington, this �� day of CSC , 20_2tj
CITY OF PORT ORCHARD
t
By:
Rob Putaansuu, Mayor
STATE OF WASHINGTON
)ss
COUNTY OF KITSAP
On this day and year above personally appeared before me, Rob Putaansuu, who
executed the foregoing instrument, and acknowledged the said instrument to be the free and
voluntary act and deed of the City of Port Orchard for the uses and purposes therein mentioned,
and on oath states he is authorized to execute the said instrument.
Given under�myRP@pad official seal this day of , 200?�
�0 COMM. ission lays
151224 ber �j y l r
=co Jenine Floyd �- 1
= -+ #taryPublicIn and for the Stat ngton=�04yAApointmentEx }es O in `- �k 1111512026 A,'Z
My commission expires
P, Sumty forms Bill of Salc-app—ed by lntc Any Bill of Sale - Maacr Form
Docusign Envelope ID: 7322C9B3-B1FF-483C-89BB-23CA5E14752E
Docusign Envelope ID: 7322C9B3-B1FF-483C-89BB-23CA5E14752E
Exhibit A
List of Required improvements
This Exhibit provides a general description of the public improvements conveyed to
the City of Port Orchard under this Bill of Sale, related to the "McCormick
Communities 660 Reservoir" project. The improvements are as shown in the
approved construction plans prepared by HDR and Encompass, dated July 31, 2023,
and the architectural plans prepared by Medici Architects, dated September 19,
2024, together with all submittals associated with each respective plan set.
1.) The specific improvements conveyed under this Bill of Sale include, but are not limited to, the
following elements as depicted in the approved construction drawings:
a. Extension of the public sanitary sewer system, including all associated manholes and
appurtenances located within the project area.
b. Extension of the public water main, including all associated f ttings and appurtenances
located within the project area.
c. Construction of public roadway and stormwater infrastructure, including all
associated structures and appurtenances located within the project area.
d. Construction of the 660 Reservoir.
e. Construction of the Pump Station Building, including all associated mechanical,
electrical, and control systems.
The quantities, unit values, and total estimated value of the improvements
described above are detailed in Exhibit B. These improvements are associated with
the following City of Port Orchard permit numbers: PW22-044, PW22-045, and 22-
617.
Docusign Envelope ID: 7322C9B3-B1FF-483C-89BB-23CA5E14752E
Exhibit B
Row Labels
Alliance Steel Fabrication
Bear Inspection & Consulting LLC
City of Port Orchard
Contour Engineering, LLC
Department of Health
Encompass Engineering & Surveying
Evergreen Lumber
Foundation Specialists
HD Fowler Company
HDR Engineering Inc.
Home Comfort Alliance
Insulation Contractors
Interior Technology Modernfold Northwest, Inc
Krazan &Associates, Inc
Malsam Tsang Engineering Corp.
Medici Architects
Mulhern+Kulp
Peltram Plumbing LLC
Puget Sound Energy
Rhyatt Construction LLC
Riley Group
RV Associates, Inc
Sound Acoustics
Source Electric
T Bailey, Inc.
Washington Cedar & Supply Co
Washington State Department of Ecology
Grand Total
Sum of Amount
Sum of Reservoir Costs
W
92,967.92
33.628.12
33, 628.12
37,226.21
18,613.11
5,650.00
2,825.00
1.984.00
1,994.00
21,379.64
10,689.82
2,077.40
-
68,134.34
126, 617.21
-
535,374.31
267,687.16
42,338.45
-
20,413.60
56,535.43
-
7,344.19
7,344.19
11,651.25
-
20,871.25
1,500.00
12,970.64
43,190.76
26,672.10
-
612.50
306.25
1,194,613.85
597, 306.93
40,095.00
-
776,381.84
5,225,510.11
5,225,510,11
9,778.22
-
6,200.00
6,200.00
8,421,718.34
6,172,094.68
Sum of Pump Station Costs
92,967,92
18,613.11
2,825.00
10,689.82
2,077.40
68,134.34
126,617.21
267,687.16
42,338.45
20,413.60
56, 535.43
11,651.25
20,871.25
1,500.00
12,970.64
43,190.76
26,672.10
306.25
597,306.93
40,095.00
776,381.84
9,778.22
2,249,623.67