HomeMy WebLinkAbout036-24 - Miles Resources, LLC - Supplement / Change OrderCITY OF PORT ORCHARD
Authorization for Change Order No. 3
Date: 10/21/2024
Project:
Contract / Job #
Bethel Ave, Bethel Rd, Lincoln
Ave SE, Mitchell Rd SE
PW2024-003
Contractor: Miles Resources, LLC
400 Valley Avenue NE
Puyallup, WA 98372
THIS CHANGE ORDER AUTHORIZES (add description).
1. During installation of the new storm system, Contractor uncovered previously abandoned utilities that were in conflict with the
new system. Contractor was directed to proceed with resolving the conflicts and to track work via force account. Additional
stump removal and use of vac truck for excavation to protect existing utilities in place was also necessary to complete the
work. New Pay Item added, 61A Utility Conflict Resolution, Force Account, Total: $36,129.45
2. Contractor was also directed to install additional lighting conduit to keep the project on schedule as Lumen encountered
delays to relocate their utilities and PSE encountered delays in finalizing their circuit plan for the lighting. Existing Pay Item
modified, 53A Luminaire Conduit System, Lump Sum, Revised Total: $26,184.00 (Increase of $9,184.00)
3. Total this Change Order: $45,313.45
Contract History
Amount Sales Tax Total Date Appvd by
Original Contract
$1,089,176.20
$0.00
$1,089,176.20
Council
Change Order 1
$10,080.00
$0.00
$10,080.00
29 -Jul -24
PW Director
Change Order 2
-$87,248.25
$0.00
-$87,248.25
21 -Oct -24
PW Director
Change Order 3
$45,313.45
$0.00
$45,313.45
21 -Oct -24
PW Director
Total Contract $1,057,321.40 $0.00 $1,057,321.40
have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
costs are true and accurate.
Kimberly Rody oa,.�za,au=,°r®me=�o,�s�mN-K,mtia.
Contractor Approval Signature
Printed Name & Title
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract
amount established by City Council can be approved by the Public
Works Director.
Change Orders that do not exceed 10%, with a maximum of
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action.
10/22/24
Public WorklDirector
Denis Ryan
Printed Name
Approved:
Mayor
Attest:
City Clerk
Council Approval Date
https://skillings-my.sharepoint.com/personal/ilee_skillings_com/Documents/20155 Port Orchard RAB/Mitchell Construction/Change Orders/Change Order #3 Bethel Ave Bethel Rd Lincoln Ave SE
Mitchell Rd SE.docx Page 1
FORCE ACCOUNT PAYMENT RECORD
Date of Work:
7/11/2024
Prime Contractor:
Miles
Project:
Sub Contractor:
Inspector:
Steve Graff
Item and Description of Work: 5 Hr work from 8:30 am to 1:30 pm multiple underground utilites conflict.
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
LABOR
Reg. I Ot.
Reg. I Ot.
1
Shane Christensen
Laborer Foreman
5.00
84.86
$424.30
2
Justin Fourneir
Operator
5.00
89.6
$448.00
3
Steve Holt
Operator
5.00
89.6
$448.00
4
Rick Cancil
General Labor
5.00
68.83
$344.15
5
Kieth Jeste
Laborer Foreman
5.00
68.83
$344.15
6
$0.00
7
$0.00
8
$0.00
9
$0.00
Subtotal
$2,008.60
31%
$622.67
Labor Total
$2,631.27
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Am
EQUIPMENT
Reg. I Ot.
Reg. I Ot.
