080-18 - Viking Fence Co. - Supplement / Change Order 1Date:
Project:
Contract / Job #
CITY OF PORT ORCHARD
Authorization for Change Order No. 1
January 16, 2019 _
Fence Repair at 1025 Tacoma
Ave — Active Club
C080-18
Contractor: Viking Fence Co
3450 State Hwy 3
Bremerton, WA 98312
THIS CHANGE ORDER AUTHORIZES TIME EXTENSION ONLY. WORK TO BE COMPLETED BY APRIL 30TH
2019.
Contract History
Amount Sales Tax Total Date Appvd b
Original Contract
$11,179.78
$1,006.18
$12,185.96
11-Dec-18
COUNCIL
Change Order 1
$0.00
$0.00
$0.00
16-Jan-19
PW DIRECTOR
Total Contract $0.00 $1,006.18 $12,185.96
I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
costs are true and accurate.
Contr for Approval Signature Public VNIQLks Dire City Engineer
JUnV�SE�V'�{e�re.�rea((rCr MARKR, DORSEY, P.E.
Printed Name & Title) 4 Printed Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract Approved:
amount established by City Council can be approved by the Public
Works Director.
Change Orders that do not exceed 10%, with a maximum of Attest'
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10` o require
Council Action.
Mayor
City Clerk
Council Approval Date
U 9ENGINEERING10TY FACILITIES\Active Club and ballfields12018 FENCE REPAIR1Viking Fence\Change Order 1_Vking Fence_1025 Tacoma Ave doc
Page 1