081-18 - Julie's Construction Striping, LLC - Supplement / Change Order 2CITY OF PORT ORCHARD
Authorization for Change Order No. 2
Date: FEBRUARY 28, 2019
Project: THERMOPLASTIC APPLICATION
Contract / Job # C081-18
Contractor: JULIES CONSTURCTION STRIPING
PO BOX 962
MCKENNA, WA 98558
THIS CHANGE ORDER AUTHORIZES A TIME EXTENSION ONLY. CONTRACT END DATE IS NOW FEBRUARY
APRIL 1ST" 2019.
Amnunt
Contract History
Salac Tnv
Original Contract
Chan a Order 1
Change Order 2
$9 912.00
$0.00
$0.00
$0.00
$0.00
$0.00
$9 912.00
$0.00
$0.00
30-Nov-18
17-Jan-19
28-Feb-19
PW DIRECTOR
PW DIRECTOR
PW DIRECTOR
[Total Contract $0.00
$0.00 $9,912.00
I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
costs are true and accurate.
�Cttractor Approval Si nature'
Printed Name & Ti e
.tr .
Pul)fii Works Director/City Engineer
MARK R. DORSEY, P.E.
Printed Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract Approved:
amount established by City Council can be approved by the Public
Works Director.
Change Orders that do not exceed 10%, with a maximum of Attest:
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action.