1
Yr 2019 #70.251 Excavator Volvo ECR145EL
Diesel / 121 hp / Track
5.00
41.74
$208.70
2
Yr 2016 #30.318 J. Deere Loader 644K
Diesel / 232hp / 2 Axle
5.00
30.12
$150.60
3
Yr 2024 #12.2089 Ford F450 Tool Truck
5.00
2.84
$14.20
4
$0.00
5
$0.00
6
$0.00
Subtotal
$373.50
21%
$78.44
Labor Total
$451.94
6.55
MATERIALS
linvoice # IMaterial IQuantity
lUnit
Pricel Total I
Tax I
I Amount
1
$0.00
2
$0.00
3
$0.00
4
$0.00
5
$0.00
6
$0.00
Subtotal
$0.00
21%
$0.00
Materials Total
$0.00
Subcontractor Force Account Work Total
Variable Overhead for Sub -contract work
Rate: 12% <_ $25K, 10% <_ $100K, 7% > $100K
Grand Total
$3,083.21
FORCE ACCOUNT PAYMENT RECORD
Date of Work:
7/11/2024
Prime Contractor:
Miles
Project:
Sub Contractor:
Inspector:
Steve Graff
Item and Description of Work: Work from 1:30 pm to 4:30 pm lower corn lines for new 12" storm sewer pipe.
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
LABOR
Reg. I Ot.
Reg. I Ot.
1
Shane Christensen
Laborer Foreman
3.00
84.86
$254.58
2
Justin Fourneir
Operator
3.00
89.6
$268.80
3
$0.00
4
Rick Cancil
General Labor
3.00
68.83
$206.49
5
Kieth Jeste
Laborer Foreman
3.00
68.83
$206.49
6
$0.00
7
$0.00
8
$0.00
9
$0.00
Subtotal
$936.36
31%
$290.27
Labor Total
$1,226.63
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
EQUIPMENT
1
Reg. I Ot.
Reg. I Ot.
1
Yr 2019 #70.251 Excavator Volvo ECR145EL
Diesel/ 121 hp / Track
3.00
121.64
$364.92
2
$0.00
3
Yr 2024 #12.2089 Ford F450 Tool Truck
3.00
26.55
$79.65
4
$0.00
5
$0.00
6
$0.00
Subtotal
0.55
$444.57
21%
$93.36
Labor Total
$537.93
MATERIALS
linvoice # IMaterial IQuantity
lUnit
Pricel Total
I Tax I
I Amount
1
$0.00
2
$0.00
3
$0.00
4
$0.00
5
$0.00
6
$0.00
Subtotal
$0.00
21%
$0.00
Materials Total
$0.00
Subcontractor Force Account Work Total
Variable Overhead for Sub -contract work
Rate: 12% <_ $25K, 10% <_ $100K, 7% > $100K
Grand Total
$1,764.56
FORCE ACCOUNT PAYMENT RECORD
Date of Work:
7/12/2024
Prime Contractor:
Miles
Project:
MIL RAB
Sub Contractor:
Inspector:
Item and Description of Work: Lowering com lines 7:00 am to 10:00 am
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
LABOR
Reg. I Ot.
Reg. I Ot.
1
Shane Christensen
Laborer Foreman
3.00
84.86
$254.58
2
Justin Fourneir
Operator
3.00
89.6
$268.80
3
$0.00
4
Rick Cancil
General Labor
3.00
68.83
$206.49
5
Kieth Jeste
Laborer Foreman
3.00
68.83
$206.49
6
$0.00
7
$0.00
8
$0.00
9
$0.00
Subtotal
$936.36
31%
$290.27
Labor Total
$1,226.63
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
EQUIPMENT
Reg. I Ot.
Reg. I Ot.
1
Yr 2019 #70.251 Excavator Volvo ECR145EL
Diesel/ 121 hp / Track
3.00
121.64
$364.92
2
No Loader on Signed Sheet
$0.00
3
Yr 2024 #12.2089 Ford F450 Tool Truck
3.00
26.55
$79.65
4
$0.00
5
$0.00
6
$0.00
Subtotal
$444.57
21%
$93.36
Labor Total
$537.93
MATERIALS
linvoice # IMaterial IQuantity
lUnit
Pricel Total
I Tax I
I Amount
1
$0.00
2
$0.00
3
$0.00
4
$0.00
5
$0.00
6
$0.00
Subtotal
$0.00
21%
$0.00
Materials Total
$0.00
Subcontractor Force Account Work Total
Variable Overhead for Sub -contract work
Rate: 12% <_ $25K, 10% <_ $100K, 7% > $100K
Grand Total
$1,764.56
FORCE ACCOUNT PAYMENT RECORD
Date of Work:
7/13/2024
Prime Contractor:
Miles
Project:
MIL RAB
Sub Contractor:
Inspector:
Steve Graff
Item and Description of Work:
Change pipe grade move 12" pipe up in CB and re grout.
