008-19 - Neptune Marine, LLC - Supplement / Change Order 2Authorization for Change Order No. 2
Date: Mav 30. 2019
Rockwell Pocket Park
Project: improvements
Contract / Job # C008-19
Contractor: Neptune Marine LLC
------------
1004 Commercial Ave. 250
Anacortes, WA 98221
THIS CHANGE ORDER AUTHORIZES THE ADDITIONAL WORK: THE INSTALLATION OF EXTRUDED CURB IN
LIEU OF CONCRETE TRAFFIC CURB.
I have reviewed the Change Order information above and certify that to the best of my knowledge descriptions and
costs are true and accurate.
177
Contractor Approval Signature Publ C
ity Engineer
T MARK R. DORSEY P.E.
Printed Name & Title Printed Name
Change Orders that do not exceed 10%, with a maximum of
$50,000, of either legally authorized budget limit or contract Approved-,
amount established by City Council can be approved by the Public Mayor
Works Director,
Change Orders that do not exceed 10%, with a maximum of Attest
$100,000, of either legally authorized budget limit or contract
amount established by City Council are to be approved by the City Clerk
Mayor.
Change Orders over $100,000 or exceed a total of 10% require
Council Action.
Council Approval Date
WENGINEERINGWARKS - LANDSCAPEIPARKSIPOB VVTF Park Expansion & Rockwell Park\Rockwell Park\Admin\Final Design & Construction Phase\RP - CACMIChange OrderslCO-
021Neptune Change Order #2 - RP.docx Page 1
CONTRACT CHANGE ORDER (CCO) NO. 2
Project Name: Rockwell Pocket Park Improvement Project
Date: 05/30/2019
To: Neptune Marine LLC
1004 Commercial Ave. 250
Anacortes, WA 98221
Attention: Travis Crabb
Ordered by Engineer under terms of Section
1-04.4 of the Standard Specifications
X Change proposed by Contractor
JUSTIFICATION
The contractor proposed the change to install extruded curb in lieu of the designed concrete traffic curb
as a cost savings and the ease of construction.
DESCRIPTION CIF WORK
The replacement of proposed concrete traffic curb with extruded curb,
MEASUREMENT AND PAYMENT
The proposed change reduces the unit price of the concrete traffic curb (line item 26) to $17.00 per linear
foot from $37.50 per linear foot and increases the bid quantity to 213 linear feet from 135 linear feet.
TIME
No additional days are associated with this change order,
ORIGINAL CURRENT EST. NET CHANGE TOTAL CHANGE ORDERS, EST. CONTRACT AFTER
CONTRACT CONTRACT THIS CHANGE ORDER_ INCLUDING THIS ONE THIS CHANGE ORDER
$412.848.67 $424w228.27-$1,571,24 $9,808.36 $422 657.04
DAYS 120 DAYS: 0 DAYS: 0 DAYS: 120
All work, materials and measurements to be in accordance with the provisions of the original contract and/or the standard specifications and
special provisions for the type of construction involved. The payments and/or additional time specified and agreed to in this order include every
claim by the Contractor for any extra payment or extension of time with respect to the work described herein, including delays to the overall
project.
Change Order#2
1 of 2
Attachment: Neptune Proposal
Change Order #2
2of2
Ian Smith
From: Travis Crabb <Travis@neptunemarine.biz>
Sent: Thursday, May 2, 2019 7:SS AM
To: Ian Smith; Mark Dorsey
Cc: Levi Nicholl
Subject: Rockwell Extruded Curb
HI Ian,
If we want to use extruded Curb at Rockwell, Neptune/Curbmaster can provide curb for 17.00 a LF
Thanks,
Travis Crabb