09/15/2017 - Tremont Street Widening Project Update
PUBLIC NOTICE
Tremont Street Widening Project Update
PORT ORCHARD, WA – As all in the community are aware, the Tremont Widening Project has begun. The initial clearing is nearing completion. Beginning next week, the first phase of traffic
control will be in place. Traffic lanes will be reduced to one lane in each direction through the entire project area. Temporary striping will be placed. The lanes will be shifted to
the north side of the street to allow the contractor’s crews to safely work on the south side. Access to all homes and businesses will remain. There should be less flagging to stop traffic
as there has been for the beginning of the project. This phase of traffic control is planned to be in place until sometime next spring.
In an effort to improve safety, we will be reducing the speed limit through this area to 25 mph.
Additional information on the project can always be found on the City’s website www.cityofportorchard.us and clicking on the Tremont Street Widening Project Information bar at the top
of the page.
###
Press Release: Website Photos
Page 2 of 2
City of Port Orchard
City Clerk’s Office
216 Prospect Street, Port Orchard, WA 98366
Voice: (360) 876-4407 ( Fax: (360) 895-9029
cityclerk@cityofportorchard.us
www.cityofportorchard.us