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
LABOR
Reg. I Ot.
Reg. I Ot.
1
Shane Christensen
Laborer Foreman
1.00
84.86
121.96
$121.96
2
Justin Fourneir
Operator
1.00
89.6
118.94
$118.94
3
Steve Holt
Operator
1.00
89.6
94.89
$94.89
4
Rick Cancil
General Labor
1.00
68.83
94.89
$94.89
5
Kieth Jeste
Laborer Foreman
1.00
68.83
121.96
$121.96
6
$0.00
7
$0.00
8
$0.00
9
$0.00
Subtotal
$552.64
31%
$171.32
Labor Total
$723.96
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
EQUIPMENT
Reg. I Ot.
Reg. I Ot.
1
Yr 2019 #70.251
Excavator Volvo ECR145EL
Diesel / 121 hp / Track
1.00
121.64
$121.64
2
Yr 2016 #30.318
Loader J.Deere 644K
Diesel / 232hp / 2 Axle
1.00
82.63
$82.63
3
Yr 2024 #12.2089
Ford F450 Tool Truck
1.00
26.55
$26.55
4
$0.00
5
$0.00
6
$0.00
Subtotal
$230.82
21%
$48.47
Labor Total
$279.29
MATERIALS
linvoice #
IMaterial IQuantity
lUnit
Pricel Total
I Tax
I
I Amount
1
$0.00
2
$0.00
3
$0.00
4
$0.00
5
$0.00
6
$0.00
Subtotal
$0.00
21%
$0.00
Materials Total
$0.00
Subcontractor Force
Account Work Total
Variable Overhead for Sub -contract work
Rate: 12% <_ $25K, 10% <_ $100K, 7% > $100K
Grand Total
$1,003.25
FORCE ACCOUNT PAYMENT RECORD
Date of Work:
7/17/2024
Prime Contractor:
Miles
Project:
MIL RAB
Sub Contractor:
Inspector:
Steve Graff
Item and Description of Work:
Install 64' of 8" Ductile Iron Pipe. Grout pipes to CBs. Install, reducer, frame and grate.
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
LABOR
Reg. I Ot.
Reg. I Ot.
1
Shane Christensen
Laborer Foreman
8.00
84.86
$678.88
2
Justin Fourneir
Operator
8.00
89.6
$716.80
3
Steve Holt
Operator
8.00
89.6
$716.80
4
Rick Cancil
General Labor
8.00
68.83
$550.64
5
Kieth Jeste
Laborer Foreman
8.00
68.83
$550.64
6
$0.00
7
$0.00
8
$0.00
9
$0.00
Subtotal
$3,213.76
31%
$996.27
Labor Total
$4,210.03
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
EQUIPMENT
Reg. I Ot.
Reg. I Ot.
1
Yr 2019 #70.251
Excavator Volvo ECR145EL
Diesel / 121 hp / Track
8.00
121.64
$973.12
2
Yr 2016 #30.318
Loader J.Deere 644K
Diesel / 232hp / 2 Axle
8.00
82.63
$661.04
3
Yr 2024 #12.2089
Ford F450 Tool Truck
8.00
26.55
$212.40
4
$0.00
5
$0.00
6
$0.00
Subtotal
$1,846.56
21%
$387.78
Labor Total
$2,234.34
MATERIALS
linvoice #
IMaterial IQuantity
lUnit
Pricel Total
I Tax I
I Amount
1
$0.00
2
$0.00
3
$0.00
4
$0.00
5
$0.00
6
$0.00
Subtotal
$0.00
21%
$0.00
Materials Total
$0.00
Subcontractor Force
Account Work Total
Variable Overhead for Sub -contract work
Rate: 12% <_ $25K, 10% <_ $100K, 7% > $100K
Grand Total
$6,444.37
FORCE ACCOUNT PAYMENT RECORD
Date of Work:
7/19/2024
Prime Contractor:
Miles
Project:
M/L RAB
Sub Contractor:
Inspector:
Steve Graff
Item and Description of Work:
Install 64' of 8" Ductile Iron Pipe. Grout pipes to CBs. Install, reducer, frame and grate.
