081-18 - Julie's Construction Striping, LLC - Supplement / Change Order 1CITY OF PORT ORCHARD Authorization for Change Order No. 1 Date: JANUARY 17, 2019 Project: THERMOPLASTIC APPLICATION Contract / Job # C081-18 Contractor: JULIES CONSTURCTION STRIPING PO BOX 962 MCKENNA, WA 98558 THIS CHANGE ORDER AUTHORIZES A TIME EXTENSION ONLY. CONTRACT END DATE IS NOW FEBRUARY 28TH 2019. Contract History illL Amount Sales Tax Total Date A vd b Original Contract $9,912.00 S0.00 $9,912.00 30-Nov-18 PW DIRECTOR Change Order 1 S0.00 S0.00 $0.00 17-Jan-19 PW DIRECTOR Total Contract $0.00 $0.00 $9,912.00 I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and costs are true and accurate. ntractor Approval Sig r ture Printed Name & Tit[O Public orks Director/ ' Engineer MARK R. DORSEY, P.E. Printed Name Change Orders that do not exceed 10%, with a maximum of $50,000, of either legally authorized budget limit or contract Approved: amount established by City Council can be approved by the Public Works Director. Change Orders that do not exceed 10%, with a maximum of Attest: $100,000, of either legally authorized budget limit or contract amount established by City Council are to be approved by the Mayor. Change Orders over $100,000 or exceed a total of 10% require Council Action. Mayor City Clerk Council Approval Date U:%ENGINEERINGISTREET1Thermoplasic120181110520181,ulies ConstruchonlChange Order 1_Thennoplasac Applications_ Julies Construction Striping doc Page 1