HomeMy WebLinkAbout036-24 - Miles Resources, LLC - Supplement / Change Order 2CITY OF PORT ORCHARD
Authorization for Change Order No. 2
Date: 10/21/2024
Project:
Contract / Job #
Bethel Ave, Bethel Rd, Lincoln
Ave SE, Mitchell Rd SE
PW2024-003
Contractor: Miles Resources. LLC
THIS CHANGE ORDER AUTHORIZES (add description).
The following items were not installed and will be deducted from the Contract:
15A Temporary Pavement ($6,498.25)
17A Modular Block Wall ($30,750.00)
60A Pedestrian Handrail ($50,000.00)
Total this Change Order: ($87,248.25)
400 Valley Avenue NE
Puyallup, WA 98372
Contract History
Amount Sales Tax Total Date Appvd by
Original Contract
$1,089,176.20
$0.00
$1,089,176.20
Council
Change Order 1
$10,080.00
$0.00
$10,080.00
29 -Jul -24
PW Director
Change Order 2
-$87,248.25
$0.00
-$87,248.25
21 -Oct -24
PW Director
Change Order 3
$0.00
$0.00
Total Contract $1,012,007.95 $0.00 $1,012,007.95
I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
costs are true and accurate.
°m re. amKm�.,aaa, Kimberly Rody 772 d- 10/22/24
�m"�� �=mm,
Contractor Approval Signature Public Wor Director
Denis Ryan
Printed Name & Title
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract
amount established by City Council can be approved by the Public
Works Director.
Change Orders that do not exceed 10%, with a maximum of
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action.
Printed Name
Approved:
Mayor
Attest:
City Clerk
Council Approval Date
https://skillings-my.sharepoint.com/personal/ilee_skillings_com/Documents/20155 Port Orchard RAB/Mitchell Construction/Change Orders/Change Order #2 Bethel Ave Bethel Rd Lincoln Ave SE
Mitchell Rd SE.docx Page 1