090-20 - Murraysmith, Inc. - CONSOR - Contract Amendment 1CITY OF PORT ORCHARD
Authorization for Amendment No. 1
Date: March 29, 2021 _ Contractor: MurraySmith, Inc.
Project: Splash Pad VE Project 600 University Street, Suite 300
Contract / Job # C090.20 Seattle, WA 99101
THIS CHANGE ORDER AUTHORIZES A TIME EXTENSION ONLY. CONTRACT END DATE EXTENDED TO
December 3151, 2021.
Contract History
Amount Sales Tax Total Date Appvd b
Original Contract
$:24,180.00
$0.00
$24,180.00
15-Dec-20
council
Amendment 1
$0.00
$0.00
$0.00
29-Mar-21
PW Director
Total Contract $24,280.00 $0.00 $24 180.00
I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
costs are true and accurate.
Contractor Approval Signature Publ Works ctor ngineer
f -C E 4, OpCe i. PA, jKKJ ,-I-L.._ !F—.N(/ WMARK R, DOR:
ited Name & Title fPrinted Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract Approved:
amount established by City Council can be approved by the Public Mayor
Works Director.
Change Orders that do not exceed 10%, with a maximum of Attest:
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action.