WHEREAS, the City of Port Orchard adopted the revised Shoreline Master Program in
1994 to regulate the property within the jurisdiction of that program, and
WHEREAS, the applicant submitted a Substantial Development Permit Application on
December 31, 1998 to construct a 46 stall parking lot across from 201 Bay Street to supplement the
parking capacity of the Port Orchard Yacht Club, and
WHEREAS, this project has received a Determination of Non -Significance by the City of
Port Orchard, and
WHEREAS, a public hearing was held on March 8, 1999 by the City Council to hear facts
and testimony concerning granting a Substantial Development Permit, and
WHEREAS, the City Council did determine that the granting of the Substantial
Development Permit is consistent with the intent of the Shoreline Management Program, and
WHEREAS, the City Council held another public hearing on December 27, 1999 to allow
public input on a request to modify the parking lot lighting depicted on the site plan approved under
Resolution No. 1853; and
WHEREAS, after closing the public hearing the City Council did approve modification of
the lighting for a parking lot site plan at 680 Grant; (note: approval of this modification does not change
any condition set forth in Resolution No. 1853, restated as follows), now therefore,
THE COUNCIL OF THE CITY OF PORT ORCHARD DOES RESOLVE AS FOLLOWS:
The City of Port Orchard issues a Substantial Development Permit to Mr. Mike Petrowske
for the construction of a parking lot in the 200 block of Bay Street, not to exceed 46 parking stalls, subject
to the following conditions:
1. Prior to commencement of work, a grading or excavation permit
shall be issued by the City of Port Orchard.
2. Before excavation or grading commences, the developer will
install filter fabric fencing and rock approaches to minimize
erosion and sedimentation. These measures will be in
accordance with City requirements and will be maintained until
the lot is paved or re -vegetated
3. Prior to the issuance of an excavation or grading permit, the
applicant shall provide a written description of the maintenance
practices and schedule for the stormwater system. These
maintenance practices and schedule are subject to approval by
Resolution No. 1883
Page 2 of 2
the City Engineer.
4. No work is allowed in the right of way, unless specifically
approved by the City Engineer.
Landscaping shall be in accordance with the current Zoning
Ordinance and shall consist primarily of native vegetation.
Landscape and irrigation plans shall be submitted for review and
approval prior to issuance of the grading and excavation permit.
The landscaping shall be installed prior to the use of the parking
lot.
6. Parking at this property is restricted to the Port Orchard Yacht
Club and shall not be used as a commercial parking lot.
Any parking lot illumination shall be directed away from the
adjacent properties and Sinclair Inlet.
PASSED by the City Council of the City of Port Orchard, APPROVED by the Mayor and
attested by the Clerk in authentication of such passage this 10`h day of January 2000.
LESLIE J. WEATHERILL, MAYOR
ATTEST:
Patricia Parks, City Clerk