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
LABOR
Reg. I Ot.
Reg. I Ot.
1
Shane Christensen
Laborer Foreman
6.00
84.86
$509.16
2
Justin Fourneir
Operator
6.00
89.6
$537.60
3
Steve Holt
Operator
6.00
89.6
$537.60
4
Rick Cancil
General Labor
6.00
68.83
$412.98
5
Kieth Jeste
Laborer Foreman
6.00
68.83
$412.98
6
$0.00
7
$0.00
8
$0.00
9
$0.00
Subtotal
$2,410.32
31%
$747.20
Labor Total
-�
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
EQUIPMENT
I
Reg. I Ot.
Reg. I Ot.
1
Yr 2019 #70.251
Excavator Volvo ECR145EL
Diesel / 121 hp / Track
6.00
121.64
$729.84
2
Yr 2016 #30.318
Loader J.Deere 644K
Diesel / 232hp / 2 Axle
6.00
82.63
$495.78
3
Yr 2024 #12.2089
Ford F450 Tool Truck
6.00
26.55
$159.30
4
$0.00
5
$0.00
6
$0.00
Subtotal
$1,384.92
21%
$290.83
Labor Total
_
r
$1,675.75
MATERIALS
linvoice # IMaterial
IQuantity
lUnit
Pricel Total I
Tax I
I Amount
1
8" Ductile Iron Pipe
64
43.15 2761.60 278.92
$3,040.52
2
8" PVC SDR35 Pipe
28
10.35 289.80
29.27
$319.07
3
SDR35 Grouted Adaptor
2
116.32 232.64
23.50
$256.14
4
$0.00
5
331.69
$331.69
6
$0.00
Subtotal
$3,947.42
21%
$828.96
Materials Total
$4,776.38
Subcontractor Force
Account Work Total
Variable Overhead for Sub -contract work
Rate: 12% <_ $25K, 10% <_ $100K, 7% > $100K
Grand Total
$9,609.65
FORCE ACCOUNT PAYMENT RECORD
Date of Work:
7/22/2024
Prime Contractor:
Miles
Project:
MIL RAB
Sub Contractor:
Inspector:
Steve Graff
Item and Description of Work:
Excavate and move existing copper phone line.
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
LABOR
Reg. I Ot.
Reg. I Ot.
1
Shane Christensen
Laborer Foreman
6.00
84.86
$509.16
2
Justin Fourneir
Operator
6.00
89.6
$537.60
3
Steve Holt
Operator
6.00
89.6
$537.60
4
Rick Cancil
General Labor
6.00
68.83
$412.98
5
Kieth Jeste
Laborer Foreman
6.00
68.83
$412.98
6
$0.00
7
$0.00
8
$0.00
9
$0.00
Subtotal
$2,410.32
31%
0.8
$747.20
Labor Total
$3,157.52
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
EQUIPMENT
Reg. I Ot.
Reg. I Ot.
