HomeMy WebLinkAbout088-25 - Transpo Group, Inc. - Contract Amendment 1Docusign Envelope ID: 194C0378-5B30-8E09-8175-78811616F0D1
CITY OF PORT ORCHARD
Authorization for Amendment No. 1
Date: 4/23/2026
Project: Anderson Hill RAB Design
Contract / Job # C088-25
Contractor: TransDo Group Inc.
12131 113th Ave NE,
Suite 203 Kirkland, WA 98034
THIS Amendment AUTHORIZES THE FOLLOWING CHANGES TO THE CONTRACT C088-25:
and a revised fee estimate as described in Exhibit A-1 — Scope of Work and the Amendment 1 Fee Estimate.
Agreement C088-25 is amended to include supplemental project management, additional survey work (Subtask 2.3
— Supplemental Topographic Survey), and environmental permitting services including a stream delineation and
mitigation plan, as further detailed in Exhibit A-1. The fee for these additional services shall be as shown in the
Amendment 1 Cost Estimate Worksheet dated April 23, 2026. In all other respects, the underlying Agreement
between the parties shall remain in full force and effect, amended as set forth herein, but only as set forth herein.
Contract History
Amount Sales Tax Total Date Appvd by
Original Contract
$294,300.00
$0.00
$294,300.00
29 -Aug -25
Council
Change Order 1
$30,800.00
$0.00
$30,800.00
12 -May -26
Council
Total Contract $30,800.00 $0.00 $325,100.00
I have reviewed the Amendment information above and certify that to the best of my knowledge
descriptions and costs are true and accurate.
Ryan Peterson az zs s: sa;a?s :o�ooe5o°�� P�m.
Contractor Approval Signature
an Peterson, Principal
Printed Name & Title
DocuSigned by:
�f✓I/lds
E
Public Works Director
Denis Ryan
Printed Name
Public Works Contracts Greater than $35,000: Change Orders that do not exceed 10%,
with a maximum of $50,000, of either legally authorized budget limit or contract
amount established by City Council can be approved by the Public Works Director.
Total Contract Amount shall reset to reflect new Council -approved contract totals
authorized prior to the requested change order. $50,000-$100,000 require Mayoral
Approval. $100,000 and over require Council Approval
Public Works Contracts under $35,000, change orders that individually do not exceed
$7,500 with an aggregate cap of $10,000.
Public Works Contracts unbudgeted and under $7,500: All Change Orders that do not
exceed an aggregate cap of $7,500 (Excluding underlying value), provided there are
departmental funds available in the budget.
All Departments: Mayor approves any and all Change orders that do not exceed 10%
of either authorized budget limit or contract amount established by City Council. With
a maximum aggregate amount of $100,000. Total Contract Amount shall reset to
reflect new Council -approved contract totals authorized prior to the requested change
order. Any individual Change order that is over $100,000 requires Council approval.
Signed by:
Approved:
Mayor
Attest:
City Clerk
May 12, 2026
Council Approval Date
Docusign Envelope ID: 194C0378-5B30-8E09-8175-78811616F0D1
Exhibit A-1 — Scope of Work
Client Name: City of Port Orchard
Project Name: SW Old Clifton Rd/Anderson Hill Rd SW Intersection Improvements
Original Agreement Dated: August 29, 2025
Amendment Dated: April 23, 2026 TG: 1.25220.00
The existing Agreement for Services between Transpo Group (Transpo) and the City of Port Orchard
(Client) is amended to include the following additional services and revised fee projection. All terms and
conditions described in the Agreement remain in force and are not modified by this Amendment.
Scope of Services
In addition to the services described in Exhibit A of the Agreement, Transpo will provide the following
services:
TASK I Project Management / Meetings
The CONSULTANT will provide ongoing project management and subconsultant coordination associated
with the additional work outlined in this contract amendment.
TASK 2 Data Collection and Analysis
SUBTASK 2.3 - Supplemental Topographic Survey (PACE)
The original scope of services assumed no additional survey work would be necessary. Due to additional
grading impacts and to support the stream delineation efforts, additional survey is necessary for the project.
