Loading...
042-20 - Cascadia Consulting Group, Inc. - Contract Amendment 1EXHIBIT B SCOPE OF WORK - AMENDMENT #1 Gity of Port Orchard Shoreline Master Program Update Support Project Schedule Time extension for additional work through December 30,2020 Additional Work Tasks & Deliverables Cascadia Consulting Group and Herrera Environmental will conduct additional work as requested to support the City of Port Orchard's Shoreline Master Program update. The budget estimate for these additional tasks include project and contract management responsibilities, including communication with the City project manager, progress reports, invoicing, schedule, and budget tracking. Task 3. Presentation to Planning Commission (August/September) Herrera will convert its draft sea level rise analysis document into a PowerPoint presentation and present it at an online meeting of the Port Orchard Planning Commission, currently slated for September L,2020. Two Herrera staff will attend the presentation to present findings and address questions on the analysis. The presentation materials will be provided for the City's future use, such as additional public meetings. Assumptions r Two Herrera staff will remotely attend the meeting. o Presentation will be half-an-hour in length, with up to an additional hour for questions. o No new analysis will be required for the presentation. . The presentation can and will be provided to the City for public use following the meeting. Deliverobles o Presentation to the Planning Commission, including a question-and-answer session o Presentation materials for future use. Estimated Cost: 53,500 Task 4. Presentation to City Council (September) Herrera will use the PowerPoint version of the draft sea level rise analysis document developed in Task 3 and also present it at an online session of the Port Orchard City Council, currently scheduled for September 22,2020. Two Herrera staff will attend the presentation to present findings and address questions on the analysis. The presentation materials will be provided for the City's future use, such as additional public meetings. Cqscadia Consulting Group, lnc. P rofess io n o I Se rv i ce Ag ree me nt L August 2020 Controct Amendment #7 Assumptions o Two Herrera staff will remotely attend the meeting. o Presentation will be half-an-hour in length, with up to an additional hour for questions. o No new analysis will be required for the presentation. o The presentation can and will be provided to the City for public use following the meeting Deliverables e Presentation to the City Council, including a question-and-answer session o Presentation materials for future use. Estimoted Cost: 57,600 Task 5. Additional Round of Reviews (september/October) The original scope of work included a single round of review and revisions. Due to schedule changes, mostly related to the COVID-19 pandemic, it is desired by the City to publicly distribute an updated/revised version of prior to incorporating comments from Ecology, which may be required as a term in the grant. Ecology will provide its comments following this public posting, but the timing is uncertain. The consultant will incorporate Ecology comments and recommendations into the previously revised document before finalizing the document. Assumptions o One round of revisions regarding Ecology's comments will be provided to Herrera following submittal of a revised draft sea level rise analysis document. This round may also include revisions following the Planning Commission and City Council briefings. . Ecology and City staff will have an opportunity to review changes being made to the documents, but that review will be limited to the changed portions of the document and a final version will be prepared based upon that final review. Deliverobles r Revised draft of sea level rise analysis document incorporating revisions to address Ecology comments. Estimated Cost: 57,800 Task 6 - Review of City Code Changes (October/November) Following the City Council briefing in September, the City will prepare a proposed response, including recommended code revisions by October L5,2O2O. The consultant will review the City's proposed code changes for consistency with the best available science document produced in an earlier task. Recommendations for modifications will be made through a single written correspondence within two weeks of receipt of the proposed changes. Cascodio Consulting Group, lnc. P rofess i o n a I Se ruice Ag ree me nt 2 August 2020 Contract Amendment #L Assumptions o One round of review and recommendations regarding the City's proposed code changes. . The summary of the consultant's review will be in writing; a discussion meeting is not currently included in the proposed estimated hours. Deliverables o Recommendations for modifications will be sent in writing within two weeks of receipt of the proposed changes. Estimated Cost: 52,500 Christy Shelton, Principal Cascadia Consulting Group, lnc. Robert Putaa nsuu,Mayor City of Port Orchard Coscadia Consulting Group, lnc. P rofess io no I Se rv ice Ag ree me nt 3 August 2020 Contract Amendment #L