HomeMy WebLinkAbout027-25 - General Mechanical, Inc. - Supplement / Change Order 1Authorization for Change Order No. 1
Date: 9/15/2024
Project: Melcher St. Pump Sta. Rehab
Contract / Job # CO27-25
Contractor: General Mechanical, Inc.
2316 S State Street
Tacoma, WA 98405
THIS CHANGE ORDER AUTHORIZES (add description).
Additional Work/Constniction Change Directives: Work Change Directive 001- Asphaltic coaling on the exterior coaling of the DI pipe is directly buried. The DI
pipe in the pump station will be in open and needs to be primed for the City to paint in the fixture. The cost of the CO is to change the exterior coating of the pipe.
See Work Change Directive 001 for additional information. $2,100.00.
Work Change Directive 002- Per RFI 002, the size of the service metering equipment and the generator connection box does not fit on the wall shown on E-201.
Credit- Moving the generator connection cabinet to the new location will shorten the length of conduit and wire required. Addition- Moving the main fuse
disconnect up above the pump station has increased the conduit and wire lengths, both cabinets will require additional strut stands to be built. See RFI 001 for
additional information and COP for cost break out. $7,300.00.
Change Order#1 1 Totals- $10,274.20 w/ tax.
_•� ,v.,-.:ip'.:+eo"•S:ic ,L. s'3i• "';+a :v�+s�,l-stit:. :5••n'rF',:A :_�'... •g,.Y
..>,: CAr≥itr•act istor, ��r : ^. :.a:':?: E
'.J•" =i.'1'�t Vii': �{ ': ��r�"• 'vp.S,, . ..i' "' ti�Y.� ', �i ��•e� yw, .\`� i.L -,
•s.. j F,: ,yy;;{��,,.. :a .,' ;:73'3; ,p..,2 i.�.°' ,- A.:-sti
�;�,::.F.:.:,.,.�•,�..: ,,..,':i::;;�:..;:�:: ;w.... unt :SalesTax" , ;� r: Total:� :;::..�r.. :�Da[e �-,:�;.d�.
.f: _•s, ,�;.,;.,,;.
Ap pvd=b .:.,
Original Contract
$715,300.00
$66,522.90
$781,822.90
25 -Feb -25
Council
Change Order 1
$9,400.00
$874.20
$10,274.20
16 -Sep -25
PW Director
Total Contract $724,700.00 $67,397.10 $792,097.10
I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
costs are true and accurate.
Contractor Approval Signature
)JSo zruc- 7"4
Printed Name & Title
Public Works Director
j1 c
Printed Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract Approved:
amount established by City Council can be approved by the Public
Works Director.
Change Orders that do not exceed 10%, with a maximum of Attest:
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action.
Mayor
City Clerk
Council Approval Date