056-21 - Aqua Tech LLC - Supplement / Change Order 1II CITY OF PORT ORCHARD Authorization for Change Order No. 1 Date: August 12, 2021 Contractor: Aqua Tech LLC Project: Cedar Heights Lift Station 111 Sparrow Court Valving & Piping Replacement Port Ludlow, WA 98365 Contract / Job # C056-21 This Change Order Authorizes a contract time extension only due to shipping delays in acquiring needed materials to complete the contracted work. C056-21 shall be extended to December 31, 2021. Amount Contract History Sales Tax Total Date Appvcl b Original Contract $28,500.00 $2,565.00 $31,065.00 08-Jun-21 Mayor Change Order 1 $0.00 $0.00 $0.00 12-Au -21 Pw DIRECTOR Total Contract $28,500.00 $2,565.00 $31,065.00 I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and costs are true and accurate. Contractor Approval Signature Robert Thurston / Owner Printed Name & Title Public or/City Engineer MARK R. DORSEY, P.E. Printed Name Change Orders that do not exceed 10%, with a maximum of $50,000, of either legally authorized budget limit or contract Approved: amount established by City Council can be approved by the Public Works Director. Change Orders that do not exceed 10%, with a maximum of Attest: $100,000, of either legally authorized budget limit or contract amount established by City Council are to be approved by the Mayor. Change Orders over $100,000 or exceed a total of 10% require Council Action. Page 1 Mayor City Clerk Council Approval Date