1
Yr 2019 #70.251
Excavator Volvo ECR145EL
Diesel / 121 hp / Track
6.00
121.64
$729.84
2
Yr 2016 #30.318
Loader J.Deere 644K
Diesel / 232hp / 2 Axle
6.00
82.63
$495.78
3
Yr 2024 #12.2089
Ford F450 Tool Truck
6.00
26.55
$159.30
4
$0.00
5
$0.00
6
$0.00
Subtotal
6
$1,384.92
21%
$290.83
Labor Total
$1,675.75
MATERIALS
linvoice #
IMaterial IQuantity
lUnit
Pricel Total
I Tax I
I Amount
1
$0.00
2
$0.00
3
$0.00
4
$0.00
5
$0.00
6
$0.00
Subtotal
$0.00
21%
$0.00
Materials Total
$0.00
Subcontractor Force
Account Work Total
Variable Overhead for Sub -contract work
Rate: 12% <_ $25K, 10% <_ $100K, 7% > $100K
Grand Total
$4,833.27
FORCE ACCOUNT PAYMENT RECORD
Date of Work:
7/23/2024
Prime Contractor:
Miles
Project:
MIL RAB
Sub Contractor:
Inspector:
Steve Graff
Item and Description of Work:
Excavate and remove large stump to place CB #49.
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
LABOR
Reg. I Ot.
Reg. I Ot.
1
Shane Christensen
Laborer Foreman
1.00
84.86
$84.86
2
Justin Fourneir
Operator
1.00
89.6
$89.60
3
Steve Holt
Operator
1.00
89.6
$89.60
4
Rick Cancil
General Labor
1.00
68.83
$68.83
5
Kieth Jeste
Laborer Foreman
1.00
68.83
$68.83
6
$0.00
7
$0.00
8
$0.00
9
$0.00
Subtotal
$401.72
31%
$124.53
Labor Total
$526.25
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
EQUIPMENT
Reg. I Ot.
Reg. I Ot.
1
Yr 2019 #70.251
Excavator Volvo ECR145EL
Diesel / 121 hp / Track
1.00
121.64
$121.64
2
Yr 2016 #30.318
Loader J.Deere 644K
Diesel / 232hp / 2 Axle
1.00
82.63
$82.63
3
Yr 2024 #12.2089
Ford F450 Tool Truck
1.00
26.55
$26.55
4
$0.00
5
$0.00
6
$0.00
Subtotal
$230.82
21%
$48.47
Labor Total
$279.29
MATERIALS
linvoice #
IMaterial IQuantity
lUnit
Pricel Total
I Tax I I
Amount
1
$0.00
2
$0.00
3
$0.00
4
$0.00
5
$0.00
6
$0.00
Subtotal
$0.00
21%
$0.00
Materials Total
$0.00
Subcontractor Force
Account Work Total
Variable Overhead for Sub -contract work
Rate: 12% <_ $25K, 10% <_ $100K, 7% > $100K
Grand Total
$805.54
FORCE ACCOUNT PAYMENT RECORD
Date of Work:
7/29/2024
Prime Contractor:
Miles
Project:
MIL RAB
Sub Contractor:
Inspector:
Steve Graff
Item and Description of Work:
Moving Phone Line to Install CB51 and 38 LF of 12" PVC to MH64
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
LABOR
Reg. I Ot.
Reg. I Ot.
1
Shane Christensen
Laborer Foreman
3.00
84.86
$254.58
2
Justin Fourneir
Operator
3.00
89.6
$268.80
3
Steve Holt
Operator
3.00
89.6
$268.80
4
Rick Cancil
General Labor
3.00
68.83
$206.49
5
Kieth Jeste
Laborer Foreman
3.00
68.83
$206.49
6
$0.00
7
$0.00
3
$0.00
9
$0.00
Subtotal
$1,205.16
31%
$373.60
Labor Total
$1,578.76
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
EQUIPMENT
Reg. I Ot.
Reg. I Ot.
1
Yr 2019 #70.251
Excavator Volvo ECR145EL
Diesel / 121 hp / Track
3.00
121.64
$364.92
2
Yr 2016 #30.318
Loader J.Deere 644K
Diesel / 232hp / 2 Axle
3.00
82.63
$247.89
3
Yr 2024 #12.2089
Ford F450 Tool Truck
3.00
26.55
$79.65
4
$0.00
5
$0.00
6
$0.00
Subtotal
$692.46
21%
$145.42
Labor Total
$837.88
26.5
llnvoice #
IMaterial IQuantity
lUnit
Pricel Total
I Tax I
I Amount
1
5
$0.00
2
$0.00
3
$0.00
4
$0.00
5
$0.00
6
$0.00
Subtotal
$0.00
21%
$0.00
Materials Total
$0.00
Subcontractor Force
Account Work Total
Variable Overhead for Sub -contract work
Rate: 12% <_ $25K, 10% <_ $100K, 7% > $100K
Grand Total
$2,416.64
FORCE ACCOUNT PAYMENT RECORD
Date of Work: 8/8/2024
Prime Contractor:
Miles
Project: MIL RAB
Sub Contractor:
Inspector: Steve Graff
Item and Description of Work: Vac Truck to clean around telephone Pedestal
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
Amount
LABOR
Reg. I Ot.
