069-21 - Technical Systems, Inc. - Supplement / Change Order 1Authorization for Change Order No. 1
Date: September 7, 2021
Project: SCADA Wireless
Contract /Job #
Communications Panel Build
C069-21
Contractor: Technical Systems, Inc.
2303 196" St SW Suite B
Lynnwood, WA 98036
This Change Order Authorizes an extension to the contract termination date only for C069-21 due to delays in
materials for the fabrication of the control panel. The contract termination date shall be extended to December
31, 2021.
Amount
Contract
Sales Tax
History
Total Date Appvd b
Original Contract
$141400.00
$1,296.00
$15,696900
07-Juk21
Mayor
Change Order 1
$0.00
$0.00
$0.00
07-Se -21
PW DIRECTOR
Total Contract $14,400.00
$10296.00
$151696.00
I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
costs are true and accurate.
Contractor Approval Signature
Printed Name & Title v
MARK R. DORSEY, P.E.
Printed Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget Ilmit or contract Approved
amount established by City Council can be approved by the Public
Works Director,
Change Orders that do not exceed 10%, with a maximum of Attest:
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action.
Mayor
City Clerk
Council Approval Date
U:\1_Adminstrallonw Systems&AsseiManagemenlSupport\Telemetry_SCADA ShakeAleri\TelemetrylSCADA\Wireless Communication Panel\ContractlCOH1-0069-21-TSl doc