The CONSULTANT will use in-house survey staff to perform all field survey work to supplement and extend
the current topographic plan as shown in ATTACHMENT A. Supplemental survey information will include
additional topographic information in the northwest and northeast corners of the intersection, along the
south right-of-way (ROW) line, and the shoulders extending west of the project. Additionally, the
CONSULTANT will survey flags placed under Task 3 as described below, pothole locations if available,
and review existing ROW.
Subtask 2.3 Assumptions
• The CLIENT will coordinate right -of -entries, if needed. The CONSULTANT will notify the CLIENT of
any right -of -entry needs to conduct the work.
Subtask 2.3 CONSULTANT Deliverables
• Topographic survey CAD file, incorporating newly collected survey data, merged with original
survey file to provide a single, consolidated base mapping dataset.
Subtask 2.3 CLIENT Responsibilities
• Coordinate right -of -entries, as needed.
TASK 3 Environmental Permitting (GeoEngineers)
The original scope of services assumed the 2018 critical areas report and mitigation plan would be used for
permitting purposes. To account for updated code requirements, revised project impact boundaries, and
verify the stream delineation, the CONSULTANT will conduct a site visit and prepare a stream delineation
report with buffer mitigation plan.
Docusign Envelope ID: 194C0378-5B30-8E09-8175-78811616F0D1
The CONSULTANT will conduct a site visit to delineate the stream with flags within the project area. A
sketch of the flag locations will be prepared and provided for survey purposes (Subtask 2.3). A stream
delineation report will be prepared for permitting purposes. This report will document onsite conditions,
stream type, buffer width, and proposed buffer mitigation. The mitigation plan will be based on impact areas
provided by the design team such as, but not limited to: staging areas, excavation areas, and other
permanent and temporary impacts. The CONSULTANT will also recommend plant selections to be
installed as mitigation for stream buffer impacts based on an assessment of the area from the site visit.
Task 3 Assumptions
• The CLIENT will secure permission for the CONSULTANT to access the project area for the site
visit. The CONSULTANT will notify the CLIENT of any right -of -entry needs to conduct the work.
• The site visit will be conducted by up to two biologists. It is anticipated the work will be completed in
one day.
• No wetlands are present within the project site or within 300 feet of the project work area. No more
than one stream will be identified and delineated during the site visit.
• The project will only result in stream buffer impacts; i.e. there will be no direct impacts to the
stream.
• Project impacts are assumed to be compensated for with buffer enhancements including native
plantings.
• There will be one round of revisions to the stream delineation report before the report is finalized.
• Report figures will be developed using the most recent survey base file, which will incorporate
surveyed points for the stream delineation flags.
• The CLIENT is responsible for permitting fees, if any.
Task 3 CONSULTANT Deliverables
• Site visit
• Stream delineation and mitigation plan report
Task 3 CLIENT Responsibilities
• Coordinate right -of -entries, as needed.
• Pay permitting fees, if any.
Docusign Envelope ID: 194C0378-5B30-8E09-8175-78811616F0D1
transpogIroup i'
Cost Estimate Worksheet
Number / Project Name
1.25220.00
Billing rates are effective from June 28, 2025 through June 26, 2026, within the ranges shown in the attachment
Only key staff are shown and other staff may work on and charge to the project as needed by the project manages
Labor
initial:
labor category
cost rate
Project
Quality
Traffic
Civil
Traffic
Project
Manager
Control
Civil Lead
Lead
Support
Support
Admin
Eng L5
Prin L7
Eng L5
Eng L4
Eng L3
Anyl L2
PA L4
$225.00
$280.00
$230.00
$195.00
$160.00
$150.00
$175.00
roject Management / Meetings 8 2 2 12 $2,650
0 $0
0 $0
Total Hours 8 0 2 2 _ 0 0 0 12
$1,800 $0 $460 $390 $0 $0 $0
Reimbursable Expenses:
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
Application
Business Meals
Mileage
Miscellaneous
Models/Renderings/Photos
Parking
Records Filing
Registrations
Reproductions
Shipping/Courier
Specialty Software
Supplies
Traffic Accident Data
Traffic Count Vendors
Travel, Hotel, Taxi, & Air Fare
Subconsu
cants:
PACE $11,173
GeoEngineers $16,940
Subconsultant C
Subconsultant D
Subconsultant E
TOTAL ESTIMATE I $30,800
Cost Estimate Prepared on: 4/23/2026