Reg. I Ot.
1
$0.00
2
$0.00
3
$0.00
4
$0.00
5
$0.00
6
$0.00
7
$0.00
8
$0.00
9
$0.00
Subtotal
$0.00
31%
$0.00
Labor Total
$0.00
Code/craft group
Workman/Equipment Working
Occupation/Equipment Size
Hours Worked
Rate
EQUIPMENT
Reg. I Ot.
Reg. I Ot.
1
$0.00
2
$0.00
3
$0.00
4
$0.00
5
$0.00
6
$0.00
Subtotal
$0.00
21%
$0.00
Labor Total
$0.00
MATERIALS linvoice # IMaterial IQuantity lUnit
Pricel Total I
Tax I
I Amount
1 Vac Truck to clean around telephone Pedestal
1.00 3640.00
$3,640.00
2
$0.00
3
$0.00
4
$0.00
5
$0.00
6
$0.00
Subtotal
$3,640.00
21%
$764.40
Materials Total
$4,404.40
Subcontractor Force Account Work Total
Variable Overhead for Sub -contract work
Rate: 12% <_ $25K, 10% <_ $100K, 7% > $100K
Grand Total
$4,404.40
MILES RESOURCES LLC
400 Valley Avenue NE
Puyallup, WA 98372
WA. Contractor LIC, # MILESRL897RK
Phone: (253) 383-3585
Fax: (253) 572-8648
To:
City Of Port Orchard
Contact: K. Chris Hammer
Address:
216 Prospect Street
Phone:
Port Orchard, WA 98366
Fax:
Project Name:
Bethel Ave, Bethel Rd, Lincoln Ave SE, Mitchell Rd SE
Bid Number:
Project Location:
2734 Mitchell Rd SE, Port Orchard, WA
Bid Date: 3/21/2024
Miles Resources is pleased to offer the following quotation for the above referenced project. Our proposed scope of work is as follows:
Item # Item Description Estimated Quantity Unit Unit Price Total Price
1 Install 2" PVC Conduit Per Revised Plans 1.00 LS $9,184.00 $9,184.00
Notes:
• COP for the additional 2" conduit to be installed by MB Electric.
Payment Terms:
Terms: Main Contract terms apply
ACCEPTED:
The above prices, specifications and conditions are satisfactory and
are hereby accepted.
Buyer:
Signature:
Date of Acceptance:
Total Bid Price: $9,184.00
CONFIRMED:
MILES RESOURCES LLC
Authorized Signature:
Estimator: Kim Rody
(253) 307-4900 kim.rody@milesresources.com
Page 1 of 1
v
e E►ecCr C
Change Order Request #001
Date: 8/5/2024
To: Mike @ Camp Solomon Schechter
From: Teila Appleby - Cell: 360-870-8578 Office: 360-455-1025
RE: Bethel Ave - Revised Illumination & PSE Plan - Conduit Adder
Here is our pricing and breakdown for the added cost to:
1. Provide and install 2" PVC conduit per plans.
2. Trenching and Backfill included.
TOTAL COST $ 8,200.00
Acceptance of Proposal: The above prices, specifications and conditions are satisfactory and are
hereby accepted. You are authorized to do the work as specified.
Date of Acceptance
Signature
Print Name [or Title]
P.O. Box 5758, Lacey, WA 98509-5758
Telephone (360) 455-1025 Fax (360) 455-1026